Construction of a Secondary

Boundary Fence and New Sections

of Primary Boundary Fence and

Boundary Patrol Road

 

Environmental Impact Assessment

(Final)

Report No.: 216727/08/02/E

January 2009

 

 

in association with

 

ADI Limited

Archaeological Assessments

Mott MacDonald Hong Kong Ltd

7th Floor, West Wing Office Building

New World Centre

20 Salisbury Road

Tsim Sha Tsui, Kowloon

Hong Kong

 

Tel: 2828 5757

 

Fax: 2827 1823

 

Anne.Kerr@mottmac.com.hk

 

This document has been prepared for the titled project or named part thereof and should not be relied upon or used for any other project without an independent check being carried out as to its suitability and prior written authority of Mott MacDonald being obtained.  Mott MacDonald accepts no responsibility or liability for the consequence of this document being used for a purpose other than the purposes for which it was commissioned.  Any person using or relying on the document for such other purpose agrees, and will by such use or reliance be taken to confirm his agreement to indemnify Mott MacDonald for all loss or damage resulting therefrom.  Mott MacDonald accepts no responsibility or liability for this document to any party other than the person by whom it was commissioned.

 

To the extent that this report is based on information supplied by other parties, [Mott MacDonald] accepts no liability for any loss or damage suffered by the client, whether contractual or tortious, stemming from any conclusions based on data supplied by parties other than Mott MacDonald and used by Mott MacDonald in preparing this report.

 

 


List of Contents Page

Chapters                                                                                                                                           

1        INTRODUCTION   1-1

1.1      Background  1-1

1.2      The Project 1-1

1.3      EIAO and Designated Projects  1-1

1.4      Scope  1-1

1.5      Need for the Project and Consequences of not Proceeding with the Project 1-3

1.6      Consideration of Alternative Alignment 1-3

1.7      Alternative / Preferred Construction Methods and Sequence of Works  1-4

1.8      Interface with Concurrent Projects  1-4

1.9      Objectives of the EIA Study  1-5

1.10    The Assessment Area  1-6

1.11    Programme  1-6

1.12    Structure of the EIA Report 1-6

2        Air Quality   2-1

2.1      Introduction  2-1

2.2      Legislation, Standards, Guidelines and Criteria  2-1

2.3      Baseline Conditions and Air Sensitive Receivers  2-2

2.4      Identification and Evaluation of Air Quality Impact 2-4

2.5      Mitigation Measures  2-5

2.6      Potential Concurrent Projects  2-6

2.7      Environmental Monitoring and Audit 2-6

2.8      Conclusion  2-6

3        NOISE IMPACT   3-1

3.1      Introduction  3-1

3.2      Relevant Legislations, Standards & Guidelines  3-1

3.3      Study Area and Construction Programme  3-3

3.4      Noise Sensitive Uses  3-3

3.5      Assessment Approach & Methodology  3-6

3.6      Analysis of Construction Activities and Sources of Noise Impact 3-7

3.7      Unmitigated Construction Noise Impacts  3-7

3.8      Possible Noise Mitigation Measures and Mitigated Impacts  3-7

3.9      Operation Phase Noise Impact Assessment 3-7

3.10    Environmental Monitoring and Audit (EM&A) Requirements  3-7

3.11    Conclusion  3-7

4        WATER QUALITY IMPACT   4-7

4.1      Introduction  4-7

4.2      Environmental Legislation, Standards, Guidelines and Criteria  4-7

4.3      Assessment Methodology  4-7

4.4      Baseline Conditions  4-7

4.5      Water Sensitive Receivers  4-7

4.6      Impact Assessment 4-7

4.7      Mitigation of Impacts  4-7

4.8      Environmental Monitoring and Audit 4-7

4.9      Conclusions  4-7

4.10    References  4-7

5        WASTE MANAGEMENT IMplications   5-7

5.1      Introduction  5-7

5.2      Environmental Legislation and Standards  5-7

5.3      Assessment Methodology  5-7

5.4      Construction Waste Impact 5-7

5.5      Evaluation of Impacts  5-7

5.6      Mitigation Measures  5-7

5.7      Land Contamination  5-7

5.8      Environmental Monitoring and Audit Requirements  5-7

5.9      Conclusions  5-7

6        Ecological Impact assessment   6-7

6.1      Introduction  6-7

6.2      Assessment Area  6-7

6.3      Sites of Conservation Importance in the Area  6-7

6.4      Ecological Baseline  6-7

6.5      Ecological Value of Project Area / habitats within the Assessment Area  6-7

6.6      Potential Ecological Impacts  6-7

6.7      Cumulative Impact 6-7

6.8      Residual Impact 6-7

6.9      Environmental Monitoring and Audit Requirements  6-7

6.10    Conclusions  6-7

6.11    References  6-7

7        Landscape and Visual Impact   7-7

7.1      Introduction  7-7

7.2      Environmental Legislation, Standards, Guidelines and Criteria  7-7

7.3      Assessment Methodology  7-7

7.4      Project Description  7-7

7.5      Review of Planning and Development Control Framework  7-7

7.6      Landscape and Visual Baseline Study  7-7

7.7      Existing Visual Context 7-7

7.8      Landscape Impact Assessment 7-7

7.9      Visual Impact Assessment 7-7

7.10    Cumulative Impacts  7-7

7.11    Recommended Mitigation Measures  7-7

7.12    Programme for Landscape Works  7-7

7.13    Conclusion  7-7

8        CULTURAL HERITAGE  8-7

8.1      Introduction  8-7

8.2      Environmental Legislation and Standards  8-7

8.3      Methodology  8-7

8.4      Results of the Desk-Based Assessment 8-7

8.5      Findings of Assessment 8-7

8.6      Impact Assessment 8-7

8.7      Mitigation Recommendations  8-7

8.8      Conclusion  8-7

8.9      References  8-7

9        SUMMARY OF ENVIRONMENTAL OUTCOMES   9-7

9.1      Overall 9-7

9.2      Air Quality  9-7

9.3      Noise  9-7

9.4      Water Quality  9-7

9.5      Waste Management 9-7

9.6      Ecology  9-7

9.7      Landscape and Visual 9-7

9.8      Cultural Heritage  9-7

10      ENVIRONMENTAL MONITORING AND AUDIT (EM&A) REQUIREMENTS   10-7

10.2    Air Quality  10-7

10.3    Noise Impact 10-7

10.4    Water Quality  10-7

10.5    Waste Management 10-7

10.6    Ecology  10-7

10.7    Landscape and Visual 10-7

10.8    Cultural Heritage  10-7

11      PROJECT IMPLEMENTATION SCHEDULE  11-7

12      SUMMARY AND CONCLUSIONS   12-7

12.1    Summary  12-7

12.2    Conclusions  12-7

 

List of Tables

 

Table 2‑1       Hong Kong Air Quality Objectives (mg/m3)(i) 2-2

Table 2‑2       Annual Average Background Air Quality (2003 – 2007) 2-3

Table 2‑3       Representative Air Sensitive Receivers  2-3

Table 3‑1       Noise Standards for Daytime Construction Activities  3-1

Table 3‑2       EIAO-TM Road Traffic Noise Criteria  3-2

Table 3‑3       Locations of the Existing Representative NSRs for Construction of Boundary Fence/ Road Construction/ Check Point Superstructure  3-4

Table 3‑4       Locations of the Existing Representative NSRs for Demolition of Exsiting Boundary Fence  3-5

Table 3‑5       Location of Existing Representative NSRs for Demolition of Check Points  3-5

Table 3‑6       Location of Planned NSR for Demolition of Existing Boundary Fence  3-6

Table 3‑7       Tentative Construction/ Demolition Activities for All Sections  3-7

Table 3‑8       Tentative Construction Plant List for Construction of Boundary Fence/ Road Construction/ Check Point Superstructure  3-7

Table 3‑9       Tentative Construction Plant Lists for Demolition of Existing Boundary Fence and Check Points  3-7

Table 3‑10     Maximum SWL of Each Activity for Construction Noise Impact Assessment 3-7

Table 3‑11     Construction Noise Impacts apart from Demolition of Existing Boundary Fence and Check Point to the NSRs  3-7

Table 3‑12     Unmitigated Noise Impact due to the Construction of Boundary Fence/ Road Construction/ Check Point Superstructure  3-7

Table 3‑13     Unmitigated Noise Impact due to the Demolition of Existing Boundary Fence  3-7

Table 3‑14     Unmitigated Noise Impact due to the Demolition of Check Points  3-7

Table 3‑15     Recommended Quiet PME and the SWL  3-7

Table 3‑16     Maximum SWLs of Plant Inventory with Mitigation Measures Implemented  3-7

Table 3‑17     Mitigated Noise Impact due to the Construction of Boundary Fence/ Road Construction/ Check Point Superstructure (Level 1) 3-7

Table 3‑18     Mitigated Noise Impact due to the Demolition of Existing Boundary Fence (Level 1) 3-7

Table 3‑19     Mitigated Noise Impact due to the Demolition of Check Points (Level 1) 3-7

Table 3‑20     Sensitivity Test for Minimum Separation Distance  3-7

Table 3‑21     Mitigated Noise Impact due to the Demolition of Existing Boundary Fence (Level 2) 3-7

Table 3‑22     Construction Noise Impact Assessment for WWF  3-7

Table 5‑1       Reviewed Historical Aerial Photographs and Land Use in the Land Requirement Limit 5-7

Table 6‑1       Habitats present in Assessment Area  6-7

Table 6‑2       Habitats present in Project Area  6-7

Table 6‑3       Mean of individuals of bird species of conservation concern and wetland-dependent bird species recorded during transect survey in Section 1 Assessment Area, Nov 2007 - Oct 2008. (Level of Concern based on Fellowes et al. 2002) 6-7

Table 6‑4       Wetland-dependent bird species recorded in the Tam Kon Chau, Mai Po San Tsuen, San Tin and Shenzhen River A count area on monthly waterbird counts conducted by the Hong Kong Bird Watching Society, April 2003 - March2008 (data from Anon 2008, Anon 2007a, Anon 2007b, Anon 2006a, Anon 2006b, Anon 2005a, Anon 2005b, Anon 2004a, Yu 2004 and Yu 2003) 6-7

Table 6‑5       Summary of Tam Kon Chau Egretry 2003-2007 (data from Anon 2007c, Anon 2006c, Anon 2005c, Anon 2004b and Wong 2003) 6-7

Table 6‑6       Relative abundance of herpetofauna species recorded in Section 1  6-7

Table 6‑7       Odonata species recorded in Section 1  6-7

Table 6‑8       Butterfly species recorded in Section 1  6-7

Table 6‑9       Mean of individuals of bird species of conservation concern and wetland-dependent bird species recorded during transect survey in section 2 Assessment Area, Nov 2007 - Oct 2008. (Level of Concern based on Fellowes et al. 2002) 6-7

Table 6‑10     Wetland-dependent bird species recorded in the Shenzhen River B count area on monthly waterbird counts conducted by the Hong Kong Bird Watching Society, April 2003 - March2008 (Data from Anon 2008, Anon 2007a, Anon 2007b, Anon 2006a, Anon 2006b, Anon 2005a, Anon 2005b, Anon 2004a, Yu 2004 and Yu 2003) 6-7

Table 6‑11     Relative abundance of herpetofauna species recorded in Section 2  6-7

Table 6‑12     Odonata species recorded in Section 2  6-7

Table 6‑13     Butterfly species recorded in Section 2  6-7

Table 6‑14     Freshwater fish species recorded in Section 2  6-7

Table 6‑15     Mean of individuals of bird species of conservation concern and wetland-dependent bird species recorded during transect survey in Section 3 Assessment Area, Nov 2007- Oct 2008. (Level of Concern based on Fellowes et al. 2002) 6-7

Table 6‑16     Record of conservation concerned species and woodland specialist at Lin Ma Hang fung shui wood and secondary woodland in the pilot biodiversity study conducted by Kadoorie Fam and Botanic Garden. (Data from Kadoorie Farm and Botanic Garden 2004; Level of Concern based on Fellowes et al. 2002) 6-7

Table 6‑17     Herpetofauna recorded in Section 3  6-7

Table 6‑18     Odonata species recorded in Section 3  6-7

Table 6‑19     Butterfly species recorded in Section 3  6-7

Table 6‑20     Aquatic fauna species recorded in Section 3  6-7

Table 6‑21     Mean of individuals of bird species of conservation concern and wetland-dependent bird species recorded during transect survey in Section 4 Assessment Area, Nov 2007- Oct 2008. (Level of Concern based on Fellowes et al. 2002) 6-7

Table 6‑22     Herpetofauna recorded in Section 4  6-7

Table 6‑23     Odonata species recorded in Section 4  6-7

Table 6‑24     Butterfly species recorded in Section 4  6-7

Table 6‑25     Ecological Evaluation of Project Area in Section 1  6-7

Table 6‑26     Ecological Evaluation of Project Area at Red Alignment in Section 2  6-7

Table 6‑27     Ecological Evaluation of Project Area at Blue and Green Alignments in Section 2  6-7

Table 6‑28     Ecological Evaluation of Project Area at Red Alignment in Section 3  6-7

Table 6‑29     Ecological Evaluation of Project Area at Blue and Green Alignments in Section 3  6-7

Table 6‑30     Ecological Evaluation of Project Area in Section 4  6-7

Table 6‑31     Potential Ecological Impacts of Habitat Loss at Section 1 and 2  6-7

Table 6‑32     Potential Ecological Impacts of Habitat Loss at Section 3 and 4  6-7

Table 6‑33     Potential Ecological Impacts of Ecological Barrier on Section 1, Blue Alignments of Section 2 and Section 4  6-7

Table 6‑34     Potential Ecological Impacts of Ecological Barrier on Red and Green Alignments of Section 2  6-7

Table 6‑35     Potential Ecological Impacts of Ecological Barrier on Blue Alignment of Section 3  6-7

Table 6‑36     Potential Ecological Impacts of Ecological Barrier on Red and Green Alignments of Section 3  6-7

Table 6‑37     Ecological Evaluation of Floral Species within Proposed Project Area  6-7

Table 6‑38     Potential Ecological Impacts on Floral Species of Conservation Concern  6-7

Table 6‑39     Potential Ecological Impacts on Fauna Species of Conservation Concern  6-7

Table 6‑40     Potential Ecological Impacts on Offsite Habitats  6-7

Table 6‑41     Potential Ecological Impacts on Offsite Disturbance to Mammals of Conservation Concern  6-7

Table 6‑42     Potential disturbance Impacts to wetland-dependent birds of conservation concern in Assessment Area. 6-7

Table 6‑43     Potential Disturbance Impacts to raptors of conservation concern in Assessment Area. 6-7

Table 6‑44     Potential Disturbance Impacts to terrestrial birds of conservation concern in Assessment Area. 6-7

Table 6‑45     Potential Ecological Impacts to Tam Kon Chau Egretry. 6-7

Table 7‑1       Degree of Impact 7-7

Table 7‑2       Residual Impact Significance Threshold Matrix  7-7

Table 7‑3       Review of Existing Planning and Development Control Framework  7-7

Table 7‑4       Landscape Resources and their Sensitivity to Change  7-7

Table 7‑5       Landscape Character Areas and their Sensitivity to Change  7-7

Table 7‑6       Visually Sensitive Receivers (VSRs) and their Sensitivity to Change  7-7

Table 7‑7       Magnitude of Change for Landscape Resources  7-7

Table 7‑8       Magnitude of Change for Landscape Character Areas  7-7

Table 7‑9       Significance of Impacts on Landscape Resources in the Construction and Operational Phases  7-7

Table 7‑10     Significance of Impacts on Landscape Character Areas in the Construction and Operational Phases  7-7

Table 7‑11     Magnitude of Change for Visually Sensitive Receivers  7-7

Table 7‑12     Significance of Impacts on Visually Sensitive Receivers in the Construction and Operational Phases  7-7

Table 7‑13     Proposed Construction Phase Mitigation Measures  7-7

Table 7‑14     Proposed Operational Phase Mitigation Measures  7-7

 

Appendices

 

Appendix A          Tentative Construction Programme

Appendix B           Typical Cross Sections of Proposed PBF, SBF, BPR and Checkpoints

Appendix C           Construction Noise Impact

Appendix D           (Not Used)

Appendix E           Waste Management

Appendix F           Ecology

Appendix G           (Not Used)

Appendix H           Cultural Heritage

 

 

 

List of Figures

 

Figure 1.1               General Layout Plan

Figure 2.1               Study Area for Air Quality Impact Assessment

Figure 2.2               Air Sensitive Receivers for Section 1

Figure 2.2a             Air Sensitive Receivers for Section 1

Figure 2.2b            Air Sensitive Receivers for Section 1

Figure 2.3               Air Sensitive Receivers for Section 2

Figure 2.3a             Air Sensitive Receivers for Section 2

Figure 2.3b            Air Sensitive Receivers for Section 2

Figure 2.3c             Air Sensitive Receivers for Section 2

Figure 2.3d            Air Sensitive Receivers for Section 2

Figure 2.4               Air Sensitive Receivers for Section 3

Figure 2.4a             Air Sensitive Receivers for Section 3

Figure 2.4b            Air Sensitive Receivers for Section 3

Figure 2.4c             Air Sensitive Receivers for Section 3

Figure 2.4d            Air Sensitive Receivers for Section 3

Figure 2.4e             Air Sensitive Receivers for Section 3

Figure 2.4f             Air Sensitive Receivers for Section 3

Figure 2.4g            Air Sensitive Receivers for Section 3

Figure 2.5               Air Sensitive Receivers for Section 4

Figure 2.5a             Air Sensitive Receivers for Section 4

Figure 3.1               Study Area for Noise Impact Assessment

Figure 3.2               Location of Noise Sensitive Receivers (Sheet 1 of 7)

Figure 3.3               Location of Noise Sensitive Receivers (Sheet 2 of 7)

Figure 3.4               Location of Noise Sensitive Receivers (Sheet 3 of 7)

Figure 3.5               Location of Noise Sensitive Receivers (Sheet 4 of 7)

Figure 3.6               Location of Noise Sensitive Receivers (Sheet 5 of 7)

Figure 3.7               Location of Noise Sensitive Receivers (Sheet 6 of 7)

Figure 3.8               Location of Noise Sensitive Receivers (Sheet 7 of 7)

Figure 3.9               Photos of Existing Noise Sensitive Receivers (Sheet 1 of 2)

Figure 3.10             Photos of Existing Noise Sensitive Receivers (Sheet 2 of 2)

Figure 3.11             Typical Section of Movable Noise Barrier

Figure 6.1               Assessment Area and Sites of Conservation Interest

Figure 6.2               Habitat Map

Figure 6.3               Habitat Map and Species of Conservation

Figure 6.4               Habitat Map and Species of Conservation

Figure 6.5               Habitat Map and Species of Conservation

Figure 6.6               Habitat Map and Species of Conservation

Figure 6.7               Habitat Map and Species of Conservation

Figure 6.8               Habitat Map and Species of Conservation

Figure 6.9               Habitat Map and Species of Conservation

Figure 7.1               Review of Planning and Development Control Framework

Figure 7.2A           Landscape Resources

Figure 7.2B            Landscape Resources

Figure 7.2C            Landscape Resources

Figure 7.2D            Landscape Resources

Figure 7.2E            Landscape Resources

Figure 7.2F            Landscape Resources

Figure 7.2G            Landscape Resources

Figure 7.2H            Landscape Resources

Figure 7.3A           Landscape Character Areas and Impacts

Figure 7.3B            Landscape Character Areas and Impacts

Figure 7.3C            Landscape Character Areas and Impacts

Figure 7.3D            Landscape Character Areas and Impacts

Figure 7.4A           Landscape Character Areas Photographs

Figure 7.4B            Landscape Character Areas Photographs

Figure 7.4C            Landscape Character Areas Photographs

Figure 7.4D            Landscape Character Areas Photographs

Figure 7.4E            Landscape Character Areas Photographs

Figure 7.4F            Landscape Character Areas Photographs

Figure 7.5A           Impacts on Landscape Resources

Figure 7.5B            Impacts on Landscape Resources

Figure 7.5C            Impacts on Landscape Resources

Figure 7.6A           Visual Envelope and Zone of Visual Influence

Figure 7.6B            Visual Envelope and Zone of Visual Influence

Figure 7.6C            Visual Context of Visual Sensitive Receivers

Figure 7.6D            Visual Context of Visual Sensitive Receivers

Figure 7.6E            Visual Context of Visual Sensitive Receivers

Figure 7.6F            Visual Context of Visual Sensitive Receivers

Figure 7.6G            Visual Context of Visual Sensitive Receivers

Figure 7.7A           Visual Impacts

Figure 7.7B            Visual Impacts

Figure 7.8A           Recommended Landscape Mitigation Measures

Figure 7.8B            Recommended Landscape Mitigation Measures

Figure 7.8C            Recommended Landscape Mitigation Measures

Figure 7.8D            Recommended Landscape Mitigation Measures

Figure 7.9A           Photomontages - Vantage Point A

Figure 7.9B            Photomontages - Vantage Point A

Figure 7.9C            Photomontages - Vantage Point B

Figure 7.9D            Photomontages - Vantage Point B

Figure 7.9E            Photomontages - Vantage Point C

Figure 7.9F            Photomontages - Vantage Point C

Figure 7.9G            Photomontages - Vantage Point D

Figure 7.9H            Photomontages - Vantage Point D

Figure 7.9I             Photomontages - Vantage Point E

Figure 7.9J             Photomontages - Vantage Point F

Figure 7.9K            Photomontages - Vantage Point G

Figure 7.9L            Photomontages - Vantage Point H

Figure 7.9M           Photomontages - Vantage Point H

Figure 8.1               Geological map showing the western part of Section 3 (Pak Fu Shan to Lin Ma Hang)

Figure 8.2               Geological map showing the eastern part of Section 3 (Lo Wu to Pak Fu Shan)

Figure 8.3               Geological map showing Sections 1 and 2 (Mai Po to Lo Wu)

Figure 8.4               Geological map showing Section 4 (Sha Tau Kok)        

Figure 8.5               Map showing the locations of known archaeological sites

Figure 8.6               Locations of Shrine (BF-HB1) and Grave (BF-G1) near Liu Pok

Figure 8.7               Location of Grave (BF-G2) on Lin Ma Hang Road

Figure 8.8               Locations of HB-2 and HB-3 at the Abandoned Village near Chuk Yuen

Figure 8.9               Location of BF-BH4 near Kong Ha (Sha Tau Kok)

 


1                        INTRODUCTION

 

1.1                   Background

 

1.1.1              The Frontier Closed Area (FCA) is an integral part of the package of measures for maintaining the integrity of the Hong Kong SAR’s boundary with the Mainland and for combating illegal immigration and other cross-boundary criminal activities.  Following a recent review, the Government has concluded that with the erection of a secondary boundary fence (SBF) along the boundary patrol road (BPR) and construction of new sections of the BPR and primary boundary fence (PBF) at certain sections along the boundary, the FCA coverage can be substantially reduced without affecting the objective of maintaining the integrity of the boundary.  The PBF and SBF will be erected along the northern and southern curbs of the realigned BPR respectively to facilitate the Police in combating cross-boundary criminal activities.  The reduced FCA will comprise a narrow strip of land covering the realigned BPR and areas to its north, together with the points of crossing the boundary (i.e. the Boundary Control Points and Sha Tau Kok town).  Areas south of the SBF will generally be excised from the FCA.

 

1.2                   The Project

 

1.2.1              The Project mainly comprises the construction of an SBF along the southern edge of the existing BPR (approximately 21.7km) from west (Pak Hok Chau) to east (Sha Tau Kok).  For sections where the existing PBF runs along the southern edge of the BPR, a new fence with sensor alarm system will be constructed on the northern edge of the BPR as part of the PBF whereas the existing PBF will become the SBF.  The project also includes the conversion of the existing maintenance services road along the Shenzhen River bank to the north of the Lok Ma Chau Loop and Hoo Hok Wai into a new section of the BPR with a PBF and an SBF; and construction of two new sections of the BPR with a PBF and an SBF along the Shenzhen River side to the north of Pak Fu Shan and northwest of Lin Ma Hang Village.  In addition, the Project includes the construction of a checkpoint at the entrance to the Sha Tau Kok town (i.e. location of “Gate One”) and replacement of the existing checkpoint at Pak Hok Chau, removal of the existing checkpoints at Lok Ma Chau, Sha Ling, Ping Che and Shek Chung Au, and removal of the existing PBF along those sections of the existing BPR which will be replaced by new sections of the BPR.

 

1.3                   EIAO and Designated Projects

 

1.3.1              The Project is a designated project (DP) under item Q.1, Part I, Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) which reads "All projects including new access roads, railways, sewers, sewage treatment facilities, earthworks, dredging works and other building works partly or wholly in an existing or gazetted proposed country park or special area, a conservation area, an existing or gazetted proposed marine park or marine reserve, a site of cultural heritage, and a site of special scientific interest."

 

1.4                   Scope

 

1.4.1              The entire length of the Project is about 21.7km from west of Pak Hok Chau to east of Sha Tau Kok and is divided into four sections as shown in Figure 1.1.  The project scope of each section is described below.

 

Section 1 – Mai Po to Lok Ma Chau Control Point

 

(i)     To erect an SBF along the existing BPR (approximately 4.1km); and

 

(ii)    To replace the existing checkpoint at Pak Hok Chau.

 

Section 2 – Lok Ma Chau Control Point to Ng Tung River

 

(i)     To convert the maintenance services road of Drainage Services Department along the Shenzhen River bank to the north of the Lok Ma Chau Loop and Hoo Hok Wai into a new section of the BPR (approximately 5.6km);

 

(ii)    To erect a new PBF with the sensor alarm system and an SBF respectively along the northern and southern side of the converted road;

 

(iii)   To remove the original PBF and the sensor alarm system thereon along the existing BPR south of the Lok Ma Chau Loop and Hoo Hok Wai; and

 

(iv)   To remove the existing checkpoint at Lok Ma Chau Road.

 

Section 3 – Ng Tung River to Lin Ma Hang Village

 

(i)     To erect an SBF along the existing BPR except the sections to the north of Pak Fu Shan and northwest of Lin Ma Hang Village (approximately 7.5km); 

 

(ii)    To construct new sections of the BPR along the Shenzhen River side to the north of Pak Fu Shan and northwest of Lin Ma Hang Village without necessitating river training (approximately 4.0km);

 

(iii)   To erect a new PBF with the sensor alarm system and an SBF along the northern and southern sides of the new sections of BPR respectively;

 

(iv)   To remove the original PBF and the sensor alarm system thereon along the existing BPR near Pak Fu Shan and Lin Ma Hang Village; and

 

(v)    To remove the existing checkpoints at Sha Ling and Ping Che.

 

Section 4 – Lin Ma Hang Village to Sha Tau Kok

 

(i)     To erect an SBF from the entrance of the Sha Tau Kok town (i.e. the location of “Gate One”) to the Sha Tau Kok Control Point (approximately 0.5km);

 

(ii)    To provide a new checkpoint at “Gate One”; and

 

(iii)       To remove the existing checkpoint at Shek Chung Au.

 

 

1.4.2              Typical cross sections of the proposed PBF, SBF, BPR and checkpoint are presented in Appendix B.

 

1.4.3              Apart from normal boundary patrol operation conducted by the Police, no significant operational or decommissioning activities would be involved in association with the proposed SBF, PBF and BPR.

 

1.4.4              Security Bureau is the project proponent, Police is the end-user of the boundary fences and the realigned BPR and Architectural Services Department is the works agent responsible for the management, planning, design and implementation of the Project.

 

1.5                   Need for the Project and Consequences of not Proceeding with the Project

 

1.5.1              While the coverage of the Frontier Closed Area (FCA) will be substantially reduced, it would still be necessary to maintain the integrity and security of the boundary area. The construction of new sections of PBF and SBF is considered to be essential to ensure effective law enforcement to safeguard boundary integrity and security and to prevent and combat illegal immigration and other cross-boundary crimes.

 

1.5.2              Without the implementation, the above purpose cannot be achieved.

 

1.6                   Consideration of Alternative Alignment

 

1.6.1              The alignment generally runs along the southern boundary of the reduced FCA, the coverage of which has taken account of the comments received during the consultation exercise conducted in September to November 2006.

 

1.6.2              For mitigating impacts on important habitats and wildlife in the order of priority of ‘Avoidance, Minimizing, Compensation’, the alignments are proposed along the existing boundary patrol road avoiding the environmentally sensitive areas as far as possible. Other alternatives are considered not feasible as they could only be established by creating new pathways in the adjacent natural habitats. The impacts would be minimized if the alignments stay along the existing boundary patrol road. In addition, mitigation measures have also been considered to minimize the environmental impacts.  For example, special type of footing would be adopted to retain the existing trees if necessary.

 

1.6.3              For Section 2, it was originally proposed in the FCA review to retain all the land north of the existing BPR in the FCA.  This covered about 100 hectares in the Lok Ma Chau Loop and about 300 hectares in the adjacent Hoo Hok Wai.  During the consultation, the local community suggested that these areas should be excluded from the FCA.  After consideration, Government decided to accept the suggestion and reduce the FCA coverage accordingly.  To this end, the existing maintenance road of the Drainage Services Department to the north of the Lok Ma Chau Loop and Hoo Hok Wai will be used as the boundary patrol road, with a primary boundary fence to be constructed along the northern edge of the road and a secondary boundary fence along the southern edge of the road.  To mitigate the environmental impacts, the proposed works would avoid the environmentally sensitive areas, e.g. fish ponds and marshes along Hoo Hok Wai, as far as possible.

 

1.6.4              The alignments to the north of Pak Fu Shan and northwest of Lin Ma Hang Village are originally proposed along the existing boundary patrol road in Section 3.  The relevant Rural Committee requested that two patches of land northwest of Lin Ma Hang and north of Pak Fu Shan be excised from the FCA to release their development potential.  After consideration, the alignment is amended to run along the Shenzhen River bank to the north of the two areas in accordance with the views of the local community.

 

1.6.5              The latest alignment is shown in Figure 1.1.  The alignment along the existing boundary patrol road and new sections of boundary patrol road is denoted in blue and red in Figure 1.1 respectively.

 

1.7                   Alternative / Preferred Construction Methods and Sequence of Works

 

1.7.1              The major construction works of the Project is provision of the secondary and primary boundary fences.  The fences mainly comprise the reinforced concrete footing and the steel fence.  For the reinforced concrete footing, precast footing had been considered to minimize the concreting works on site.  However, it was found that the precast option is not feasible due to the limited road width which hinders the transportation of the precast units.  In addition, the longitudinal and horizontal alignment of the boundary patrol road varies significantly.  Thus, standard precast concrete units cannot be applied and cast-in-situ option is necessary to match the site condition.

 

1.7.2              Apart from the boundary fences, the Project also involves provision of two checkpoints.  Since the size of the proposed Pak Hok Chau Checkpoint is comparatively small, it is proposed to adopt prefabricated house instead of traditional reinforced concrete structure to minimize the environmental impact.

 

1.8                   Interface with Concurrent Projects

 

1.8.1              There are three potential interface projects identified.

 

Liantang/Heung Yuen Wai Boundary Control Point in Section 3

 

1.8.2              A new Boundary Control Point (BCP) is proposed to be constructed at Heung Yuen Wai.  Civil Engineering and Development Department, the works agent of the new BCP, has been informed that the construction of the BPR, the PBF and the SBF in Section 3 not affected by the new BCP will be completed by end 2012.

 

Advance Works for River Training in Section 3

 

1.8.3              In association with the proposed BCP at Heung Yuen Wai, Drainage Service Department (DSD) will carry out advance works for the river training from Ping Yuen River to Pak Fu Shan.  As advised by DSD, the works will commence in mid-2012 and its exact extent could only be confirmed after a study at the end of 2009.  Since the advance works would involve realignment of certain sections of the Shenzhen River, the existing BPR and the existing PBF, it would result in abortive works if the SBF were to be provided along the originally proposed alignment in the affected section.  ArchSD is liaising with DSD on the inclusion of the construction of the affected section of the SBF under DSD’s advance works.  The proposed works from Ping Yuen River to Pak Fu Shan would hence be excised from this Project.  Given that DSD’s advance works are still at a preliminary stage and the realignment of the affected sections of the Shenzhen River, the existing BPR and the existing PBF is subject to DSD’s further study, this EIA Report is done based on the originally proposed alignment of the BPR, PBF and SBF in Section 3 set out in Figure 1.1.

 

Proposed New Wave Wall / Modification to Existing Wave Wall in Section 2

 

1.8.4              The works in Section 2 will have interface with DSD’s proposed modification of the existing wave wall and construction of a new wave wall alongside the Shenzhen River in Section 2.  Liaison with DSD is on-going to resolve the interface issue and the entrustment approach may be adopted.  This EIA Report has already taken into account the potential entrustment of works of the existing wave wall from DSD.

 

1.9                   Objectives of the EIA Study

 

1.9.1              The objectives of the EIA study are as follows:

 

(i)             to describe the Project and associated works together with the requirements for carrying out the Project;

 

(ii)           to identify and describe elements of community and environment likely to be affected by the Project and/or likely to cause adverse impacts to the Project, including natural and man-made environment, and the associated environmental constraints;

 

(iii)          to provide information on the consideration of alternatives to avoid and minimize potential environmental impacts to environmentally sensitive areas and other sensitive uses; to compare the environmental benefits and dis-benefits of each of different options; to provide reasons for selecting the preferred option(s) and to describe the part environmental factors played in the selection of preferred option(s);

 

(iv)         to identify and quantify all environmental sensitive receivers, emission sources and determine the significance of impacts on sensitive receivers and potential affected uses;

 

(v)           to identify and quantify any potential losses or damage to flora, fauna and natural habitats;

 

(vi)         to identify and quantify any potential landscape and visual impacts and to propose measures to mitigate these impacts;

 

(vii)        to identify and quantify any potential archaeological and cultural heritage and propose measures to mitigate these impacts;

 

(viii)      to propose provision of mitigation measures so as to minimize pollution, environmental disturbance and nuisance during construction and operation of Project;

 

(ix)         to investigate the feasibility, practicability, effectiveness and implications of the proposed mitigation measures;

 

(x)           to identify, within the study area, any individual project(s) that fall under Schedule 2 and/or Schedule 3 of the EIAO; to ascertain whether the findings of this EIA study have adequately addressed the environmental impacts of those projects; and where necessary, to identify the outstanding issues that need to be addressed in any further detailed EIA study;

 

(xi)         to identify, predict and evaluate the residual environmental impacts (i.e. after practicable mitigation) and the cumulative effects expected to arise during the construction and operation phases of the Project in relation to sensitive receivers and potential affected uses;

 

(xii)        to identify, assess and specify methods, measures and standards, to be included in the detailed design, construction and operation of the Project which are necessary to mitigate these environmental impacts and cumulative effects and reduce them to acceptable level;

 

(xiii)      to investigate the extent of the secondary environmental impacts that may arise from the proposed mitigation measures and to identify constraints associated with the mitigation measures recommended in the EIA study, as well as the provision of any necessary modification; and

 

(xiv)      to design and specify environmental monitoring and audit requirements to ensure the effective implementation of the recommended environmental protection and pollution control measures.

 

1.10               The Assessment Area

 

1.10.1           The works are mainly located along the existing BPR from west of Pak Hok Chau to east of Sha Tau Kok, the Shenzhen River side at Lok Ma Chau Loop, Hoo Hok Wai, north of Pak Fu Shan and northwest of Lin Ma Hang Village within the FCA.  Access to these areas is controlled by Closed Area Permits issued under Section 37(2) of the Public Order Ordinance.  The location of the fence alignment, the new sections of BPR, the new checkpoint, the four existing checkpoints to be removed and the replacement checkpoint to be constructed are shown in Figure 1.1.

 

1.11               Programme

 

1.11.1           The Project is being planned and designed by the Consultant appointed by ArchSD.  The works will be implemented by the Contractors appointed by ArchSD and the first Construction Contract is expected to be awarded in late 2009.  The construction works are expected to commence in late 2009 for completion in late 2012 subject to the potential adjustment due to the project of Liantang/Heung Yuen Wai Boundary Control point and its advance river training works as described in Sections 1.8.2, 1.8.3 and 1.8.4.  The tentative construction programme is shown in Appendix A.

 

1.12               Structure of the EIA Report

 

1.12.1           The EIA has been prepared to contain all the findings of the Study as follows:

 

·        Section 2 presents the Air Quality Impact Assessment;

·        Section 3 presents the Noise Impact Assessment;

·        Section 4 presents the Water Quality Impact Assessment;

·        Section 5 presents the Waste Management Implications;

·        Section 6 presents the Ecological Impact Assessment;

·        Section 7 presents the Landscape and Visual Impact Assessment;

·        Section 8 presents the Impact on Cultural Heritage;

·        Section 9 provides a summary of the Environmental Outcomes;

·        Section 10 presents the Environmental Monitoring and Audit (EM&A) Requirements;

·        Section 11 presents an Implementation Schedule; and

·        Section 12 presents a summary of the Conclusions of the EIA.


2                        Air Quality

 

2.1                   Introduction

 

2.1.1              This section describes the potential air quality impacts associated with the construction and operation of the proposed secondary boundary fences, new sections of primary and secondary boundary fences and boundary patrol roads as discussed in Section 1.4. The major air emission will be the dust generation from the construction of the boundary fences and patrol roads. During the operation phase, the patrol police cars on the new boundary patrol roads will be subject to the vehicular emission.

 

2.1.2              Representative Air Sensitive Receivers (ASRs) within 500m of the study area have been identified and extended to include off-site air quality impact along the boundary patrol roads. Suitable mitigation measures, where necessary, are recommended to protect the ASRs and to ensure that the legislative criteria are complied with. The study area for the air quality impact assessment is shown in Figure 2-1.

 

2.2                   Legislation, Standards, Guidelines and Criteria

 

2.2.1              Legislation, Standards, Guidelines and Criteria relevant to the consideration of air quality impacts under this study include the following:

 

·         Hong Kong Air Pollution Control Ordinance;

·         Air Pollution Control (Construction Dust) Regulation; and

·         Environmental Impact Assessment Ordinance and Technical Memorandum on Environmental Impact Assessment Process.

 

Hong Kong Air Pollution Control Ordinance

 

2.2.2              Hong Kong’s air quality is regulated through the Air Pollution Control Ordinance (Cap. 311) (“APCO”). The APCO specifies Air Quality Objectives (“AQOs”), which are the statutory limits for a number of pollutants and the maximum allowable number of times that these may be exceeded over specified periods – these pollutants are defined as Criteria Pollutants (“CP”). The Air Quality Objectives (AQOs) that have been defined for these pollutants (CP) are given in the following table.

 

 

Table 21     Hong Kong Air Quality Objectives (mg/m3)(i)

Pollutant

1 Hour (ii)

8 Hours (iii)

24 Hours (iii)

3 Months (iv)

1 Year

 (iv)

Sulphur Dioxide

800

N.A.

350

N.A.

80

Total Suspended Particulates

500(vii)

N.A.

260

N.A.

80

Respirable Suspended Particulates (v)

N.A.

N.A.

180

N.A.

55

Carbon Monoxide

30,000

10,000

N.A.

N.A.

N.A.

Nitrogen Dioxide

300

N.A.

150

N.A.

80

Photochemical Oxidants (as ozone) (vi)

240

N.A.

N.A.

N.A.

N.A.

Lead

N.A.

N.A.

N.A.

1.5

N.A.

Notes:

(i)      Measured at 298K(25 oC) and 101.325 kPa (one atmosphere).

(ii)     Not to be exceeded more than three times per year.

(iii)    Not to be exceeded more than once per year.

(iv)    Yearly and three monthly figures calculated as arithmetic means.

(v)     Respirable suspended particulates means suspended particles in air with nominal aerodynamic diameter of 10 micrometres and smaller.

(vi)    Photochemical oxidants are determined by measurement of ozone only.

(vii)   This is not an AQO but a criterion for construction dust impact assessment under Annex 4 of the Technical Memorandum on Environmental Impact Assessment Process.

 

Air Pollution Control (Construction Dust) Regulation

 

2.2.3              Air Pollution Control (Construction Dust) Regulation stipulates the construction dust control requirements for both notifiable (e.g. site formation) and regulatory (e.g. road opening) works to be carried out by the Contractor.  The requirements for various notifiable and regulatory works are given in Parts 1 and 2 of the Regulation respectively.  Part 3 of the Regulation stipulates the general control requirements (e.g. site boundary and entrance) for construction dust.  The control requirements for individual activities (e.g. stockpiling of dusty material) are given in Part 4 of the Regulation. 

 

Environmental Impact Assessment Ordinance and Technical Memorandum on Environmental Impact Assessment Process

 

2.2.4              The criteria for evaluating air quality impacts are stated in Annexes 4 and 12 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).  The EIAO-TM states that the hourly Total Suspended Particulates (TSP) level should not exceed 500mg/m3 (measured at 25oC and one atmosphere) for construction dust impact assessment 

 

2.3                   Baseline Conditions and Air Sensitive Receivers

 

Baseline Conditions

 

2.3.1              The project mainly comprises the construction of a secondary boundary fence along the southern edge of the existing boundary patrol road from west (Pak Hok Chau) to east (Sha Tau Kok).

 

2.3.2              The nearest EPD air quality monitoring station (AQMS) is located at Yuen Long and Tap Mun.  Taking into account data for 2003 – 2007, the annual average air quality data collected at the monitoring station is presented in Table 2‑2.

 

Table 22     Annual Average Background Air Quality (2003 – 2007)

Air Pollutants

Annual Average Background Concentration at Yuen Long Monitoring Station (ug/m3)

Annual Average Background Concentration at Tap Mun Monitoring Station (ug/m3)

HKAQO

(ug/m3)

Total Suspended Particulates (TSP)

103

-

80

Respirable Suspended Particulates (RSP)

64

50

55

Nitrogen Dioxide (NO2)

60

14

80

Sulphur Dioxide (SO2)

26

15

80

 

Representative Air Sensitive Receivers

 

2.3.3              The selected ASRs, represent the closest distance from the proposed project site boundary or patrol road alignment, have been identified within the study area of 500m of the proposed alignment of the secondary boundary fence in accordance with the criteria as set out in Annex 12 of the EIAO-TM by means of site inspections and reviews of land use plans.

 

2.3.4              Identified ASRs with horizontal distances from the proposed alignment of the boundary fences are summarized in Table 2‑3.  The locations of the ASRs for each section (Sections 1 – 4) are shown in Figures 2-2 to 2-5.

 

Table 23     Representative Air Sensitive Receivers

ASR ID

Description

Type of Use

Separation Distance between the ASRs and the Project Site Boundary

Section 1

ASR 1

Mai Po Village House

Residential

101.4

ASR 2

Mai Po Village House

Residential

63.6

ASR 3

Mai Po San Tsuen

Residential

346.7

ASR 4

Lin Barn Tsuen

Residential

441.1

Section 2

ASR 5

Ha Wan Tsuen

Residential

13

ASR 6

Lok Ma Chau San Tsuen

Residential

21.7

ASR 7

Lok Ma Chau Village House

Residential

77.9

ASR 8

Ping Hang Village House

Residential

23.1

ASR 9

Ma Tso Lung Village House

Residential

15.6

ASR 10

Liu Pok

Residential

117.9

ASR 11

Temple

Worship

188.5

ASR 12

Tak Yuet Lau, House No. 4

Residential

18.7

Section 3

ASR 13

Lo Wu, House No. 3

Residential

100.4

ASR 14

Lo Wu Public School, House No. 39

Educational

58.5

ASR 15

Temple

Worship

111.8

ASR 16

Muk Wu, House No. 125

Residential

155

ASR 17

Sam Wo Public School

Educational

341.8

ASR 18

Muk Wu Chuen Yiu, House No. 11

Residential

75.8

ASR 19

Ta Kwu Ling, House No. 10

Residential

56.3

ASR 20

Kiu Liu Village

Residential

67.7

ASR 21

Chuk Yuen, House No. 19

Residential

110

ASR 22

Tsz Tong

Worship

198.1

ASR 23

Wang Lek Village House

Residential

55.8

ASR 24

Wang Lek Village House

Residential

6.5

ASR 25

Lin Ma Hang, House No. 1A

Residential

199.5

Section 4

ASR 26

Cannan English & Chinese Kindergarten

Educational

88

ASR 27

Ha Tam Shui Hang, House No. 221

Residential

67

ASR 28

Sha Tau Kok Estate, Block 1

Residential

88.2

ASR 29

Ha Tam Shui Hang, House No. 128

Residential

121

ASR 30

Kong Ha Village

Residential

126.7

ASR 31

Shan Tsui Village

Residential

88.2

 

2.4                   Identification and Evaluation of Air Quality Impact

 

Construction Phase

 

2.4.1              The construction and demolition of the boundary fences and patrol road will be divided into four sections, from which the major construction activities include the excavation, footing construction, fence installation, road construction, the demolition of existing boundary fence and the check points at Pak Hok Chau and Sha Tau Kok. There is no consolidated demolition programme, but it is expected the demolition will be commenced after the completion of the construction of secondary boundary fence.

 

2.4.2              Refer to the tentative construction programme in Appendix A, some construction activities will be carried out at the same period of time. However, in real situation, each construction activity will be carried out separately at different road sections.

 

2.4.3              The soil materials will be mainly generated from the construction activities including site clearance, construction and demolition, excavation and the waste generated from the construction works.  The total amount of soil materials generated each day from the project site will be in the range of 88m3/day to 248m3/day, which depends on the sections and the construction activities which will be carried out.  As such, an average number of trucks hauling on the site will be in the range of 11-30 trucks/day so as to remove the soil materials generated from the construction activities.  Given the Border Patrol Road is narrow (~4m to 8m), the number of trucks hauling around the road would be limited and hence the air quality impact is predicted minimal.

 

2.4.4              The likely air quality impacts arising from the construction of the secondary boundary fences include dust nuisances and gaseous emissions from Powered Mechanical Equipment (PMEs) and construction vehicles. It is anticipated that fugitive dust would also be generated from construction of concrete footing and fences, material handling and wind erosion from the site.

 

2.4.5              As the PMEs used for each section will not be operating concurrently as the construction works for the four sections are anticipated to be carried out in phases, fugitive dust impacts and gaseous emissions will be minimal. In addition, fugitive dust impacts from the construction vehicles will be further minimised with the implementation of the appropriate dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation.  As such, air quality impacts resulting from the proposed construction works are considered to be insignificant.

 

Operational Phase

 

2.4.6              Based on site observation during October 07 to August 08 and the confirmation from the Border District Police Headquarter, the traffic flow along the Border Patrol Road (BPR) observed is less than 50 veh/hr.  The main function of BPR is for boundary patrol, the Border District Police (BDP) is the main user of the BPR, the BPR would not be opened to the public except permit holders and there is no plan to revise this policy.  Based on such assumption, it is anticipated that the traffic flow of the BPR would not exceed 50 veh/hr in 15 years after its commissioning.  Hence, there will be limited gaseous emissions from the cars on the patrol roads, the potential air quality impacts are considered to be insignificant during operation.

 

2.5                   Mitigation Measures

 

Construction Phase

 

2.5.1              Construction dust impacts should be controlled within the 1-hour TSP criterion of 500 mg/m3 and 24-hour TSP AQO of 260 mg/m3.  Therefore, effective control measures and good site practices should be implemented to meet the requirements of the Air Pollution Control (Construction Dust) Regulation and to minimize construction dust impact.

 

2.5.2              During construction phase, the Contractor shall make reference, but not limited, to the following measures:

·        any excavated dusty materials or stockpile of dusty materials should be covered entirely by impervious sheeting or sprayed with water so as to maintain the entire surface wet, and recovered or backfilled or reinstated within 24 hours of the excavation or unloading;

·        the working area of excavation should be sprayed with water immediately before, during and immediately after the operations so as to maintain the entire surface wet;

·        dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting;

·        the area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should paved with concrete, bituminous materials or hardcores;

·        the portion of road leading only to a construction site that is within 30m of designated vehicle entrance or exit should be kept clear of dusty materials;

·        all dusty materials should be sprayed with water prior to any loading, unloading or transfer operation;

·        vehicle speed should be limited to 10kph except on completed access roads; and

·        every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites.

 

Operational Phase

 

2.5.3              As the gaseous emission from the operation of the secondary boundary fences and new boundary patrol roads are considered to be insignificant, air quality mitigation measures during the operational phase are not required.

 

2.6                   Potential Concurrent Projects

 

2.6.1              As mentioned in Section 1.8, there are three potential concurrent projects within the assessment area. The proposed works at Section 3 will be completed at the end of 2012, prior to the construction of the new Boundary Control Point (BCP) at Heung Yuen Wai, and hence no interface will be occurred.

 

2.6.2              The advance works from River Trainings in Section 3 and proposed new wave wall or modification to existing wave wall in Section 2 will be carried out concurrently with the project work. However, it is recommended that the proposed works from the two projects would be exercised from this project to avoid any duplications. At such, an entrustment approach for the concurrent projects would be adopted, and the cumulative impacts from the concurrent project are considered to be minimal. 

 

2.7                   Environmental Monitoring and Audit

 

2.7.1              Full compliance with the air quality criteria will be achieved at all ASRs with the implementation of dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation. Dust monitoring is considered not necessary during the construction phase but weekly site audits are required to ensure that the dust control measures are properly implemented.  No operational monitoring is considered to be necessary for this project.

 

2.8                   Conclusion

 

2.8.1              The construction works for the four sections will be carried out in phases, the potential air quality impacts will not be anticipated.  Air quality impacts resulting from the construction works of the Project are considered to be insignificant to air sensitive receivers.

 

2.8.2              Gaseous emissions from the operation of the secondary boundary fence and the new boundary patrol roads are considered to be insignificant, no air quality impact will be anticipated during the operational phase.


3                     NOISE IMPACT

 

3.1                   Introduction

 

3.1.1          The noise impact assessment evaluated the impact quantitatively using standard acoustic principles and making reference to the approach and methodology documented in Annexes 5 and 13 of Environmental Impact Assessment Ordinance – Technical Memorandum and EIAO Guidance Note No. 9/2004 – Preparation of Construction Noise Impact Assessment under EIAO for construction phase and EIAO Guidance Note No. 12/2005 – Road Traffic Noise Impact Assessment under the EIAO for operational phase.

 

3.2              Relevant Legislations, Standards & Guidelines

 

General Construction Activities during Non-Restricted Hours

 

3.2.1          Noise impacts arising from general construction activities other than percussive piling during the daytime period (07:00-19:00 hours of any day not being a Sunday or general holiday) shall be assessed against the noise standards tabulated in Table 3-1 below.

Table 31     Noise Standards for Daytime Construction Activities

Noise Sensitive Uses

0700 to 1900 hours on any day not being a Sunday or general holiday, Leq (30 min), dB(A)

All domestic premises including temporary housing accommodation

75

Hotels and Hostels

Educational institutions including kindergarten, nurseries and all others where unaided voice communication is required

70

65 during examination

Source: EIAO-TM, Annex 5, Table 1B - Noise Standards for Daytime Construction Activities.

Note:

·         The above standards apply to uses, which rely on opened windows for ventilation.

·         The above standards shall be viewed as the maximum permissible noise levels assessed at 1m from the external facades.

 

General Construction Activities during Restricted Hours

 

3.2.2          Noise impacts arising from general construction activities (excluding percussive piling) conducted during the restricted hours (19:00-07:00 hours on any day and anytime on Sunday or general holiday) and percussive piling during anytime are governed by the Noise Control Ordinance (NCO).

 

3.2.3          For carrying out general construction activities involving the use of Powered Mechanical Equipment (PME) within restricted hours, a Construction Noise Permit (CNP) is required from the Authority under the NCO.  The noise criteria and the assessment procedures for issuing a CNP are specified in Technical Memorandum on Noise from Construction Work Other Than Percussive Piling (GW-TM) under the NCO.

 

3.2.4          The use of Specified PME (SPME) and/or the carrying out of Prescribed Construction Work (PCW) within a Designated Area (DA) under the NCO during the restricted hours are also prohibited without a CNP.  The relevant technical details can be referred to Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM) under NCO. 

 

3.2.5          Designated areas, in which the control of SPME and PCW shall apply, are established through the Noise Control (Construction Work Designated Areas) Notice made under Section 8A(1) of the NCO. 

 

3.2.6          All sections of the construction works except the Sha Tau Kok section have been checked to fall outside the Designated Areas defined under the NCO (with effective from 1 January 2009).  Moreover, no percussive pilling will be involved in this Project.

 

3.2.7          As such, the application for CNP for any general construction activities involving the use of any PME shall refer to the GW-TM and DA-TM.  However, the Contractor has the responsibility to check the latest status and coverage of the Designated Areas at the time of construction of the project.

 

3.2.8          Regardless of the description or assessment made in this chapter, the assessment of a filed application for a CNP by the Authority will be guided by the relevant Technical Memoranda.  The Authority will consider all the factors affecting their decision taking contemporary situations/ conditions into account.  Nothing in this Report shall pre-empt the Authority in making their decisions, and there is no guarantee that a CNP will be issued.  If a CNP is to be issued, the Authority may include any conditions they consider appropriate and such conditions are to be followed while the works covered by the CNP are being carried out.  Failing to do so may lead to the cancellation of the permit and prosecution action under the NCO.

 

Road Traffic Noise

 

3.2.9          Relevant criteria for road traffic noise levels at the affected sensitive façade are given in Table 3-2 below.

Table 32     EIAO-TM Road Traffic Noise Criteria

Noise Sensitive Uses

Road Traffic Noise, Peak Hour Traffic, L10 (1-hr) dB(A)

All domestic premises including temporary housing accommodation

70

Hotel and Hostels

Educational institutions including kindergarten, nurseries and all others where unaided voice communication is required

65

Source: EIAO-TM, Annex 5, Table 1 - Noise Standards for Planning Purposes

Note:

·         The above standards apply to uses, which rely on opened windows for ventilation.

·         The above standards shall be viewed as the maximum permissible noise levels assessed at 1m from the external facades.

 

 

 

 

 

3.3              Study Area and Construction Programme

 

3.3.1          As stated in Clause 3.4.2.2(i) of the EIA Study Brief, the Study Area shall include all areas within 300m (the 300m envelope) from the Project Boundary.  Although the study area can reach 300m from the work sites, the first-tier NSRs are usually selected as representative NSRs in the noise impact assessment.  Other NSRs further away from these first-tier NSRs are expected to be less affected by comparison.  The assessment area of noise impact assessment is shown in Figure 3-1.

 

3.3.2          A tentative construction programme is shown in Appendix A.  The construction programme shows that the construction activities including the excavation, footing construction, fence installation, road construction and the check point superstructure at Sha Tau Kok of all sections are in phases.  However, in real situation, each construction activities will be carried out in segment by segment, the length of each segment is estimated to be 50m, which is a normal practice of construction.

 

3.3.3          Given that the narrow and long construction works area of Section 1 to Section 3 (~4m to 8m in width), the construction activities would be constructed sequentially along each Section.  The construction works would start from the west end of each Section and cumulative impact from the concurrent works could be avoided as the length of each Section is more than 2km.  Hence, the construction noise impact would be dominated by the construction activity of any one Section for each NSR.

 

3.3.4          Moreover, there is currently no firmed demolition programme of existing boundary fence and the check points at Lok Ma Chau, Sha Ling, Ping Che and Shek Chung Au.  It is expected the demolition activities will be commenced after the secondary boundary fence is constructed.  Hence, the noise impact of construction and demolition activities could be assessed separately.

 

3.4              Noise Sensitive Uses

 

3.4.1          Representative Noise Sensitive Receivers (NSRs) have been identified in accordance with Annex 13 of the EIAO-TM.  The NSRs include existing, planned/ committed noise sensitive developments and relevant uses earmarked on the relevant Outline Zoning Plans, Development Permission Area Plans, Outline Development Plans, Layout Plans and other relevant published land use plans, including plans and drawings published by Lands Department, where applicable.

 

3.4.2          There are numerous villages situated along the proposed alignment which are identified as NSRs.  For the purpose of this construction noise assessment, representative NSRs of each village close to the site have been selected within the Study Area for prediction of the levels of construction noise impact.  Descriptions of selected representative existing NSRs are tabulated in Table 3-3 to Table 3-6 below and the respective locations are shown in Figure 3-2 to Figure 3-8.  The shortest distance between the noise source, construction of boundary fence/ road construction, demolition of existing boundary wall and check points, which are the footing foundation of the fence and the receivers are measured and listed in Table 3-3 to Table 3-6 below.  Photos of existing noise sensitive receivers are shown in Figure 3-9 and Figure 3-10.

 

Table 33     Locations of the Existing Representative NSRs for Construction of Boundary Fence/ Road Construction/ Check Point Superstructure

NSR ID

Description

Usage

Shortest Distance (m)

Section 1

Mai Po

VH01

Village House

Residential

44

VH02

Village House

Residential

59

VH03

Village House

Residential

147

Section 2

Ha Wan Tsuen

HAT01

Village House

Residential

206

Lok Ma Chau San Tsuen

LMC01

Village House

Residential

>300

LMC02

Village House

Residential

>300

LMC03

Village House

Residential

>300

Ping Hang

PH01

Village House

Residential

>300

Ma Tso Lung

MTL01

Village House

Residential

>300

Liu Pok

LP01

House No. 1B, Liu Pok

Residential

>300

Tak Yuet Lau

TYL01

House No. 4, Tak Yuet Lau

Residential

204

Section 3

Lo Wu

LW01

House No. 3, Lo Wu

Residential

103

LW02

House No. 39, Lo Wu

Residential

60

Muk Wu

MW01

House No. 125, Muk Wu

Residential

130

MW02

House No. 11, Muk Wu Chuen Yiu

Residential

78

Ta Kwu Ling

TKL01

House No. 10, Tak Kwu Ling

Residential

43

Kaw Liu Village

KL01

Village House

Residential

18

Chuk Yuen

CY01

House No. 19, Chuk Yuen

Residential

106

Wang Lek

WL01

Village House

Residential

101

WL02

Village House

Residential

85

WL03

House No. 1A, Lin Ma Hang

Residential

155

Section 4

Sha Tau Kok

STK01

House No. 221, Ha Tam Shui Hang

Residential

42 (Boundary Fence)

132 (Checkpoint superstructure)

STK02

House No. 128, Ha Tam Shui Hang

Residential

100 (Boundary Fence)

235 (Checkpoint superstructure)

STK03

Block 1, Sha Tau Kok Estate

Residential

16 (Boundary Fence)

73 (Checkpoint superstructure)

STK04

Block 28, Sha Tau Kok Estate

Residential

91 (Boundary Fence)

169 (Checkpoint superstructure)

Table 34     Locations of the Existing Representative NSRs for Demolition of Exsiting Boundary Fence

NSR ID

Description

Usage

Shortest Distance (m)

Section 2 – Demolition of Existing Boundary Fence

HAT01

Village House

Residential

9

LMC01

Village House

Residential

21

LMC02

Village House

Residential

74

LMC03

Village House No. 201

Residential

55

PH01

Village House

Residential

7

MTL01

Village House

Residential

15

LP01

House No. 1B, Liu Pok

Residential

118

TYL01

House No. 4, Tak Yuet Lau

Residential

4

Section 3 – Demolition of Existing Boundary Fence

WL01

Village House

Residential

48

WL02

Village House

Residential

6

Table 35     Location of Existing Representative NSRs for Demolition of Check Points

NSR ID

Description

Usage

Shortest Distance (m)

Demolition of Check Points

Pak Hok Chau

VH01

Village House

Residential

75

Lok Ma Chau

LMC03

Village House No. 201

Residential

53

Sha Ling

SL01

Village House No. 190

Residential

149

Ping Che

PC01

House No. 5A, Tong Fong

Residential

59

Shek Chung Au

STK05

Village House

Residential

110

 

3.4.3          The potential planned/ committed noise sensitive uses within the assessment area have been checked with Planning Department and Lands Department.  Relevant correspondances have been attached in Appendix C1.  Planning Department stated that there is neither rezoning application approved nor any planned/ committed development including residential/ school/ hotel within the assessment area.  However, there is a planning application no. A/YL-ST/313 for temporary open storage of new left-hand-drive vehicles prior to sale was approved by the Rural and New Town Planning Committee on 21/7/2006 up to 21/7/2009.  Also, the Town Planning Board deferred a review application no. A/DPA/YL-MP/31 for a residential development on 17/5/1996, hence these two developments are not identified as noise sensitive uses.  Lands Department stated that they are not in position to disclosure these kinds of relevant information to third party.

 

3.4.4          Nevertheless, according to the Outline Zoning Plans along the works area from Mai Po to Sha Tau Kok, there is a Village Type Development (“V” zone) zoned near Lok Ma Chau.  As the construction of New Territories Exempted House is always permitted, an assessment point located at the V zone boundary is selected as a planned NSR for worst-case scenario assessment.  Description of the planned NSR and location is shown in Table 3-6 below and Figure 3.3 respectively. 

Table 36     Location of Planned NSR for Demolition of Existing Boundary Fence

NSR ID

Description

Usage

Shortest Distance (m)

Section 2 – Demolition of Existing Boundary Fence

V01

Planned Village House

Planned Residential

11

 

3.5              Assessment Approach & Methodology

 

3.5.1          Assessment approach to the noise impact is in line with the Guidance Note titled “Preparation of Construction Noise Impact Assessment under the Environmental Impact Assessment Ordinance” (GN 9/2004).

 

3.5.2          In addition, the assessment of construction noise impact is based on standard acoustic principles, and the guidelines given in GW-TM issued under the NCO where appropriate.  Where no sound power level (SWL) can be found in the relevant TM, reference has been made to BS 5228 Part I or noise emission levels measured for PME used in previous projects in Hong Kong.  The approach used is as follows: -

1.       Assume a typical construction schedule and project-specific equipment inventory for each work stage in Table 3-8 to Table 3-9 together with the number and type of PME that are considered likely for completing the works during the non-restricted hours;

2.       Obtain from the GW-TM, Sound Power Levels (SWL) for each PME assumed in the equipment inventory;

3.       Assume that likely noise source to be located near the boundary fence;

4.       For each of the representative NSRs in Table 3-3 to Table 3-6, with the use of the shortest distance to the noise source as worst-case scenario, calculate the maximum unmitigated Predicted Noise Level (PNL) amongst all construction work sites, corrected for facade reflection to obtain the Corrected Noise Level (CNL);

5.       If necessary, replace some of the PME with silenced equipment and/ or consider to use temporary noise barriers to calculate the mitigated noise impact;

6.       Consider any potential impact from the concurrent impact as mentioned in Section 1.8; and

7.       Compare the mitigated CNL with the noise standards given in Table 3-1 to determine acceptability and the need for further mitigation/ EM&A.

3.5.3          The calculation methodology is estimated with the following standard formula (1):

SPL = SWL – DC +FC                       (1)

where

Sound Pressure Levels, SPL in dB(A)

Sound Power Levels, SWL in dB(A)

Distance Attenuation, DC in dB(A) = 20*Log(D)+8 (where D is the distance between NSRs and noise source in meters)

Façade Correction, FC in dB(A) = 3dB(A)

 

3.6              Analysis of Construction Activities and Sources of Noise Impact

 

3.6.1          As mentioned in the Section 1.4, the entire boundary fence is divided into four sections namely Section 1 to Section 4 as shown in Figure 1.1.

 

3.6.2          It is expected that works for the construction/ demolition of the boundary fence can roughly be divided into several work stages as given in Table 3-7.  There is no confirmed programme for the demolition of existing boundary fence and the check points as yet, however, it is expected that this demolition activity would be commenced after the completion of construction of secondary boundary fence and hence no cumulative impact is expected. 

 

3.6.3          It is also expected that the construction/ demolition activities will be conducted during non-restricted hours, construction/ demolition works during restricted hours will not be anticipated. 

 

3.6.4          To facilitate an estimate of the likely level of construction noise impact during non-restricted hours, an inventory of project-specific PME needed has been assumed with the typical construction works are shown in Table 3-8 to Table 3-9 below.  The number of PME used for the construction/ demolition activities is also included.  The checkpoint replacement in Section 1 would be in pre-fabrication method which does not involve any construction activities and no PME would be involved.

 

3.6.5          As the Boundary Patrol Road is narrow and this Road is the main route for patrolling and emergency, the frequency and the size of PME employed on site would be limited.  The Contractor would prefer the use of smaller machines, for example, the use of mini-robot mounted breakers and excavators instead of the regular PME listed in the GW-TM to avoid obstruction the patrolling and emergency access.  Also, the duration of the use of lorry for loading and uploading of construction material and/or excavated material should be limited such that the progress of construction works would not be hindered. 

 

3.6.6          Moreover, in general construction situtation, the loading and uploading activities would not be carried out at the footing location/ checkpoints location to hinder the general excavation or footing construction activities.  As such, the distance from the lorry to noise sensitive uses would be longer, a 20m further away from the footing location is assumed for calculation.  The construction noise impact assessment would then be assessed for general construction activities (excavation, road construction, footing construction and checkpoint superstructure) and loading and uploading activities seperately.

 

3.6.7          Each construction/ demolition activity would be carried out in sequence, for example, during the excavation activities and the demolition of existing boundary fence, the PME such as mini-robot mounted breakers and excavators will not be operated concurrently as the works are usually carried out using the same equipment in sequence.  During the footing construction of the boundary fence, excavation and the concreting works will not be operated concurrently as the works are also carried out in sequence.  Table 3-8 below shows the grouping of each construction sequence.

 

3.6.8          The number and the percentage of time used of PMEs assumed for worst-case scenario for each construction/ demolition activities is shown in Appendix C2.  The Project Proponent confirmed that the plant inventories adopted in this assessment are technically feasible for undertaking the construction/ demolition works.

 

3.6.9          According to Section 1.8 of this EIA Report, there is one potential concurrent project, the Proposed New Wave Wall/ Modification of Existing Wave Wall in Section 2.  Based on the latest information obtained, the construction works would be in entrustment approach and the construction programme and the PME list in Section 2 has been incoporated (excavation and footing construction work for both wave wall and the boundary patrol road and boundary fence). 

Table 37     Tentative Construction/ Demolition Activities for All Sections

Section

Activity ID

Construction/ Demolition Activities

Section 1

1A

Excavation

 

1B

Footing Construction

 

1C

Fence Installation

Section 2

2A

Excavation

 

2B

Footing Construction

 

2C

Road Construction

 

2D

Fence Installation

Section 3

3A

Excavation

 

3B

Footing Construction

 

3C

Road Construction

 

3D

Fence Installation

Section 4

4A

Excavation

 

4B

Footing Construction

 

4C

Fence Installation

 

4D

Check Point Superstructure

Section 1 – Section 4

-

Loading and Uploading activities with the use of Lorry

Section 2 and Section 3

-

Demolition of Existing Boundary Fence

Section 1 – Section 4

-

Check Points Demolition

Table 38     Tentative Construction Plant List for Construction of Boundary Fence/ Road Construction/ Check Point Superstructure

Construction Activities/ PME

TM Ref.

SWL dB(A)/ Unit

Quantity

Percentage on time

Excavation

 

Group 1

 

Breaker, mini- robot mounted

[1]

115

1

100%

Total SWL, dB(A)

115

 

Group 2

 

Excavator, mini robot mounted

[1]

94

1

100%

 

Generator, Standard

CNP 101

108

1

100%

 

Water Pump (electric)

CNP 281

88

1

100%

Total SWL, dB(A)

108

 

Group 3

 

Lorry

CNP 141

112

1

50%

Total SWL, dB(A)

109

Maximum SWL, dB(A)

115

Footing Construction

 

Group 1

 

Lorry

CNP 141

112

1

50%

Total SWL, dB(A)

109

 

Group 2

 

Generator, Standard

CNP 101

108

1

100%

 

Bar bender and cutter (electric)

CNP 021

90

1

100%

 

Water pump (electric)

CNP 281

88

1

100%

Total SWL, dB(A)

108

 

Group 3

 

Compactor, vibratory

CNP 050

105

1

100%

 

Concrete lorry mixer

CNP 044

109

1

100%

Total SWL, dB(A)

110

Maximum SWL, dB(A)

110

Fence Installation

 

Group 1

 

Lorry

CNP 141

112

1

50%

Total SWL, dB(A)

109

 

Group2

 

Generator, Standard

CNP 101

108

1

100%

 

Drill/grinder, hand-held (electric)

CNP 065

98

1

100%

Total SWL, dB(A)

108

Maximum SWL, dB(A)

109

Road Construction

 

Group 1

 

Lorry

CNP 141

112

1

50%

Total SWL, dB(A)

109

 

Group 2

 

Excavator, mini-robot mounted

[1]

94

1

100%

Total SWL, dB(A)

94

 

Group 3

 

Road Roller

CNP 185

108

1

100%

Total SWL, dB(A)

108

Maximum SWL, dB(A)

109

Check Point Superstructure

 

Group 1

 

Excavator, mini-robot mounted

[1]

94

1

100%

Total SWL, dB(A)

94

 

Group 2

 

Lorry

CNP 141

112

1

50%

Total SWL, dB(A)

109

 

Group 3

 

Generator, standard

CNP 101

108

1

100%

 

Bar bender and cutter (electric)

CNP 021

90

1

100%

Total SWL, dB(A)

108

 

Group 4

 

Compactor, vibratory

CNP 050

105

1

100%

 

Concrete lorry mixer

CNP 044

109

1

100%

 

Concrete pump, stationary/ lorry mounted

CNP 047

109

1

100%

Total SWL, dB(A)

113

Maximum SWL, dB(A)

113

Note:

[1] Details extracted from EPD website:

http://www.epd.gov.hk/epd/english/application_for_licences/guidance/files/OtherSWLe.pdf

 

Table 39     Tentative Construction Plant Lists for Demolition of Existing Boundary Fence and Check Points

Demolities Activities/ PME

TM Ref.

SWL dB(A)/ Unit

Quantity

Percentage on time

Demolition of Existing Boundary Fence and Check Points

 

Group 1

 

Generator, standard

CNP 101

108

1

100%

 

Drill/ grinder, hand-held (electric)

CNP 065

98

1

100%

Total SWL, dB(A)

108

 

Group 2

 

Breaker, mini robot mounted

[1]

115

1

100%

Total SWL, dB(A)

115

 

Group 3

 

Excavator, mini robot mounted

[1]

94

1

100%

Total SWL, dB(A)

94

 

Group 4

 

Lorry

CNP 141

112

1

50%

Total SWL, dB(A)

109

Maximum SWL, dB(A)

115

Note:

[1] Details extracted from EPD website:

http://www.epd.gov.hk/epd/english/application_for_licences/guidance/files/OtherSWLe.pdf

 

3.6.10      Given the similar construction method for each section and the construction activities would be carried out in sequence, the maximum SWL of each activity is summarised in Table 3-10 below for carrying construction noise impact assessment for worst-case scenario. 

 

Table 310   Maximum SWL of Each Activity for Construction Noise Impact Assessment

Section

Construction/ Demolition Activities

Total SWL, dB(A)

Section 1 – Section 4

Excavation

115

 

Footing Construction

110

 

Fence Installation

108

Section 2 and Section 3

Road Construction

108

Section 4

Check Point Superstructure

113

Section 1 – Section 4

Loading and Uploading Activities with the use of Lorry

109

Section 2 and Section 3

Demolition of Existing Boundary Fence

115

Section 1 – Section 4

Check Points Demolition

115

 

3.6.11      The construction noise impacts due to construction activities (excavation, footing construction, road construction and check point superstructure) to the NSRs within 300m assessment area are identified in Table 3-11. 


 Table 311  Construction Noise Impacts apart from Demolition of Existing Boundary Fence and Check Point to the NSRs

NSR ID

Description

Construction Activities

Section 1

Section 2

Section 3

Section 4

1A

1B

1C

2A

2B

2C

2D

3A

3B

3C

3D

4A

4B

4C

4D

VH01

Village House

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

VH02

Village House

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

VH03

Village House

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

HAT01

Village House

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

LMC01

Village House

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

LMC02

Village House

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

LMC03

Village House

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

V01

Planned Residential

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

PH01

Village House

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MTL01

Village House

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

LP01

House No. 1B, Liu Pok

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TYL01

House No. 4, Tak Yuet Lau

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

LW01

House No. 3, Lo Wu

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

LW02

House No. 39, Lo Wu

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MW01

House No. 125, Muk Wu

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MW02

House No. 11, Muk Wu Chuen Yiu

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TKL

House No. 10, Tak Kwu Ling

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

KL01

Village House

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

CY01

House No. 19, Chuk Yuen

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

WL01

Village House

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

WL02

Village House

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

WL03

House No. 1A, Lin Ma Hang

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

STK01

House No. 221, Ha Tam Shui Hang

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

STK02

House No. 128, Ha Tam Shui Hang

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

STK03

Block 1, Sha Tau Kok Estate

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

STK04

Block 28, Sha Tau Kok Estate

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Note:

As there is no confirmed programme for demolition of existing fence and check points, it is expected that this demolition activity would be commenced after the completion of construction of secondary boundary fence


3.7              Unmitigated Construction Noise Impacts

 

3.7.1          Based on the staged construction activities and PME inventory, the predicted highest construction noise impacts amongst all construction stages for the unmitigated scenario have been summarised in Table 3-12 to Table 3-14 below together with calculation summary sheet shown in Appendix C2.

Table 312   Unmitigated Noise Impact due to the Construction of Boundary Fence/ Road Construction/ Check Point Superstructure

NSR ID

Usage

Unmitigated Noise Level, dB(A)

Noise Criteria, dB(A)

Mitigation Measures Required?

Section 1

VH01

Residential

77

75

Yes

VH02

Residential

75

75

No

VH03

Residential

67

75

No

Section 2

HAT01

Residential

64

75

No

TYL01

Residential

64

75

No

Section 3

LW01

Residential

70

75

No

LW02

Residential

74

75

No

MW01

Residential

68

75

No

MW02

Residential

72

75

No

TKL01

Residential

77

75

Yes

KL01

Residential

85

75

Yes

CY01

Residential

69

75

No

WL01

Residential

70

75

No

WL02

Residential

71

75

No

WL03

Residential

66

75

No

Section 4

STK01

Residential

78

75

Yes

STK02

Residential

70

75

No

STK03

Residential

86

75

Yes

STK04

Residential

71

75

No

Note: Bold figure denotes exceedance of relevant noise criteria

Table 313   Unmitigated Noise Impact due to the Demolition of Existing Boundary Fence

NSR ID

Usage

Unmitigated Noise Level, dB(A)

Noise Criteria, dB(A)

Mitigation Measures required?

Section 2 – Demolition of Existing Boundary Fence

HAT01

Residential

91

75

Yes

LMC01

Residential

84

75

Yes

LMC02

Residential

73

75

No

LMC03

Residential

75

75

No

V01

Planned Residential

89

75

Yes

PH01

Residential

93

75

Yes

MTL01

Residential

86

75

Yes

LP01

Residential

69

75

No

TYL01

Residential

98

75

Yes

Section 3 – Demolition of Existing Boundary Fence

WL01

Residential

76

75

Yes

WL02

Residential

94

75

Yes

Note: Bold figure denotes exceedance of relevant noise criteria

Table 314   Unmitigated Noise Impact due to the Demolition of Check Points

NSR ID

Usage

Unmitigated Noise Level, dB(A)

Noise Criteria, dB(A)

Mitigation Measures required?

Demolition of Check Points

VH01

Residential

72

75

No

LMC03

Residential

76

75

Yes

SL01

Residential

67

75

No

PC01

Residential

75

75

No

STK05

Residential

69

75

No

Note: Bold figure denotes exceedance of relevant noise criteria

 

3.7.2          As shown in the tables above, exceedances of noise criteria were predicted, mitigation measures should be implemented to ameliorate the impacts.  It is noted that with a separation distance of 60m between the noise sensitive uses and the construction/ demolition activities, similar as VH02, full compliance of noise criteria could be achieved.  Hence, for those NSRs with the distance over 300m as shown in Table 3-3, the unmitigated noise impact should also be complied with relevant noise criteria.

 

3.8              Possible Noise Mitigation Measures and Mitigated Impacts

 

Level 1 – Use of Quiet Plant and Movable Noise Barrier

 

3.8.1          With construction/ demolition work undertaken at a distance of 60m or less to the NSRs, mitigation measures should be considered.  Quiet plant is defined as a PME which has a SWL lower than that given in the Technical Memorandum for Noise from Construction Work Other Than Percussive Piling for the same type of equipment.  Examples of known SWLs of various types of quiet plant available in Hong Kong are shown in Table 3-15 and have been successfully applied in other EIA/ works and contributed to achieve noticeable noise reduction. 

Table 315   Recommended Quiet PME and the SWL

Quiet Plant

SWL, dB(A)

Reference

Breaker, excavator mounted (hydraulic), 52kW

106

BS5228 C8-12

Generator, super silenced

95

CNP 103

Lorry

105

BS5228 C3-59

Concrete lorry mixer (6m3)

100

BS5228 C6-23

Road roller

101

BS5228 C8-30

Concrete Pump (100kW)

106

BS5228 C6-36

 

3.8.2          Also, purpose-built movable noise barriers should be used to mitigate construction noise directly at sources that are not usually mobile.  As the village houses along the boundary fence is typical 1-2 storeys, the movable noise barrier is effective to block the direct line of sight from the receiver to the noise source.  According to the EIAO Guidance Note No. 9/2004, a 5 dB(A) and 10 dB(A) reduction is assumed for movable plant and stationary plant respectively.  The noise screening effect for each item of plant considered in this assessment is listed as follows:

·         Mobile plant – assume 5 dB(A) reduction: Breaker, Excavator, Vibratory Compactor, Hand-held Driller, Road Roller; and

·         Stationary plant – assume 10 dB(A) reduction: Generator, Concrete Pump and Water Pump

 

3.8.3          The movable noise barriers should be free of gaps and made of materials having a surface mass density in excess of 7 kg/m2.  To improve the effectiveness of noise reduction, non-flammable absorptive lining can be adhered on the inner surface of the barrier.  The barrier can be in the form of vertical or bend top barrier and the width of the barrier should have with an effective height/ width to block the line of sight to from the NSRs to the noise source.  A typical section of movable noise barrier is shown in Figure 3.11. 

 

3.8.4          However, it should be noted that the noise mitigation measures including the phasing of works and the use of movable noise barriers adopted in this EIA report are specified to this project only.  With the consideration of specify work type and the low-rise village houses in this project, these specific designs of movable noise barrier with the screening effect provided that the direct line of sight between the noise sensitive uses and the noise source is blocked.  This mitigation measure of noise screening should not be lightly applied to the other projects without careful consideration of the specify works, design of noise barriers and the noise sensitive receivers’ situation.

 

3.8.5          By replacing the regular PMEs with the quieter ones and with the use of movable noise barrier, the maximum SWLs for the worst-case scenario of the revised plant inventory is listed in Table 3-16 below and in Appendix C3. 

Table 316   Maximum SWLs of Plant Inventory with Mitigation Measures Implemented

Section

Construction/ Demolition Activities

Total SWL, dB(A)

Section 1 – Section 4

Excavation

101

 

Footing Construction

103

 

Fence Installation

94

Section 2 and Section 3

Road Construction

96

Section 4

Check Point Superstructure

104

Section 1 – Section 4

Loading and Uploading Activities with the use of Lorry

102

Section 2 and Section 3

Demolition of Existing Boundary Fence

101

Section 1 – Section 4

Check Points Demolition

101

 

 

3.8.6          The noise impact has been re-assessed and summarised in Table 3-17 to Table 3-19 with calculation summary sheet was shown in Appendix C3.

Table 317   Mitigated Noise Impact due to the Construction of Boundary Fence/ Road Construction/ Check Point Superstructure (Level 1)

NSR ID

Usage

Mitigated Noise Level, dB(A)

Noise Criteria, dB(A)

Mitigation Measures Required?

Section 1

VH01

Residential

65

75

No

Section 3

TKL01

Residential

65

75

No

KL01

Residential

73

75

No

Section 4

STK01

Residential

66

75

No

STK03

Residential

74

75

No

Table 318   Mitigated Noise Impact due to the Demolition of Existing Boundary Fence (Level 1)

NSR ID

Usage

Mitigated Noise Level, dB(A)

Noise Criteria, dB(A)

Mitigation Measures required?

Section 2 – Demolition of Existing Boundary Fence

HAT01

Residential

77

75

Yes

LMC01

Residential

70

75

No

V01

Planned Residential

75

75

No

PH01

Residential

79

75

Yes

MTL01

Residential

72

75

No

TYL01

Residential

84

75

Yes

Section 3 – Demolition of Existing Boundary Fence

WL01

Residential

62

75

No

WL02

Residential

80

75

Yes

Note: Bold figure denotes exceedance of relevant noise criteria

 

Table 319   Mitigated Noise Impact due to the Demolition of Check Points (Level 1)

NSR ID

Usage

Mitigated Noise Level, dB(A)

Noise Criteria, dB(A)

Mitigation Measures Required?

Demolition of Check Points

LMC03

Residential

62

75

No

 

3.8.7          With all these measures in place, the mitigated construction noise impacts have been predicted with noise exceedance still exist.  Therefore, further mitigation measures should be considered.

 

Level 2 – Alternative Demolition Method of Existing Boundary Fence

 

3.8.8          Based on Table 3-18 above, noise exceedance was found during the demolition of existing boundary fence.  A sensitivity test below showing that the maximum of SWL for the demolition of existing boundary fence which is 102 dB(A) as shown in Table 3-16.  With a minimum separation distance of 12m would comply with the noise criteria of 75 dB(A). 

Table 320   Sensitivity Test for Minimum Separation Distance

Maximum SWL, dB(A)

Distance, (m)

Distance Attenuation, dB(A)

Façade Correction, dB(A)

Maximum SPL, dB(A)

102

12

-30

+3

75

 

3.8.9          Given the existing boundary fence and the works area are close promixity to the noise sensitive receivers, particular migitaion measures should be applied to those NSRs having a distance of less than 12m between the sensitive receivers and the footing location of the existing boundary fence.  In addition to the use of quiet plant and movable noise barrier, alternative demolition method of existing boundary fence at Section 2-3 shall be used where demolition works would be undertaken at a distance of 12m or less to the NSRs and the Project Proponent comfirmed this alternative demolition method is feasible.  These particular mitigation measures include:

 

Demolition of Existing Fence

·         the use of welder is recommened to replace the use of hand-held driller;

·         the use of hand-held breaker with movable noise barrier is recommended to replace the use of mini-robot mounted breaker; a 10 dB(A) noise reduction was assumed for the hand-held breaker with the movable noise barrier; and the duration for the use of hand-held breaker is minimal as only the surface level of the footing to be broken; and

·         the removal of the footing of the existing boundary fence should be carried by concrete crusher mini-robot mounted after the surface level broken by hand-held breaker.

 

3.8.10      With these mitigation measures in place, the mitigated construction noise impacts have been predicted and the summary of assessment results of mitigated scenario is shown in Table 3-21.   The revised plant inventory for demolition of existing boundary fence and the calculation summary sheet is shown in Appendix C4.

Table 321   Mitigated Noise Impact due to the Demolition of Existing Boundary Fence (Level 2)

NSR ID

Usage

Mitigated Noise Level, dB(A)

Noise Criteria, dB(A)

Mitigation Measures Required?

Section 2 – Demolition of Existing Boundary Fence

HAT01

Residential

69

75

No

PH01

Residential

70

75

No

TYL01

Residential

75

75

No

Section 3 – Demolition of Existing Boundary Fence

WL02

Residential

72

75

No

 

3.8.11      With these further mitigation measures in place, the mitigated construction noise impacts have been predicted and full compliance of noise criteria has achieved.

 

3.8.12      There is an office area managed by World Wide Fund (WWF) near the existing checkpoint of Section 1 (which has a longer distance to the works area compared with VH01), there may have potential educational usages (with no examination period assumed) and hostel uses within the office area.  The maximum SWL of construction activities of Section 1 is 103 dB(A) as shown in Table 3-16.  A sample calculation for the potential construction noise impact to WWF is summarised below in Table 3-22 which showed the compliance of relevant 70 dB(A) noise criteria.

Table 322   Construction Noise Impact Assessment for WWF

Maximum SWL, dB(A)

Distance, (m)

Distance Attenuation, dB(A)

Façade Correction, dB(A)

Maximum SPL, dB(A)

103

140

-51

+3

55

 

3.8.13      By combining with the implementation of mitigation measures proposed and the designed EM&A requirements, construction noise impact should be controlled to within acceptable levels.

 

3.8.14      However, it is recommended that the Contractor should also adopt good working practices in order to minimise construction noise as far as possible, e.g.:

 

·         The Contractor shall adopt the Code of Practice on Good Management Practice to Prevent Violation of the Noise Control Ordinance (Chapter 400) (for Construction Industry) published by EPD;

·         The Contractor shall observe and comply with the statutory and non-statutory requirements and guidelines;

·         Before commencing any work, the Contractor shall submit to the Engineer Representative for approval the method of working, equipment and noise mitigation measures intended to be used at the site;

·         The Contractor shall devise and execute working methods to minimise the noise impact on the surrounding sensitive uses, and provide experienced personnel with suitable training to ensure that those methods are implemented;

·         Noisy equipment and noisy activities should be located as far away from the NSRs as practical;

·         Unused equipment should be turned off.  Number of operating PME should be kept to a minimum and the parallel use of noisy equipment / machinery should be avoided;

·         Regular maintenance of all plant and equipment; and

·         Material stockpiles and other structures should be effectively utilised as noise barriers, where practicable.

 

3.9              Operation Phase Noise Impact Assessment

 

Road Traffic Noise

 

3.9.1          The operation of the new sections of the boundary patrol road may have road traffic noise impact to noise sensitive receivers nearby, the impact on the identified NSRs is assessed following the criteria and guidelines set out in Annexes 5 and 13 of the TM.

 

3.9.2          It is anticipated that the road traffic generated would be minimal as there are mainly police patrol cars and maintenance cars (e.g. WSD, DSD etc.) travelling along the boundary patrol road. 

 

3.9.3          Based on site observation during October 2007 to August 2008, the traffic flow observed on the Boundary Patrol Road was less than 50 veh/hr, it is anticipated that the function of future Boundary Patrol Road would be the same as the existing Boundary Patrol Road and the traffic flow 15 years after the commissioning of the Project is hence assumed to be less than 50 veh/hr.

 

3.9.4          Predicted road traffic noise is calculated in accordance to the UK methodology for the Calculation of Road Traffic Noise (CRTN) published by Department of Transport, UK.  In order to satisfy the minimum traffic flow requirement for CRTN, the traffic flow of the BPR is assumed to be 50veh/hr.  Moreover, the traffic speed and the percentage of heavy vehicles of the BPR are assumed as 50 km/hr and 100% respectively as worst case scenario.  The correction of low traffic flow to the calculated noise level has also been considered.  The Project Proponent confirmed these assumptions are capable for calculation of road traffic noise.

 

3.9.5          The village house at Wang Lek (WL02) is the nearest noise sensitive receiver to the new section of the boundary patrol road (85m).  The predicted road traffic noise level is 60 dB(A) which is 10 dB(A) less than the criteria 70 dB(A).  Moreover, for those noise sensitive receivers exposed to the existing boundary patrol road, it is anticipated the impact would be similar to the existing scenario as the traffic flow 15 years after the commissioning of the Project is expected to be still less than 50 veh/hr.  Nevertheless, potential traffic impact has also been assessed.  The village house at Kaw Liu Village (KL01) is the nearest noise sensitive receiver to the existing boundary patrol road (18m).  The predicted road traffic noise level is 66 dB(A) which is 4 dB(A) less than the criteria 70 dB(A).

 

3.9.6          A worst-case assumption of road traffic flow and the percentage of heavy vehicle has been adopted in the prediction, it is concluded that potential road traffic noise impact would comply with the noise criteria stipulated in the EIAO-TM.

 

3.10          Environmental Monitoring and Audit (EM&A) Requirements

 

3.10.1      Given the results from the noise impact predicted during the construction phase could be mitigated to acceptable noise level, to ensure that the nearby NSRs will not be subjected to unacceptable construction noise impact, an Environmental Monitoring and Audit (EM&A) programme is recommended.  Details on the noise monitoring requirements, methodology and action plans have been described in the accompanying EM&A Manual.

 

3.11          Conclusion

 

3.11.1      The construction noise impact assessment has been based on a best estimate of the construction sequence and machines inventory. 

 

3.11.2      The potential noise impact that could arise from daytime construction activities of the Project has been evaluated.  With the use of quiet plant, the movable noise barriers and the alternative demolition method, all the construction noise impact can be mitigated to acceptable levels.  The Contractor shall, from time to time, be aware of the noise impacts on the surrounding NSRs through adequate noise monitoring during the works so that adjustments could be made to control the construction noise levels.  These requirements should be triggered by an Event and Action Plan as part of the EM&A which should be incorporated into the works contract in order to make it enforceable.

 

3.11.3      During the operation phase, the road traffic noise generated from the newly constructed Border Road is predicted remaining unchanged to the existing scenario as there are mainly police patrol cars and maintenance cars (e.g. WSD, DSD etc.) travelling along the boundary patrol road.  A worst-case assumption of road traffic flow and the percentage of heavy vehicle has been adopted in the prediction, it is concluded that potential road traffic noise impact would comply with the noise criteria stipulated in the EIAO-TM.


4                        WATER QUALITY IMPACT

 

4.1                   Introduction

 

4.1.1              A water quality impact assessment has been undertaken to define the nature and scale of potential environmental impacts associated with the Project specifically in terms of the effects in the vicinity of water sensitive receivers. The assessment has been carried out in accordance with section 3.4.3 of the Study Brief and Annexes 6 and 14 of the Technical Memorandum to the EIAO.

 

4.1.2              This chapter presents the assessment of potential water quality impacts which may arise during both the construction and operation of the Project. Mitigation measures have been proposed to alleviate the potential water quality impact, and the residual impacts after implementation of these measures are evaluated. 

 

4.2                   Environmental Legislation, Standards, Guidelines and Criteria

 

4.2.1              Water quality impacts have been assessed with reference to the relevant environmental legislation and standards. The following relevant pieces of legislation and associated guidelines are applicable to the evaluation of water quality impacts associated with the Project.

 

·         Water Pollution Control Ordinance (WPCO) (Cap. 358);

·         Technical Memorandum for Effluents Standards for Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (WPCO, Cap. 358, S.21);

·         Environmental Impact Assessment Ordinance (Cap. 499., S.16), Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), Annexes 6 and 14;

·         Hong Kong Planning Standard and Guidelines (Chapter 9); and

·         Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94).

 

Water Pollution Control Ordinance

 

4.2.2              Under the Water Pollution Control Ordinance (WPCO) (Chapter 358), Hong Kong waters are divided into 10 Water Control Zones (WCZs) and 4 supplementary water control zones. Each of which has a designated set of statutory Water Quality Objectives (WQOs) designed to protect the inland and/or marine environment and its users. The proposed project is located in the Deep Bay and Mirs Bay Water Control Zones. The WQOs are applicable as evaluation criteria for assessing compliance of any effects from the construction and operation of the Project.  

 

Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters

 

4.2.3              This technical memorandum (TM-DSS) was issued under section 21 of the WPCO. It sets the limits to control the physical, chemical and microbial quality of effluent discharges into foul sewers, stormwater drains, inland and coastal waters. Specific limits apply for different areas and are different between surface waters and sewers. The limits vary with the rate of effluent flow. Sewage from the proposed construction activities should comply with the standards for effluent discharged into foul sewers, inshore waters or marine waters of Deep Bay and Mirs Bay WCZs, as shown in Tables 4, 5, 8, 10a and 10b of the TM-DSS.

 

No Net Increase Requirement

 

4.2.4              Effluent treatment is required prior to discharge into the water courses in the Deep Bay Area, in order to meet the criteria of “no net gain” in pollution load as specified in the Town Planning Board Guidelines No. 12B. The underlying principle is to protect the important habitats and wildlife of the Deep Bay region.

 

Environmental Impact Assessment Ordinance (Cap. 499) Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM)

 

4.2.5              Under Section 16 of the EIAO, EPD issued the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) which specifies the assessment methods and criteria for environmental impact assessment. This Study follows Annex 6 – Criteria for Evaluating Water Pollution and Annex 14 – Guidelines for Assessment of Water Pollution under the EIAO-TM to assess the potential water quality impacts that may arise during construction and operation phases of the Project.

 

Hong Kong Planning Standards and Guidelines (HKPSG)

 

4.2.6              Chapter 9 of these guidelines provide guidance for potentially polluting uses including environmental considerations in the planning of civil engineering infrastructure and operation. The guidelines recommend that unspoilt areas designated for conservation, Sites of Special Scientific Interest, areas used for commercial fisheries including fish culture and shellfish cultivation should be taken care in planning and implementation of works to avoid, minimize or ameliorate pollution caused by silt, oil and floating refuse.

 

Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94)

 

4.2.7              This Practice Note issued by ProPECC in 1994 also provides useful guidelines on the management of construction site drainage and prevention of water pollution associated with construction activities.

 

4.3                   Assessment Methodology

 

4.3.1              The Study Area for the water quality impact assessment is defined as 500m from the Project site boundary according to the Study Brief. Construction phase of the Project will include the construction of primary and secondary boundary fence, new boundary patrol road, two new checkpoints and the removal of existing boundary fence and checkpoints at various places. These works will be commenced near existing water systems including rivers, streams and fish ponds.

 

4.3.2              In order to assess the impacts on water systems during construction and operations, it is first necessary to define what activities will take place which could potentially affect water quality.

 

4.3.3              During the construction phase, facilities such as dust suppression sprays and temporarily stockpile will be used on site. Wash water runoff and erosion of excavated materials by rainfall may contain suspended solids and contaminants. Domestic sewage will be generated from site workers. During the operational phase, as the proposed checkpoint at Shek Chung Au will be provided with sanitary facilities, sewage will be generated. All these runoff and sewage may cause chemical and biological disruptions of marine water, freshwater systems, stormwater channels and fish ponds.

 

4.3.4              No reclamation or dredging works is required. There will not be any physical disruptions of marine water, freshwater systems, stormwater channels or fish ponds. No impact on ground water, hydrology or flow regime is anticipated. Potential biological and chemical disruptions mentioned can be avoided and mitigated by good site practices.

 

4.4                   Baseline Conditions

 

4.4.1              The water environmental aspects of the Study Area include marine water, river water, drainage, freshwater stream and fishponds. Within the Study Area, water quality is dominated by effluents from agricultural activities, disposal of domestic sewage from nearby villages and industrial discharges.

 

Marine Water Quality

 

4.4.2              The Study Area of the Project lies within the Deep Bay and Mirs Bay Water Control Zones. Marine water bodies in the Study Area include Inner Deep Bay and Starling Inlet.

 

4.4.3              Marine water quality at Inner Deep Bay remained poor in 2006 with low dissolved oxygen level, high amount of suspended solids and E. coli, failing to compile with WQOs. The EPD monitoring station of most relevance is DM1. A summary of the recently published EPD marine water monitoring data collected at DM1 are presented in Table 4-1.

Table 41     Summary of EPD Marine Water Quality Monitoring Data at Inner Deep Bay Monitoring Station DM1 between 2004 and 2006

Parameter

WQO

2004

2005

2006

Dissolved Oxygen (mg/L)

≥ 4.0

3.3

(1.6 – 7.0)

2.9

(1.3 – 6.3)

3.8

(1.4 – 6.7)

pH

6.5 – 8.5

7.7

(7.2 – 8.3)

7.5

(7.0 – 8.0)

7.3

(6.8 – 7.9)

Total Inorganic Nitrogen (mg/L)

≤ 0.7

6.26

(2.98 – 8.97)

5.48

(3.68 – 7.01)

3.86

(1.16 – 6.47)

Unionised Ammonia (mg/L)

0.021

0.162

(0.022 – 0.521)

0.096

(0.023 – 0.460)

0.041

(0.002 – 0.110)

E. coli (cfu/100mL)

610

3,600

(70 – 37,000)

9,800

(2,100 – 360,000)

2,000

(140 – 14,000)

Note:   1. Unless otherwise specified, data presented are depth-averaged values.

2. Data presented are annual arithmetic means of the depth-averaged results except for E. coli which is annual geometric means.

3. Data in brackets indicate the ranges.

4. cfu – colony forming unit.

 

4.4.4              Starling Inlet coastal waters and mudflat are habitats of ecological importance. They are the main feeding sites for Great Egrets and Little Egrets nesting on A Chau. Marine water quality at Starling Inlet fully complied with WQOs in recent years. The EPD monitoring station of most relevance is MM1. A summary of the recently published EPD marine water monitoring data collected at MM1 are presented in Table 4-2.

 

Table 42     Summary of EPD Marine Water Quality Monitoring Data at Starling Inlet Monitoring Station MM1 between 2004 and 2006

Parameter

WQO

2004

2005

2006

Dissolved Oxygen (mg/L)

≥ 4.0

8.0

(5.3 – 10.6)

7.2

(4.8 – 12.6)

7.9

(6.0 – 11.0)

pH

6.5 – 8.5

8.3

(8.1 – 8.5)

8.3

(8.0 – 8.7)

8.2

(7.9 – 8.4)

Total Inorganic Nitrogen (mg/L)

≤ 0.3

0.10

(0.03 – 0.28)

0.17

(0.04 – 0.43)

0.13

(0.03 – 0.31)

Unionised Ammonia (mg/L)

≤ 0.021

0.006

(0.003 – 0.020)

0.007

(0.003 – 0.019)

0.004

(0.001 – 0.007)

E. coli (cfu/100mL)

610

44

(2 – 360)

96

(20 – 930)

39

(3 – 4,300)

Note:   1. Unless otherwise specified, data presented are depth-averaged values.

2. Data presented are annual arithmetic means of the depth-averaged results except for E. coli which is annual geometric means.

3. Data in brackets indicate the ranges.

4. cfu – colony forming unit.

 

River Water Quality

 

4.4.5              The Study Area includes Shenzhen River, the lower reaches of River Indus and River Ganges, and Lin Ma Hang Stream.

 

4.4.6              Shenzhen River is the boundary river between Hong Kong and Shenzhen, and drainage outlets of various rivers in the two places. Its tributaries include River Indus, River Beas and River Ganges. It is highly polluted by industrial and domestic discharges due to the fast development of industry and residential buildings in Shenzhen. In recent years, Hong Kong and Shenzhen governments jointly completed the three-stage Shenzhen River Regulation Project. However, by field observations, the river water quality of Shenzhen River remained poor. Shenzhen River flows into Inner Deep Bay estuary, so its water quality has significant effect on the water quality of Mai Po Ramsar Site. A summary of the water qualities of various sections of Shenzhen River from 2006 to 2007 is presented in Table 4-3.


Table 43     Summary of River Water Quality Monitoring Data at Various sections of Shenzhen River between 2006 and 2007

Parameters

WQO

Shenzhen River Sections

Shenzhen River Mouth

Ta Sha Lok

Man Kam To

Ganges River Mouth

2006

2007*

2006

2007*

2006

2006

pH

6.0 – 9.0

6.86

7.25

6.81

6.90

6.71

6.93

DO (mg/L)

≥ 4

4.32

6.99

1.58

3.72

2.71

3.87

BOD5 (mg/L)

≤ 5

9.73

7.32

28.95

25.49

14.26

18.82

SS (mg/L)

≤ 20

43.73

51.87

66.02

41.86

62.30

69.19

Note:   1.Data source: EM&A monitoring data of Shenzhen River Regulation Project Stage III Contract C (長江水資源保護科學研究所, 2007).

            2. The 2007 data indicate Jan to May 2007 only.

            3. Data for Chemical Oxygen Demand (COD) were not available.

 

4.4.7              River Indus and River Ganges flow into Shenzhen River. Downstream of Rivers Indus and Ganges are included in the Study Area. In field observations during wet season, the river bank of River Ganges turned into a marsh supporting various residential waterbirds. At present, the river water quality monitoring conducted by EPD provides spatial and temporal river water quality data, and these data may be used to represent the baseline water quality conditions of Rivers Indus and Ganges. The EPD river quality monitoring stations of most relevance for downstream of River Indus and River Ganges are IN1 and GR1 respectively. The recently published EPD river water monitoring data collected at IN1 and GR1 are summarized in Table 4-4 and Table 4-5.

 

Table 44     Summary of EPD River Water Quality Monitoring Data at downstream of River Indus in the Deep Bay Water Control Zones between 2003 and 2006

Parameters

WQO

2003

2004

2005

2006

pH

6.58.5

7.2

(6.9 – 7.9)

7.1

(6.7 – 7.3)

7.1

(6.8 – 7.6)

7.2

(6.6 – 7.3)

BOD5 (mg/L)

3

5

(4 – 20)

15

(5 – 32)

11

(4 – 37)

7

(1 – 29)

COD (mg/L)

15

24

(12 – 44)

30

(17 – 78)

31

(15 – 58)

26

(10 – 60)

SS (mg/L)

≤ 20

34

(9 – 77)

37

(7.6 – 440)

34

(12 – 63)

25

(7 – 88)

DO (mg/L)

≥ 4

5.2

(2.5 – 11.8)

3.9

(1.4 – 7.2)

3.6

(1.6 – 9.8)

3.8

(1.6 – 7.4)

E. coli

(cfu/100mL)

≤1000

78,000

(11,000 –

3,000,000)

190,000

(25,000 – 2,900,000)

320,000

(18,000 – 4,200,000)

140,000

(6,400 – 2,600,000)

Ammonia-nitrogen (mg/L)

Annual average ≤0.021

2.45

(0.41 – 11.00)

5.85

(0.98 – 18.00)

5.80

(1.10 – 17.00)

5.35

(0.31 – 21.00)

Nitrate-nitrogen (mg/L)

--

1.65

(0.01 – 3.90)

1.05

(0.01 – 3.60)

1.00

(0.01 – 2.40)

1.20

(0.01 – 4.20)

Aluminium (µg/L)

(a) Waste discharges shall not cause the toxins in water to attain such levels as to produce significant toxic carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms, with due regard to biologically cumulative effects in food chains and to toxicant interactions with each other.

(b) Waste discharges shall not cause a risk to any beneficial uses of the aquatic environment.

225

(80 – 610)

270

(90 – 2,400)

290

(70 – 640)

140

(50 – 370)

Cadmium (µg/L)

0.1

(0.1 – 0.9)

0.1

(0.1 – 1.0)

0.1

(0.1 – 0.2)

0.1

(0.1 – 0.2)

Chromium (µg/L)

1

(1 – 5)

5

(1 – 21)

4

(1 – 19)

3

(1 – 15)

Copper (µg/L)

6

(2 – 7)

8

(3 – 50)

8

(3 – 16)

6

(2 – 13)

Lead (µg/L)

3

(1 – 6)

3

(1 – 40)

3

(1 – 10)

3

(1 – 7)

Zinc (µg/L)

90

(40 – 250)

75

(30 – 750)

100

(50 – 1,400)

80

(40 – 190)

Note:   1. WQO follows WPCO Cap.358R.

2. Data presented are in annual medians of monthly samples, except those for E. coli which are in annual geometric means.

3. Figures in brackets are annual ranges.

4. cfu – colony forming unit

 

Table 45     Summary of EPD River Water Quality Monitoring Data at downstream of River Ganges in the Deep Bay Water Control Zone between 2003 and 2006

Parameters

WQO

2003

2004

2005

2006

pH

6.58.5

7.4

(7.0 – 7.7)

7.4

(6.9 – 7.7)

7.4

(7.3 – 8.0)

7.6

(6.8 – 8.1)

BOD5 (mg/L)

3

26

(3 – 320)

16

(8 – 95)

32

(8 – 74)

38

(4 – 170)

COD (mg/L)

15

60

(17 – 400)

49

(37 – 150)

78

(16 – 170)

60

(7 – 1,100)

SS (mg/L)

≤ 20

195

(33 – 520)

79

(11 – 340)

29

(17 – 720)

50

(23 – 660)

DO (mg/L)

≥ 4

5.1

(1.8 – 9.6)

3.9

(1.6 – 6.4)

4.8

(2.2 – 8.0)

6.2

(1.8 – 8.0)

E. coli

(cfu/100mL)

≤1000

59,000

(3,700 – 830,000)

130,000

(27,000 – 700,000)

120,000

(9,000 – 1,600,000)

230,000

(34,000 – 1,700,000)

Ammonia-nitrogen (mg/L)

Annual average ≤0.021

22.00

(3.50 – 110.00)

17.50

(3.80 – 83.00)

20.50

(4.20 – 61.00)

36.00

(3.10 – 210.00)

Nitrate-nitrogen (mg/L)

--

0.14

(0.01 – 0.93)

0.21

(0.01 – 1.60)

0.25

(0.01 – 1.60)

0.28

(0.01 – 1.30)

Aluminium (µg/L)

(a) Waste discharges shall not cause the toxins in water to attain such levels as to produce significant toxic carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms, with due regard to biologically cumulative effects in food chains and to toxicant interactions with each other.

(b) Waste discharges shall not cause a risk to any beneficial uses of the aquatic environment.

290

(160 – 960)

210

(50 – 540)

165

(70 – 1,300)

155

(70 – 900)

Cadmium (µg/L)

0.2

(0.1 – 0.4)

0.1

(0.1 – 0.2)

0.1

(0.1 – 0.5)

0.1

(0.1 – 0.2)

Chromium (µg/L)

2

(1 – 4)

1

(1 – 2)

1

(1 – 4)

1

(1 – 6)

Copper (µg/L)

14

(6 – 120)

12

(2 – 38)

8

(4 – 73)

13

(4 – 23)

Lead (µg/L)

5

(2 – 13)

3

(1 – 11)

3

(1 – 31)

2

(1 – 6)

Zinc (µg/L)

125

(30 – 440)

40

(20 – 130)

50

(30 – 900)

40

(20 – 350)

Note:   1. WQO follows WPCO Cap.358R.

2. Data presented are in annual medians of monthly samples, except those for E. coli which are in annual geometric means.

3. Figures in brackets are annual ranges.

4. cfu – colony forming unit

 

4.4.8              From Table 4–4 and Table 4–5 it may be observed that compliance with river water quality objectives in the downstream of Rivers Indus and Ganges is low. The recorded levels of biochemical oxygen demand, suspended solids and Ammonia-nitrogen all exceed the WQOs, and high chemical oxygen demand and E. coli counts further indicate poor water quality in the downstream of Rivers Indus and Ganges.  This is considered to be the result of the direct discharge of sewage from domestic premises.

 

4.4.9              Lin Ma Hang Stream is a natural stream with riparian vegetation. The stream water is clean, slow flowing and relative undisturbed. This stream is listed as a Site of Special Scientific Interest (SSSI), since it is one of the lowland streams recognized as having high ecological value. It supports a very high diversity of primary freshwater fish. A total of 16 species has been recorded and 14 of them are native species which represent nearly 50 percent of the native primary freshwater fish in Hong Kong. This stream also supports a number of rare freshwater fish species, including Rasbora steineri, Rasborinus lineatus and Mastacembelus armatus. Current water quality data of Lin Ma Stream was obtained and summarized in Table 4–6.


Table 46     Summary of Water Quality of Lin Ma Hang Stream in 2006

Parameters

Lin Ma Hang Stream

Downstream

Upstream

DO (mg/L)

7.85

8.15

pH

6.75

6.5

SS (mg/L)

2.75

7

BOD5 (mg/L)

3

3

COD (mg/L)

6

3.5

Ammonia-nitrogen (µg/L)

<10

15

Nitrite-nitrogen (µg/L)

<10

<10

Nitrate-nitrogen (µg/L)

<10

19.5

Zinc (ug/L)

<10

<10

Iron (µg/L)

310

270

Magnesium (µg/L)

605

400

Note:   1. Data source: Stream water quality survey conducted by Ove Arup (2007).

         2. The “<” sign denotes that the actual value was below reporting limit.

 

Drainage Channel

 

4.4.10           The drainage channel besides Ha Tam Shui Hang is included in the Study Area. From field observation, it is a clear and medium-flowing channel covered with vegetation. No data for the water quality of this drainage channel is available. It is at least 250 m away from the proposed construction of boundary fence along the existing boundary road, therefore the proposed works will not affect its water quality.

 

Active Fishponds

 

4.4.11           The Study Area included a large number of active fishponds. They were located at Mai Po, Sam Po Shue, Lok Ma Chau, Hoo Hok Wai, Ta Sha Lok, Nam Hang and Yuen Leng Chai. Except the fishpond at Yuen Leng Chai, other fishponds are actively managed for rearing freshwater fish. The fishpond at Yuen Leng Chai was a restored fishpond, being as one mitigation measure for ecological impact in the Shenzhen River Regulation Project Stage III. According to the EM&A Report, the fishpond habitat was completely restored in September 2006.

 

4.4.12           Since most of the fishponds within the Study Area were proprietary, data for water quality of these fishponds was not available. Water quality monitoring data for three fishponds located near the boundary fence in Lok Ma Chau area was available and summarized in Table 4-7.

Table 47     Summary of Water Quality of Fishpond in Lok Ma Chau area

Parameter

Fishpond

Dissolved Oxygen (mg/L)

4.1

(1.8 – 7.1)

Turbidity (NTU)

54.6

(6.6 – 206)

Suspended Solid (mg/L)

88

(11 – 1700)

Note:   1. Data source: Water Quality Monitoring Results for KCR Lok Ma Chau Spurline conducted by Hyder (2003).

            2. Samples were taken at water surface, time period from Dec 2002 to Aug 2003.

 

4.4.13           From the monitoring results of the fishponds shown in Table 4-7, it may be observed that the high turbidity and level of suspended solid indicate poor water quality in the fishponds. Level of dissolved oxygen may be maintained by active air pumping.

 

4.5                   Water Sensitive Receivers

 

4.5.1              The identified water sensitive receivers within the Study Area include Lin Ma Hang Stream SSSI, wetlands and active fishponds adjacent to the proposed boundary fence and patrol road. The Shenzhen River, River Indus, River Ganges, Inner Deep Bay and Starling Inlet are the indirect water sensitive receivers.

 

4.6                   Impact Assessment

 

Identification and Evaluation of Impacts during Construction Phase

 

4.6.1              Potential sources of impacts on water quality during the construction phase include site preparation, formation of patrol roads, concreting work, demolition of fence, stockpiling and site depots.

 

4.6.2              Preparation of land for construction of fence and roads will involve excavations and the removal of surface vegetation. These may lead to soil erosion releasing high level of organic matters into adjacent watercourses and fishponds during the wet season. Increased surface runoff with high suspended solids loadings may also be resulted.

 

4.6.3              Asphalt laying and concreting work are required in the formation of patrol roads and fence footing respectively. In case of asphalt/concrete spillage or washdown, water quality of adjacent fishponds and watercourses will be threatened due to the present of contaminants and changes in pH. Level of suspended solids and turbidity will also be increased. These may create toxic conditions for aquatic life.

 

4.6.4              Demolition of existing boundary fence and checkpoints may cause water pollution due to accidental drop of waste materials into adjacent watercourses. Moreover, demolition may require spraying of water for dust suppression. This may generate surface runoff consisting suspended solids and greases.

 

4.6.5              Temporarily stockpile required during construction may generate site surface runoff as a result of daily activities. This might be exacerbated during rainstorms, generating high levels of sediments discharged into fishponds and streams.

 

4.6.6              Site depots are required for maintenance and repair services for equipments on site. These will include storage and use of engines, hydraulic oil, chemicals and lubricants. Spillage and stormwater runoff from site depots, if directly discharged into nearby watercourses, will cause contamination of water. Provision of chemical toilets is also required on site. Domestic sewage generate at the outfall will affect water quality by the increase in E. coli and BOD.

 

4.6.7              The various construction activities and their associated impact on water quality described in the above sections are summarized in Table 4-8.

Table 48     Summary for Identification and Evaluation of Potential Impacts on Water Quality during Construction

Activity

Effect

Site preparation

Soil erosion and surface runoff. Increase in suspended solids and organic matters.

Formation of patrol roads & concreting work

Spillage or washdown of asphalt and concrete. Change in pH and increase in suspended solids.

Demolition of fence and checkpoints

Accidental drop of waste materials into water causing contamination; Spraying of water for dust suppression causing runoff of suspended solids.

Temporarily stockpile

Site surface runoff causing discharge of high levels of sediment

Site depots & Chemical toilets

Spillage and runoff of chemicals, oil and grease; Domestic sewage discharge.

 

Identification and Evaluation of Impacts during Operational Phase

 

4.6.8              In the operational phase of boundary fence and patrol roads, discharges or water polluting activities is not anticipated and therefore there will be no impact on water quality by the Project.

 

4.6.9              During operation, sanitary facilities provided only in the proposed checkpoint at Shek Chung Au will generate domestic sewage. If directly discharged into Mirs Bay, rivers or streams, such domestic sewage will affect water quality by the increase in E. coli and BOD.    

 

4.6.10           With appropriate mitigation measures, there will be no impact on water quality by domestic sewage from sanitary facilities.

 

4.7                   Mitigation of Impacts

 

Construction Phase

 

4.7.1              Potential water quality impacts primarily relate to the uncontrolled surface runoff and discharge of silts during construction. Good site practices in addition to the implementation of mitigation measures would minimize the impact to the surrounding water environment.

 

General Prevention and Precaution Measures

 

·         The site should be confined to avoid silt runoff from the site;

·         No discharge of silty water into the river, stream or drainage channel within and in the vicinity of the site;

·         Any soil contaminated with chemicals/oils shall be removed from site and the void created shall be filled with suitable materials;

·         Stockpiles to be covered by tarpaulin to avoid spreading of materials during rainstorms;

·         Suitable containers shall be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport;

·         Chemical waste containers shall be labelled with appropriate warning signs in English and Chinese to avoid accidents.  There shall also be clear instructions showing what action to take in the event of an accidental;

·         Storage areas shall be selected at safe locations on site and adequate space shall be allocated to the storage area;

·         Any construction plant which causes pollution to the water system due to leakage of oil or fuel shall be removed off-site immediately;

·         Spillage or leakage of chemical waste to be controlled using suitable absorbent materials;

·         Chemicals will always be stored on drip trays or in bunded areas where the volume is 110% of the stored volume;

·         Regular clearance of domestic waste generated in the temporary sanitary facilities to avoid waste water spillage; and

·         Temporary sanitary facilities to be provided for on-site workers during construction.

 

Concreting Work

 

4.7.2              A temporary drainage channel and associated facilities should be provided to collect the runoff generated and prevent concrete-contaminated water from entering watercourses. Adjustment of pH can be achieved by adding a suitable neutralising reagent to wastewater prior to discharge.

 

4.7.3              For the fence footing works site in the proximity of Lin Ma Hang Stream SSSI, the concreting works should be temporarily isolated with proper methods, such as by placing of sandbags or silt curtains with lead edge at bottom and properly supported props, to prevent adverse impacts on the water quality of the natural stream.

 

Soil Excavation and Stockpiling

 

4.7.4              Excavated soil which needs to be temporarily stockpiled should be stored in a specially designated area and provided with a tarpaulin cover to avoid runoff into the drainage channels.

 

Site Depot

 

4.7.5              All compounds in works areas should be located on areas of hard standing with provision of drainage channels and settlement ponds where necessary to allow interception and controlled release of settled/treated water. Hard standing compounds should drain via an oil interceptor. The oil interceptor should be regularly inspected and cleaned to avoid wash-out of oil during storm conditions. A bypass should be provided to avoid overload of the interceptor's capacity. Any contractor generating waste oil or other chemicals as a result of his activities should register as a chemical waste producer. Disposal of the waste oil should be done by a licensed collector.

 

4.7.6              Good housekeeping practices should be implemented to minimise careless spillage and to keep the storage and the work space in a tidy and clean condition. Appropriate training including safety codes and relevant manuals should be given to the personnel who regularly handle the chemicals on site.

 

 

Construction of Checkpoints

 

4.7.7              Sewage system should be constructed to divert domestic sewage, which will be generated from the sanitary facilities provided in the new checkpoint at Shek Chung Au, to public sewer connected to government sewage treatment facilities.

 

Operational Phase

 

4.7.8              With a sewage system constructed, no direct discharge or accidental spillage of domestic sewage would be expected during the operation of the new Checkpoint at Shek Chung Au. No additional pollution loads on Mirs Bay would be anticipated. Thus, no impact is anticipated during the operation of the Project.

 

Residual Impacts

 

4.7.9              No residual impact is anticipated during the construction or operation of the Project.

 

Cumulative Impacts

 

4.7.10           No cumulative impact is expected.

 

4.8                   Environmental Monitoring and Audit

 

4.8.1              A site auditing programme at weekly intervals is proposed to ensure mitigation measures during construction phase will be implemented to protect the water environment in the sensitive area from being further degraded. The audit details will be given in the EM&A Manual.

 

4.9                   Conclusions

 

4.9.1              Water quality impacts during the construction phase will be controlled through the implementation of good site practice. With appropriate mitigation and precautions measures in place during construction, there should be relatively minor impacts associated with this project during or following construction. In the operation phase, the impact from sanitary facilities is anticipated to be negligible.

 

4.10               References

 

Environmental Protection Department, 2007a. Marine Water Quality in Hong Kong in 2006. Monitoring Section Waste and Water Science Group EPD, the Government of HKSAR.

 

Environmental Protection Department, 2007b. River Water Quality in Hong Kong in 2006. Monitoring Section Waste and Water Science Group EPD, the Government of HKSAR.

 

Environmental Protection Department, 2006a. Marine Water Quality in Hong Kong in 2005. Monitoring Section Waste and Water Science Group EPD, the Government of HKSAR.

 

Environmental Protection Department, 2006b. River Water Quality in Hong Kong in 2005. Monitoring Section Waste and Water Science Group EPD, the Government of HKSAR.

 

Environmental Protection Department, 2005a. Marine Water Quality in Hong Kong in 2004. Monitoring Section Waste and Water Science Group EPD, the Government of HKSAR.

 

Environmental Protection Department, 2005b. River Water Quality in Hong Kong in 2004. Monitoring Section Waste and Water Science Group EPD, the Government of HKSAR.

 

Environmental Protection Department, 2004. River Water Quality in Hong Kong in 2003. Monitoring Section Waste and Water Science Group EPD, the Government of HKSAR.

 

Environmental Protection Department, 1991. Technical Memorandum Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters. EPD Water Policy Group. The Government Printer, Hong Kong.

 

Hong Kong Environmental Protection Department, 1997. Technical Memorandum on Environmental Impact Assessment Process. Printing Department, Hong Kong Government.

 

Hyder Consulting Limited, 2003. KCRC East Rail Extensions – Sheung Shui to Lok Ma Chau – Monthly EM&A Report. Kowloon-Canton Railway Corporation, Hong Kong.

 

Ove Arup & Partners Hong Kong Limited, 2007. EIA Report for North East New Territories (NENT) Landfill Extension. Environmental Protection Department, Hong Kong.

 

Planning Department Hong Kong Government, 1994. Hong Kong Planning Standards and Guidelines: Chapter 9 Environment.

 

長江水資源保護科學研究所, 2007。治理深圳河第三期第二階段合同C工程:環境監察與審核月報。深圳市治理深圳河辦公室,中國。

 

 

 


5                        WASTE MANAGEMENT IMplications

 

5.1                   Introduction

 

5.1.1              This section of the EIA report identifies the potential wastes arising from the construction and demolition of the proposed boundary fences and boundary patrol roads and provides an assessment of the potential environmental impacts associated with the handling and disposal of these wastes as per the requirements of the Study Brief item 3.4.4. This section also provides an assessment of possible land contamination within the Project Area.

 

5.1.2              The options for reuse, minimization, recycling treatment, storage, collection, transport and disposal of wastes arising from the Project have been examined. Where appropriate, procedures for waste reduction and management are considered and environmental control measures for avoiding and minimizing the potential impacts are recommended with reference to the applicable waste legislation and guidelines.

 

5.2                   Environmental Legislation and Standards

 

Legislation

 

5.2.1              The following legislation encompasses the storage, collection treatment and disposal of the wastes arising from the Project:

 

·             Waste Disposal Ordinance (Cap 354);

·             Waste Disposal (Chemical Waste) (General) Regulation (Cap 354);

·             Waste Disposal (Charges for Disposal of Construction Waste) Regulations (Cap 354);

·             Land (Miscellaneous Provisions) Ordinance (Cap 28); and

·             Public Health and Municipal Services Ordinance (Cap 132) - Public Cleansing and Prevention of Nuisances (Urban Council) and (Regional Council) By-laws.

 

Guidelines

 

5.2.2              The following documents, guidelines and circulars provide guidance on waste management as follows:

 

·         Waste Reduction Framework Plan, 1998 to 2007, Planning, Environment and Lands Bureau, Government Secretariat (5 November 1998);

·         Environmental Guidelines for Planning in Hong Kong (1990), Hong Kong Planning and Standards Guidelines, Hong Kong Government;

·         New Disposal Arrangements for Construction Waste (1992); Environmental Protection Department & Civil Engineering Department;

·         Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), Environmental Protection Department;

·         Works Branch Technical Circular No. 12/2000, Fill Management;

·         Works Branch Technical Circular No. 2/93, Public Dumps;

·         Works Branch Technical Circular No. 16/96, Wet Soil in Public Dumps; and

·         Environment, Transport and Works Bureau Technical Circular (Works) No. 19/2005, Environmental Management on Construction Sites.

 

5.3                   Assessment Methodology

 

5.3.1              The potential environmental impacts due to the management of the wastes arising from the Project have been assessed according to the criteria presented in Annex 7 and 15 of the EIAO-TM and are summarized as follows:

 

·         Estimation of the types and quantities of the wastes to be generated;

·         Assessment of the secondary environmental impacts due to the management of waste with respect to potential hazards, air and odour emissions, noise, wastewater discharges and traffic; and

·         Assessment of the potential impacts on the capacity of waste collection, transfer and disposal facilities.

 

5.4                   Construction Waste Impact

 

Potential Sources of Impact

 

5.4.1              The Project will involve the following works:

 

5.4.2              Construction of a secondary boundary fence (SBF) along the existing boundary patrol road (BPR);

·         Conversion of the existing maintenance services road along the Shenzhen River bank into new section of BPR with a primary boundary fence (PBF) and an SBF;

·         Construction of BPR with a PBF and an SBF;

·         Construction of a checkpoint at the entrance to the Sha Tau Kok town (“Gate One”);

·         Replacement of an existing checkpoint at Pak Hok Chau;

·         Removal of 4 existing checkpoints at Lok Ma Chau, Sha Ling, Ping Che and Shek Chung Au; and

·         Removal of the existing PBF along sections where existing PBF will be replaced by new sections of PBF.

 

5.4.3              The works to be carried out for the proposed Project will result in the generation of a variety of wastes which may include:

 

·         Site clearance waste;

·         Construction and demolition materials;

·         Chemical waste; and

·         General refuse.

 

5.4.4              If not properly managed, the handling and disposal of these wastes may cause adverse environmental nuisance and impacts. The nature of each of these wastes is discussed below.

 

Site Clearance Waste

 

5.4.5              Most part of the land requirement limit of the Project is mainly the existing boundary roads or assess roads, except the two new sections of the BPR with a PBF and an SBF along the Shenzhen River side to the north of Pak Fu Shan and northwest of Lin Ma Hang Village. As these areas are currently rural areas and covered by vegetation, the site clearance wastes may include:

·         Topsoil

·         Grass

·         Low and tall shrub

·         Trees

 

Construction and Demolition Materials

 

5.4.6              Construction and demolition (C&D) material arising from the proposed Project may include:

 

·         Excavated materials from construction of footing of fence and checkpoint structures

·         Waste timber formwork

·         Spent concrete and cement screening

·         Material and equipment wrappings

·         Damaged / surplus construction materials

·         Concrete and structural steel from checkpoints to be removed

·         Ceramic / ceiling tiles

·         Glass, wood and plastics of fixtures and scaffolding

·         Trimmings from scaffolding

·         Wiring

 

Chemical Waste

 

5.4.7              Plant and vehicle servicing will likely be the primary source of chemical waste in the construction period. This may include:

 

·         Scarp battery or spend acid / alkali from their maintenance

·         Used engine oils hydraulic fluids and waste fuel

·         Spent mineral oils / cleaning fluids from mechanical machinery

·         Spent solvents / solutions, some of which may be halogenated, from equipment cleaning activities

 

General Refuse

 

5.4.8              Municipal sold waste will be generated by workers during the construction period, and the waste may include:

 

·         Food waste

·         Packaging

·         Wastepaper

 

5.4.9              In the operational phase, small amount of municipal solid waste, such as packaging and wastepaper will be generated at the new and replacement checkpoints.

 

5.5                   Evaluation of Impacts

 

5.5.1              The main construction works of the boundary fences and patrol roads is scheduled to commence in 2009 with an occupation date of 2012. The estimates of wastes arising from the construction activities and the potential environmental impacts associated with the handling, storage, transport and disposal of these wastes are discussed below.

 

Site Clearance Waste

 

5.5.2              The major construction works for the Project include the PBF and SBF along the existing BPR, “Gate One” checkpoint in Sha Tau Kok and the new section of BPR along the Shenzhen River side to the north of Pak Fu Shan and northwest of Lin Ma Hang Village. As the proposed location of Checkpoints to be constructed, replaced or removed and the existing BPR are currently used as roads, site clearance would be limited to the removal of a vegetation and topsoil for the construction of the new section of BPR. Approximately 140m3   of site clearance wastes will be generated. These wastes are anticipated to be reused as far as possible for landscaping purposes on-site. However, due to the limited landscaping of the checkpoints, BPR and boundary fences, those materials cannot be reused on-site should be separated and disposed of at designated landfill.

 

Construction & Demolition Materials

 

5.5.3              The volume of C&D materials generated from excavation, scaffolding works, fence installation, checkpoints removal and construction of new and replacement checkpoints is estimated as approximately 72,200m3. Approximately 70000m3 from these are excavated materials likely to be some breaking up hard paving, soil with some rock. These excavated materials will be reused as backfilling on-site, wherever possible, to minimize the waste amount of disposal off-site to a public fill facility.

 

5.5.4              C&D materials should be sorted into inert C&D materials, metals, timber and non-inert C&D materials. The generation of C&D materials should be minimized while the reuse of inert C&D materials on-site should be maximized. Inert materials should be stockpiled for reuse in the construction as far as possible. It is estimated that the remaining 2,200m3 of C&D materials will be generated from the demolition of fence and checkpoints, such as old fences and fixtures with low recycle value. These C&D materials will be reused or recycled as far as possible in order to minimize the volume of C&D waste disposing to landfill. Disposal to landfill will be the last resort. The contractor is responsible for the separation of the C&D materials and transfer of these materials to the public filling areas or landfills. The contractor is also encouraged to reuse the C&D materials in other proper sites according to contract provision.

 

Chemical Waste

 

5.5.5              Waste oil and solvent from plant and vehicles are considered to be the major chemical waste produced in the construction phase. It is difficult to quantify the amount of chemical waste, if any, generated as this will depend on the works within the Project Area. It is expected that the quantity of chemical waste, such as lubricating oil and solvent, produced from plant maintenance will be minimum. These wastes will be readily collected by a licensed waste haulier and send to the Chemical Waste Treatment Centre at Tsing Yi or other approved treatment facility.

 

5.5.6              Storage, handling, transport and disposal of chemical waste should be arranged in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Waste published by the EPD. As the anticipated chemical waste generation is in small quantity, the potential environmental impacts arising from the storage, handling and disposal can be negligible.

 

General Refuse

 

5.5.7              According to Figure 11 in EPD’s Monitoring of Solid Waste in 1999, the projection of per capita generation rates of commercial and industrial waste in year 2011 is 0.55 kg/employee/day (the employment size of this value includes all sectors under the Hong Kong Standard Industrial Classification). This value is adopted to estimate the quantity of municipal solid waste generated on-site by workforce.

 

5.5.8              The total volume of waste generated depends on the number of workers to be employed on-site during the course of the works from 2009 to 2012. It is anticipated that the number of workers and site staff to be employed is about 100 – 200. Considering there will be 200 workers work on-site 6 days per week, the amount of municipal solid waste generated will be approximately 660 kg/week.

 

5.5.9              Municipal solid waste generated by site workers will have potential impacts in terms of nuisance, insects and vermin if there is no appropriate management. This may give rise to adverse environmental impacts to both workers and nearby villagers. Therefore disposal of refuse at the sites other than approved waste transfer or disposal facilities will be prohibited. Effective collection of site wastes will prevent waste materials being blown around by wind, or creating an odour nuisance or pest and vermin problem. Waste storage areas should be well maintained and cleaned regularly. Contractor should undertake the responsibility of disposal of unwanted materials at such a frequency to avoid nuisance, according to the general avoidance of nuisances measures required under the Contract. The measures include set-up a temporary refuse collection facilities by the Contractor and store the waste in appropriate containers prior to collection and disposal.

 

5.5.10           With the implementation of good waste management practices at the site, adverse environmental impacts are not expected to arise from the storage, handling and transportation of workforce wastes.

 

5.6                   Mitigation Measures

 

Introduction

 

5.6.1              Recommendations on recycling, storage, transportation and disposal measures are listed in this section for avoiding or minimizing the potential adverse impacts associated with waste arising from the Project. The recommendations should be incorporated into an on-site waste management plan for the construction works to be undertaken by the Contractor. The waste management plan should incorporate site-specific factors, such as the designation of area for the segregation and temporary storage of reusable and recyclable materials. 

 

5.6.2              Contractor should undertake the responsibility to ensure that only approved licensed waste collectors are used and that appropriate measures to minimize adverse impacts, including windblown litter and dust from the transportation of these wastes are employed. Moreover, it is also the Contractor’s responsibility to ensure all the necessary waste disposal permits are obtained.

 

 

 

Waste Management Hierarchy

 

5.6.3              Various waste management options are as followed:

 

·         Avoidance and minimization, i.e. not generating waste through changing or improving practices and design;

·         Reuse of materials, thus avoiding disposal (generally with only limited reprocessing);

·         Recovery and recycling, thus avoiding disposal (although reprocessing may be required); and

·         Treatment and disposal, according to relevant laws, guidelines and good practice.

 

5.6.4              This hierarchy should be used to evaluate waste management options, thus allowing waste reduction measures to be introduced at the detailed design stage and carried through to the construction phase.

 

5.6.5              Training and supervision of construction staff should be given at the site to increase awareness and draw attention to waste management issues and the need to minimize waste generation. Training requirement should be included in the site waste management plan.

 

Storage, Collection and Transport of Waste

 

5.6.6              Permitted waste hauliers should be used to collect and transport waste to the appropriate disposal points. Measures to minimize adverse impacts shall be instigated as appropriate and as far as practical, such as:

 

·         Handle and store waste in a manner to ensure that they are held securely without loss or leakage, thereby minimizing the potential for pollution;

·         Use authorized / licensed waste hauliers to collect specific category of waste;

·         Remove waste in a timely manner;

·         Maintain and clean waste storage area regularly;

·         Minimize windblown litter and dust during transportation by either covering trucks or transporting waste in enclosed containers;

·         Obtain the necessary waste disposal permits from the appropriate authorities, if they are required;

·         Disposal waste at licensed waste disposal facilities; and 

·         Maintain records of the quantities of waste generated, recycled and disposed.

 

Site Clearance

 

5.6.7              The topsoil and vegetation removed and excavated material may have to be temporarily stockpiled on-site. Control measures should be taken at the stockpiling area to prevent the generation of dust and pollution of stormwater channels, fish ponds or river channels. However, to eliminate the risk of blocking drains in the wet season, it is recommended that stockpiling of excavated materials during the wet season should be avoided as far as practicable.

 

 

 

 

Dust:

 

·         Wetting the surface of the stockpiled soil with water when necessary, especially during the dry season;

·         Covering the stockpiled soil with sheets;

·         Minimizing disturbance of the stockpiled soil; and

·         Enclosure of stockpiling area.

 

Water Quality:

 

·         Installation of silt traps for the surface water drainage system; and

·         Covering stockpiled material with tarpaulin during heavy rainstorm.

 

5.6.8              Potential dust impacts due to the haulage of site clearance / excavated materials should be minimized by employing the following control measures:

 

·         Dropping heights for those materials should be controlled to a practical height to minimized the fugitive dust arising from unloading;

·         Materials should not be loaded to a level higher than the side and tail boards, and should be dampened or covered before transport;

·         The travelling speed should be reduced to 10km hr-1 to reduce dust dispersion and re-suspension from the operation haul trucks; and

·         Wheel washing facilities should be installed and used by all vehicles leaving the Project Area.

 

Construction & Demolition Materials

 

5.6.9              In order to minimize waste generation and to keep environmental impacts within acceptable levels, environmental control measures are recommended.

 

5.6.10           Careful design, planning and good site management can minimize over-ordering and generation of waste materials such as concrete, mortars and cement grouts. The design of formwork should maximize the use of standard wooden panels so to achieve high reuse levels. Alternatives such as steel formwork or plastic facing should be considered to increase the potential for reuse.

 

5.6.11           The Contractor should recycle as much of the C&D materials as possible on-site. Proper segregation of waste on-site will increase the feasibility of certain components of the waste stream by the recycling contractors. Different areas of the worksite shall be designated for such segregation and storage wherever site conditions permit.

 

5.6.12           Trip-ticket system should be employed to monitor the disposal of C&D material and solid at public filling facilities and landfills, and to control fly-tipping. Government has established a differentiated charging scheme for the disposal of waste to landfill, construction waste sorting facilities and public fill facilities. This will provide additional incentives to reduce the volume of waste generated and to ensure proper segregation of wastes.

 

 

 

Chemical Waste

 

5.6.13           For those processes which would generate chemical waste, alternatives which generate reduced quantities or even no chemical waste, or less dangerous types of chemical wastes should be considered.

 

5.6.14           The Contractor should register with the EPD as a Chemical Waste Producer if chemical wastes are produced at the construction site. The guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes should be followed strictly:

 

Containers used for the storage of chemical wastes should:

·         be suitable for the substance they are holding, resistant to corrosion, maintained in good condition, and securely closed;

·         have a capacity of less then 450 litres unless the specification has been approved by EPD; and

·         display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations.

 

The storage and disposal of chemical wastes should:

·         be covered to prevent rainfall entering (water collected within the bund must be tested and disposed as chemical waste if necessary);

·         be arranged so that incompatible materials are adequately separated;

·         be via a licensed waste collector; and

·         be to a facility licensed to receive chemical waste, such as the Chemical Waste Treatment Facility which also offers a chemical waste collection service and can supply the necessary storage containers.

 

5.6.15           Waste Exchange Scheme operated by the Centre of Environmental Technology can assist finding receivers or buyers for the small quantity of chemical waste to be generated from the Project.

 

General Refuse

 

5.6.16           General refuse should be stored in enclosed bins or compaction units separate from C&D materials and chemical wastes. A reputable waste collector should be employed by the Contractor to remove general refuse from the Project Area, separately from C&D wastes, on a daily or every second day basis to minimize odour, pest and litter impacts. Burning of refuse on construction sites is prohibited by law.

 

5.6.17           In the operational phase, small amount of municipal waste may be generated at checkpoints, but the associated adverse impacts are unlikely under the proper management and no mitigation measures are required.

 

Construction Waste Management Plan

 

5.6.18           A construction waste management plan (CWMP) should be prepared and developed by the contractor to ensure proper collection, treatment and disposal of waste on site. This CWMP will also take into account the requirement to handle chemical wastes on site which will need to be managed by a licensed waste collection contractor.

 

5.7                   Land Contamination

 

Land contamination Environmental Legislation and Standards

 

5.7.1              Comprehensive desktop study for land contamination assessment was carried out during March to June 2008. The following legislation, guidelines and guidance notes were in force for land contamination assessment:

 

·         Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM);

·         Guidance Notes for Contaminated Land Assessment and Remediation (2007);

·         Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management (dated December 2007); and

·         EPD Guidance Notes for Investigation and Remediation of Contaminated Sites of: Petrol Filling Stations; Boatyards; and Car Repair/Dismantling Workshops (1999).

 

Assessment Methodology

 

5.7.2              In accordance with Guidance Note for Contaminated Land Assessment and Remediation, an assessment evaluation should:

 

·         provide a clear and detailed account of the present use of the land and the relevant past land use history, in relation to possible land contamination;

·         identify potential contamination and associated impacts, risks or hazards; and

·         if required, submit a plan to evaluate the actual soil contamination conditions.

 

5.7.3              To identify and evaluate the potential contamination impacts within the land requirement limit of the Project, the tasks listed below have been done:

 

·         Desktop appraisal to review the historic and current land uses; and

·         Walk-over site survey to confirm the current land uses.

 

Desktop Appraisal

 

5.7.4              Aerial photographs from the Aerial Photograph Library (APL) of the Civil Engineering and Development Department (CEDD) were reviewed and collated. As the Project area is under the jurisdiction of the Hong Kong Police Force (HKPF) and Drainage Services Department (DSD), questionnaires for the land use history and possible site contamination (Appendix E-1A) were sent to the mentioned two authorities to acquire and confirm the historic and present information needed.

 

Walk-over Site Survey

 

5.7.5              Walk-over site surveys were carried out to verify the desktop appraisal and to identify any contamination hotspots within the land requirement limit along the proposed alignment of BPR, PBF, SBF and the checkpoints to be replaced, constructed and removed. All accessible area were visited as far as practicable to collect information about the current conditions, land uses, activities undertaking within the land requirement limit. Photographs were taken wherever possible and presented in Appendix E-2.

 

Potential for land contamination

 

Desktop Appraisal

 

5.7.6              Aerial photographs from 1940s to 2006, whichever available in the APL of CEDD, were studied. The historical aerial photos covering the land requirement limit were reviewed and the land use was evaluated as summarized in Table 5-1.

Table 51     Reviewed Historical Aerial Photographs and Land Use in the Land Requirement Limit

Section 1

 

 

Year

Ref. No

Height (ft)

Land Use

1949

Y02582, Y02584-Y02585

8000

Intertidal mudflat

1986

A07477

4000

Road, Checkpoint

1995

CN10607, CN10523R

3000

Road, Checkpoint

2000

CN27657R, CN27659R

3000

Road, Checkpoint

2002

CW42719, CW42740R

4000

Road, Checkpoint

2004

CW54625R

20000

Road

Section 2

 

 

Year

Ref. No

Height (ft)

Land Use

1973

4779-4780, 4786-4787

6000

Road near fish pond and agricultural land

1986

A06238, A06240

4000

Road, Checkpoint

1995

CN10523R, CN10467R-CN10468

3000

Road, Shenzhen River, DSD Maintenance Access

2000

CN27661R,CN27663R, CN27665, CN27667R

3000

Road, DSD Maintenance Access, Checkpoint

2002

CW42710R, CW42713R, CW42715R

4000

Road, DSD Maintenance Access

2004

CW54625R-CW54626R

20000

Road, DSD Maintenance Access

Section 3

 

 

Year

Ref. No

Height (ft)

Land Use

1986

A05593-A05594

4000

Grassland (Proposed PBR near Pak Fu Shan), Road (Existing PBR)

1993

A34391R-A34393R, A36402R-A36403R

4000

Road (Man Kam To to Muk Wu Nga Yiu, Ta Kwu Ling to Chuk Yuen), Checkpoint, Grassland and Shenzhen River

1995

CN10421R-CN10422R

3000

Road (Ma Kam To to Lo Shue Ling)

2000

CN28518R, CN28523R, CN28527R, CN28530R

4000

Road (Lo Wu to Chuk Yuen), Checkpoint

2002

CW42701R, CW42703R, CW42704R, CW42706R, CW42708R

4000

Road (Lo Wu to Chuk Yuen), Checkpoint

2004

CW54652R, CW54626R

20000

Road, Grassland, Checkpoint

Section 4

 

 

Year

Ref. No

Height (ft)

Land Use

1986

A05584

4000

Road near Sha Tau Kok Control Point, Grassland

1995

CN10423R

3000

Road near Sha Tau Kok Control Point

2002

CW42795R

4000

Road near Sha Tau Kok Control Point

 

5.7.7              From the aerial photos available, the area of Section 1, Mai Po, was still intertidal mudflat and rural area in the 1940s, while boundary patrol road was found from the photos taken in 1980s. For the remaining Section 2, 3 and 4, upon the photos from 1970s or 1980s, the existing boundary patrol can be identified easily. No recognised industries with potential for causing land contamination as listed in the EPD Guidance Note were found within or in the vicinity of the land requirement limit of construction, removal and replacement of the Boundary Fences and Checkpoints. Detailed alignment and land requirement plan are shown in the Contamination Assessment Plan (CAP) submitted to and reviewed by EPD in December 2008.

 

5.7.8              Most of the area along the proposed alignment of boundary fences was used as road and checkpoints throughout at least the last 20 years, since 1986. Aerial photographs of parts of the study area were missing or not available in the APL, especially those from 1950s to early 1980s. There was no photo-taking within those areas for that period of time according to the photograph index in the APL, while some were borrowed by other parties.

 

5.7.9              To fill in the information gap of the aerial photograph study, questionnaires were sent to the DSD and HKPF, which the Project area is under their jurisdiction, for the land use history and possible contamination within the Project area. The questionnaire and reply from the DSD and HKPF are shown in Appendix E-1B and E-1C.

 

5.7.10           A nil return as per the questionnaire mentioned in Section 5.7.9 was received from DSD in June 2008 regarding the possible site contamination and land use history of the area of the existing maintenance access along the Shenzhen River bank to the north of the Lok Ma Chau Loop and Hoo Hok Wai, where a new Boundary Patrol Road and Boundary Fences are proposed to be built. The questionnaire was sent again and reply from DSD was received in September 2008 (Appendix E-1B). The existing maintenance access along the Shenzhen River to the north of the Lok Ma Chau was formed under the Shenzhen River Regulation Project Stage 1 while section to the north of Hoo Hok Wai was formed under the Shenzhen River Regulation Project Contract A of Stage 2 and the access have been used since 1997. Under the Shenzhen River Regulation Project (Stage I & II), there is no record of land contamination over the area of the existing maintenance access shown on the Project plan. Most of the land used for the river regulation project was originally fish ponds or landscaping areas. Although the Lok Ma Chau Loop area was filled by contaminated and uncontaminated mud dredged from the old Shenzhen River, the maintenance access was constructed on the embankment formed only by uncontaminated materials. As the works of this Project will only carry out within the required land limit, where limited to the maintenance access, the potential land contamination and hazardous risks are expected to be low.

 

5.7.11           According to the HKPF, the land use of the area before BPR was rural area immediately due south of the boundary with no specific land use, while the area used as checkpoints were rural area within the FCA. The BPR is situated at the boundary between Hong Kong Special Administration Region and Shenzhen while the area located south of the boundary is declared as Closed Area under the Public Order Ordinance, CAP 245 since 1951. For the Checkpoints studied in this assessment, except the “Gate One” Checkpoint, are used to control the access to the FCA. In 1979, British Army units were stationed on the Sino-British border to bolster hard-pressed policeman after a worrying illegal immigration. The BPR and the Checkpoints involved in this Project, except “Gate One” Checkpoint, were built by the British Army along with the old border fence and other security features, such as the observation towers. The Hong Kong Police Force formally took over the BPR and Checkpoints together with other security facilities from the British Army in 1990. After taken over by the Police, materials listed in the questionnaire had not been used, stored or generated in the land requirement limit of boundary patrol road. As to the Checkpoints, only anti-corrosive paints have been used on the drop bars and associated metalwork and electrical wiring for the supply of electricity. Based on the information provided, the area was rural area within FCA with no specific use before taken over by the HKPF. As such, there is no indication of concerned industrial activities and usage, storage or generation of concerned materials listed in the Questionnaire leading to land contamination. The potential land contamination is therefore anticipated to be low.

 

Walk-over Site Survey

 

5.7.12           Walk-over site surveys have been conducted to verify the desk-top appraisal of the current land use of the land requirement limit. Surveys confirmed that majority of the alignment of the Boundary Patrol Road is primarily fenced off by a boundary fence which runs mainly along the northern side of the BPR as shown in Plate 1 – Plate 3 of Appendix E-2. Along the edge of BPR, steep slopes, marshland, fish ponds and private agricultural and poultry farm are commonly found. For the Section 4, the land requirement limit, where the new BPR and boundary fences to be built, is used as road paved with concrete (Plate 4 of Appendix E-2). No visible oil or chemical stains were observed during the site survey.

 

5.7.13           The area along the Shenzhen River bank to the north of the Lok Ma Chau Loop and Hoo Hok Wai is an existing maintenance services road of Drainage Services Department (Plate 5 of Appendix E-2). No visible sign of industrial activity was noted. The area at the Shenzhen River side to the north Pak Fu Shan and northwest of Lin Ma Hang Village are undeveloped rural areas, which were not accessible during the site surveys (Plate 6 of Appendix E-2). The possibility of land contamination in these two areas is considered to be low as there is no recognised industrial land use history.

 

5.7.14           The Pak Hok Chau Checkpoint, which is proposed to be replaced in the Project, is no longer manned according to the HKPF and our site survey. It is located at the border roadside in the plantation / woodland area of Mai Po as shown in Plate 7 of Appendix E-2.

 

5.7.15           For the checkpoints proposed to be removed, Lok Ma Chau Checkpoint and Shek Chung Au Checkpoint are located next to the plantation / woodland area at the roadside (Plate 8 and Plate 9 of Appendix E-2). Ping Che Checkpoint is located next to grassland area (Plate 10 of Appendix E-2) while the Sha Ling Checkpoint is located in the middle of the road with other surface structures, including the shelter, located next to an open storage area (Plate 11 of Appendix E-2). The footings of these Checkpoints would be removed and therefore, limited excavation, approximately 0.3m in depth, will be involved. The land requirement limit for the demolition is estimated to be less than 1m around the surface structures of the Checkpoints to be removed. Without any recognised industrial use of the areas, the possibility of land contamination is anticipated as low.

 

5.7.16           For the new “Gate One” Checkpoint, the area for the surface structures, including the shelter, is currently used as road with concrete paving as shown in Plate 12 and Plate 13 of Appendix E-2. No visible oil or chemical stains were observed in the land requirement limit. Minor excavation, approximately 0.3m in depth will be involved for the construction of footings. Potential land contamination and hazardous risks are expected to be low.

 

Prediction and Evaluation of Environmental Impacts

 

5.7.17           Based on the findings from the desktop appraisal and walk-over site survey, no contaminated sites and industrial activities were identified within or in vicinity of the land requirement limit of the Project. The potential land contamination by previous land use as rural area is anticipated to be minimal. In the operational phase, no industrial activities will be carried out and the completed boundary patrol road will be concrete-paved. The likelihood of land contamination as a result of the boundary fence operation is expected to be minimal. Hence, no adverse environmental impacts on land contamination for the Project are predicted in both construction and operational phase.

 

5.7.18           A Contamination Assessment Plan, which included the aerial photos studied, detailed alignment and land requirement plan, has been subitted to and reviewed by EPD in December 2008.

 

5.8                   Environmental Monitoring and Audit Requirements

 

5.8.1              It is recommended that auditing of each waste stream should be carried out periodically to determine if wastes are managed in accordance with approved procedures and the site waste management plan. The audits should look at all aspects of waste management including waste generation, storage, recycling, treatment, transport and disposal. An appropriate audit programme would be defined as the commencement of any related physical activity undertaken within the Project Area boundary.

 

5.9                   Conclusions

 

Site construction waste

 

5.9.1              The construction activities generate waste types include site clearance, C&D material, chemical waste from the maintenance of construction plant and equipment and general refuse from the workforce. Provided that these wastes are maximally reused, handled, transported and disposed of using approved methods and that the recommended good site practices are followed, adverse environmental impacts are not expected during the construction phase.

 

5.9.2              During operation phase, only small amount of general refuse is expected to be generated and therefore no adverse environmental impact is expected provided that they are stored and disposed properly.

 

Land contamination

 

5.9.3              Based on the available information and results of the desktop appraisal together with the walk-over site survey, potential land contamination for this Project is expected to be insignificant. No adverse environmental impact is expected during operational phase. No further site investigations or laboratory testing are proposed.

 

 

 

 

 


6                        Ecological Impact assessment

 

6.1                   Introduction

 

6.1.1              This Chapter describes the ecological profile of the assessment area for the ecological impact assessment of the potential impacts that may arise from the construction and operation of the secondary boundary fence, the demolition and relocation of some sections of the primary boundary fence, boundary patrol roads and checkpoints.

 

6.1.2              The objectives of this ecological assessment are as follows:

 

·         to establish an ecological baseline for the boundary fence project study area, focusing on key habitats and species present;

·         to assess the ecological impacts of the proposed fencing works;

·         to recommend ecological mitigation measures to reduce or eliminate significant impacts. The order of priority of these measures should be: avoidance, minimization, compensation; and

·         to determine whether residual impacts are acceptable.

 

6.2                   Assessment Area

 

6.2.1              The Assessment Area for ecological surveys covered an area of 500 m radius around the proposed alignment of the construction of the boundary fence, patrol roads and the removal of primary fence in some sections (Figure 6.1).

 

6.2.2              Methodology and the transect routes for fauna survey of the ecological baseline assessment are presented in Appendix F-1 and Figure F1 in Appendix F.

 

6.3                   Sites of Conservation Importance in the Area

 

Wetland Conservation Area (WCA)

 

6.3.1              In order to to conserve the ecological value of the existing contiguous and adjoining active/abandoned fishponds in the landward part of the Ramsar, a Wetland Conservation Area (WCA) was designated by the Town Planning Board (TPB PG-No. 12B) to maintain the ecological vlue of the fishponds which form an integral part of the wetland ecosystem in the Deep Bay Area. It also mitigates the negative impact arising from undesirable land uses and human disturbance, by protecting the ecological resources of the wetland and fishponds and conserves the integrity of the Deep Bay wetland ecosystem. The Mai Po fishponds, ecological mitigation area at Sham Po Shue and part of the Lok Ma Chau fishpond areas are fall within WCA of the Assessment Area. This habitat is an important foraging site for waterbird species, including the globally threathened Black-faced Spoonbill Platalea minor and the ardeids breeding at ajacent egreties.

 

Wetland Buffer Area (WBA)

 

6.3.2              The Wetland Buffer Area is a buffer area of about 500m landward of the WCA boundary. A substantial number of the fishponds within the WBA have been filled or degraded by the presence of open storage use. These degraded areas may be considered as target areas to allow an appropriate level of residential/recreational development so as to provide an incentive to restore some of the lost fishponds (Town Planning Board, 1999). The Assessment Area around Lok Ma Chau and Tai Law Hau are within the WBA, which cover hillside grassland, wet agricultural land and villages.

 

Mai Po Inner Deep Bay Ramsar Site

 

6.3.3              The Mai Po Inner Deep Bay Ramsar Site covers the Mai Po Marshes SSSI (Figure 6.1), the Inner Deep Bay area and the inter-tidal mudflats with 1,500 hectares of wetlands. It was designated as a “Wetland of International Importance” under the Ramsar Convention on 4 September 1995. The Ramsar Site is a natural shallow estuarine area, with extensive inter-tidal mudflats, dwarf mangroves, gei wai and fishponds. These wetlands provide a wide range of habitats to support a high diversity of fauna (Tsim and Lock, 2002), including some rare mammals and restricted-range invertebrates. This habitat is particularly important to migratory waterbirds for roosting and feeding. More than 40,000 waterbirds including a number of globally threatened species stop-over or overwinter at this wetland annually. Moreover, at least 28 globally threatened bird species, including 3 critically endangered, have been recorded in the Ramsar Site.

 

Mai Po Nature Reserve

 

6.3.4              The Mai Po Nature Reserve is situated inside the Mai Po Marsh SSSI which was designated in 1976. Since 1983, World Wide Fund for Nature Hong Kong (WWFHK) have assisted the Hong Kong Government in managing the Nature Reserve (some 380 ha) in particular habitat and visitor facility management (Tsim et al, 2002). The man-made gei wai provide a valuable feeding and nesting habitat for vaious wildlife species and especially important to the migratory waterbirds including the globally threatened Black-faced Spoonbill Platalea minor.

 

Mai Po Marshes SSSI

 

6.3.5              Mai Po Marshes SSSI contains 393 hectares of marsh, of which 53% of the marshes are gei wai. These marshes contain the largest and most important dwarf mangrove in Hong Kong. In addition, the gei wai also provides both feeding and nesting habitats for various waterbirds.

 

Tam Kon Chau Egretry

 

6.3.6              Egretry count by Agriculture, Fisheries and Conservation Department (AFCD) in 2007 recorded 26 breeding pairs of Chinese Pond Heron at Tam Kon Chau Egretry, which comprises 9.1% of the total active nest for Chinese Pond Heron of that year (Annon, 2007c). All nests at the Tam Kon Chau colonies were built on Banyan trees (Ficus microcarpa).

 

Ecological Mitigation Area at Yuen Leng Chai

 

6.3.7              Two fishponds temporarily affected by the construction works of the Shenzhen River Regulation Project Stage 3 (near Yuen Leng Chai) were restored and enhanced after the completion of the construction works as an ecological mitigation measure.

 

Lok Ma Chau Loop

 

6.3.8              Lok Ma Chau (LMC) Loop is located at the direct vicinity of WCA and WBA. The wetland west of the LMC Loop and the area south of the Loop were designated by the Town Planning Board (TPB) as WCA and WBA respectively in order to retain the ecological integrity of the Deep Bay wetland ecosystem and avoid adverse impacts of development which may possibly affect the Mai Po Inner Deep Bay Ramsar Site (No. 32 Working Paper of HK2030). The LMC Loop was previously used as dumping site for soft sediment, about 1 million m3 of the Loop is contaminated. It has been reinstated to form part of the mitigation area for the loss of fishpond due to the training of Shenzhen River.

 

Hoo Hok Wai and Ta Sha Lok

 

6.3.9              Hoo Hok Wai and Ta Sha Lok cover the wetland area with large number of active fishponds, reinstated ponds for the Shenzhen River Stage 2 Project and marshes. These habitats provide feeding and roosting grounds for a variety of wetland fauna especially waterbirds and dragonflies are not within but adjacent to the Wetland Buffer Area. It was identified as an area of conservation importance under the Land Use Planning for the Closed Area (Planning Department, 2008).

 

Lin Ma Hang Lead Mines Site of Special Scientific Interest (SSSI)

 

6.3.10           The site is situated on a hillside near San Kwai Tin northeast of the Lin Ma Hang. Lin Ma Hang Lead Mines SSSI was recognized as the most important resting and breeding roost site for Greater Bent-winged Bat Miniopterus magnater and Lesser Bent-winged Bat Miniopterus pusillus. Endangered species Common Bent-winged Bat Miniopterus schreibersii listed in IUCN and China Red Data Book was also recorded (Shek and Chan, 2005). Other uncommon species to be found in the area included Intermediate Horseshoe Bat Rhinolophus affinus, Least Horseshoe Bat Rhinolophus pusillus, Rickett's Big-footed Bat  Myotis ricketti and Chinese Myotis Myotis chinensis (Shek and Chan, 2005).

 

Lin Ma Hang Stream SSSI

 

6.3.11           Lin Ma Hang Stream is listed as one of the Ecologically Important Stream (EIS) in the ETWB Technical Circular No. 5/2005 and was designated as a Site of Special Scientific Interest (SSSI) due to the rich in freshwater fish records (Figure 6.1). The stream supports 15 species of primary freshwater fishes including several species of conservation concern Channa asiatica, Mastacembelus armatus, Rasbora steineri and Rasborinus lineatus (DSD, 2007). It also supports some common but local concerned species (Fellowes et al., 2002), which includes Sapphire Flutterer (Rhyothemis triangularis) and Dancing Shadow-emerald (Idionyx victor). Butterfly of conservation concern found included Glassy Bluebottle (Graphium cloanthus), Small Grass Yellow (Eurema brigitta), Centaur Oak Blue (Arhopala pseudocentaurus) (KFBG, 2004). Wetland-dependent herpetofauna species, Chinese Waterside Skink (Tropidophorus sinicus) was also reported from the stream.

 

Further Study

 

6.3.12           Although some ecological baseline and sites of conservation importance were identified, the large Assessment Area in particular Hoo Hok Wai and Yuen Leng Chai has limited information available. Therefore detailed ecological surveys were carried out in accordance with the methodology set out in Appendix F-1 to fill the information gap.

 

6.4                   Ecological Baseline

 

Overview of Ecological Profile of 500m Assessment Area

 

6.4.1              A habitat survey was conducted within the Assessment Area (Figures 6.2-6.9). A total of 15 types of habitat were identified:

 

·         Woodland;

·         Shrubland;

·         Plantation;

·         Gei Wai;

·         Mangrove;

·         Pond;

·         Marsh;

·         Wet Agricultural Land;

·         Dry Agricultural Land;

·         Abandoned Agricultural Land / Low-lying Grassland;

·         Hillside Grassland;

·         Stream / River;

·         Drainage Channel;

·         Open Field;

·         Developed Area.

 

6.4.2              The areas of each habitat type within the Assessment Area and Project Area are listed in Table 6-1 and Table 6-2 respectively. Project Area refers to the proposed land required for the construction works.

 

Table 61     Habitats present in Assessment Area

Habitat

Project Area

Area (ha)

%

Woodland

80.4

3.2

Shrubland

35.4

1.4

Plantation

91.7

3.6

Gei Wai

22.4

0.9

Mangrove

1.3

0.1

Pond

389.6

15.5

Marsh

106.8

4.2

Wet Agricultural Land

13.2

0.5

Dry Agricultural Land

32.4

1.3

Abandoned Agricultural Land / Low-lying Grassland

310.0

12.3

Hillside Grassland

318.9

12.7

Stream / River

38.2

1.5

Drainage Channel

140.2

5.6

Open Field

4.3

0.2

Developed Area

933.9

37.1

Total

2519.1

100

 

Table 62     Habitats present in Project Area

Habitat

Project Area

Area (ha)

%

Woodland

0

0.0

Shrubland

0

0.0

Plantation

0

0.0

Mangrove

0

0.0

Pond

0

0.0

Marsh

0

0.0

Wet Agricultural Land

0

0.0

Dry Agricultural Land

0

0.0

Abandoned Agricultural Land / Low-lying Grassland

5.9

26.3

Hillside Grassland

0

0.0

Stream / River

0

0.0

Drainage Channel

0

0.0

Open Field

0.1

0.5

Developed Area

16.4

73.2

Total

22.4

100

 

6.4.3              Representative photographs of each type of habitats are illustrated in Plates F1-F15 in Appendix F.

 

Woodland

 

6.4.4              Majority of the woodlands within the Assessment Area is secondary woodland, with few fung shui woods behind some rural villages.

 

6.4.5              Several secondary woodlands located along the existing patrol roads, which includes woodlands near Liu Pok, Man Kam To Boundary Crossing and Pak Fu Shan.

 

6.4.6              Five fung shui woods were identified within the Assessment Area. Fung Shui Woods refer to woodlands preserved by the villagers for traditional fung shui beliefs. These fung shui woods situated behind rural villages Kan Tau Wai, Tsung Yuen Ha, Sheung Tam Shui Hang, Shan Tsui and Lin Ma Hang. Most of these fung shui woods located far away from the alignment of at least 200m. Shan Tsui fung shui wood is located about 150m away from the proposed alignment.

 

6.4.7              Dominant species are native tree and shrub species such as Aquilaria sinensis, Aporusa dioica, Celtis sinensis, Cinnamomum camphora, Cratoxylum cochinchinense, Mallotus paniculatus, Schefflera heptaphylla, Schima superba, Psychotria asiatica and Uvaria macrophylla.

 

Shrubland

 

6.4.8              Shrubland is a subsequent succession stage of grassland. Most of these habitats are located along hillside where human disturbance particularly hill fire due to Chung Yeung Festival event is not serious.

 

6.4.9              Common shrubs include Rhodomyrtus tomentosa, Melastoma candidum, Melastoma sanguineum, Ficus hirta, Litsea rotundifolia, Ilex asprella, Phyllanthus reticulates and Desmos chinensis etc.

 

Plantation

 

6.4.10           Plantation is forest dominated by planted species for reforestation, landscape or fruit production purposes. Common plantation species include Acacia auriculiformis, Acacia confusa, Lophostemon confertus, Casuarina equisetifolia, Clausena lansium, Dimocarpus longan, Litchi chinensis and Syzygium jambos.

 

Gei Wai

 

6.4.11           Gei wai is a kind of inter-tidal pond traditionally managed for shrimp production. In the Assessment Area of the project, it can only be found at Mai Po (Figure 6.3). Dominant mangrove species include Kandelia obovata, Avicennia marina and Aegiceras corniculatum, while Phragmites australis and Brachiaria mutica are common species along the banks of the gei wai.

 

6.4.12           Gei wais in Mai Po Nature Reserve are internationally important to migratory waterbirds. A large variety of waterbirds can be found in gei wai habitat including the globally threatened species Black-faced Spoonbill Platalea minor. The high diversity of avifauna in this habitat is due to the low disturbance, high naturalness and good ecological linkage to Deep Bay ecosystem.

 

Mangrove

 

6.4.13           Only two small patches of mangrove were identified in Sha Tau Kok (Figure 6.9). Its plant composition is similar to other mangrove stands found in coastal areas along Starling Inlet. Dominant mangrove species are Kandelia obovata, Avicennia marina and Aegiceras corniculatum.

 

Pond

 

6.4.14           A large area of fishpond habitat is identified at Mai Po, San Tin, Lok Ma Chau and Hoo Hok Wai. Except those at Hoo Hok Wai, most of the ponds are within either WCA or WBA at Deep Bay areas.

 

6.4.15           Floral composition of this habitat is comparatively simple. Common species found along the pond bund and the slopes include Brachiaria mutica, Phragmites australis, Panicum maximum and Cynodon dactylon.

 

6.4.16           Due to its large and continuous area, the fishponds provide a good habitat for various groups of wetland-dependent birds for both feeding and roosting. Different micro-habitats in the fishponds are utilized by birds of different foraging groups and thereby support a rich diversity of avifauna. The clear open fishpond area is also attractive to some raptors which are not wetland related in its natural habitat such as Bonelli’s Eagle Hieraaetus fasciatus.

 

6.4.17           The riparian vegetation and shallow water margin at the fishpond also provide microhabitats for dragonfly and herpetofauna species of conservation concern. Dragonfly species Scarlet Basker Urothemis signata and reptile species such as Many-banded Krait Bungarus multicinctus multicinctus, Chinese Cobra Naja atra and Burmese Python Python molurus bivittatus were recorded in this study.  

 

Marsh

 

6.4.18           Marshes are mainly found in Hoo Hok Wai areas north of Ma Tso Lung. These marshes were originated from disused fishponds or agricultural lands. Dominant wetland plant species include Colocasia esculenta, Ludwigia octovalvis, Phragmites australis, Brachiaria mutica, Commelina diffusa and Cyclosorus interruptus.

 

6.4.19           This kind of habitat is favourable to a certain kind of freshwater wetland birds such as Yellow Bittern Ixobrychus sinensis and Greater Painted Snipe Rostratula benghalensis. A dragonfly species of local concern Sapphire Flutterer Rhyothemis triangularis was recorded in the marsh habitat.

 

Wet Agricultural Land

 

6.4.20           Wet agricultural lands were recorded at Lok Ma Chau Village and Chow Tin Tsuen. Major crops include Ipomoea aquatica and Nasturtium officinale. These would be favourable habitat to a certain species of freshwater wetland birds such as Wood Sandpiper Tringa glareola, Green Sandpiper Tringa ochropus, Long-toed Stint Calidris subminuta and Temminck’s Stint Calidris temminckii.

 

Dry Agricultural Land

 

6.4.21           These are also artificial habitats for crop production. They occur in small patches near the rural villages within the Assessment Area. Common crops observed during surveys included Lactuca sativa, Brassica parachinensis, Brassica chinensis, Colocasia esculenta, Apium graveolens and Daucus carota.

 

Abandoned Agricultural Land / Low-lying Grassland

 

6.4.22           These habitats were originated from agricultural lands after abandonment and are common in the areas between Ma Tso Lung and Sha Tau Kok via Man Kam To, Ta Kwu Leng and Lin Ma Hang.

 

6.4.23           Common plant species include Ipomoea cairica, Brachiaria mutica, Conyza bonariensis, Bidens alba, Amaranthus viridis, Ipomoea triloba, Emilia sonchifolia, Youngia japonica, Mikania micrantha, Mimosa pudica, Polygonum chinense, Scoparia dulcis, Solanum nigrum, Panicum maximum and Cynodon dactylon etc.

 

Hillside Grassland

 

6.4.24           This is the dominant habitat on the hill range along the southern edge of the Assessment Area. The grasslands are maintained by frequent hill fire and can be rapidly replaced by shrubs when fires are prevented. Common grass species include Arundinella sp., Eulalia sp., and Ischaemum sp.

 

Stream / River

 

6.4.25           The longest river within the Assessment Area is the unchannelised section of Shenzhen River at its uppercourse. The Lin Ma Hang Stream is an ecologically important tributary of the unchannelised Shenzhen River. Others also include ditches within the fishpond areas at San Tin.

 

6.4.26           Dominant plant species along the streams and ditches are common riparian vegetation such as Brachiaria mutica, Commelina diffusa, Pennisetum purpureum, Alocasia odora and Rumex trisetifer.

 

6.4.27           Common lowland fish species recorded in streams and ditches include Chinese Barb Puntius semifasciolatus, Gupy Poecilia reticulata and the exotic species Mosquito Fish Gambusia affinis and Nile Tilapia Oreochromis niloticus.

 

Drainage Channel

 

6.4.28           Major drainage channels include the channelised Shenzhen River, lower course of the Ng Tung River, Ping Yuen River and Tam Shui Hang. Common riparian plants found on the concrete banks include Brachiaria mutica, Commelina diffusa, Phragmites australis and Sesbania javanica.

 

6.4.29           Due to its close ecological linkage to Deep Bay mudflat, the downstream Mai Po-San Tin section of the channelized Shenzhen River is rich in bird diversity. The exposed mudflats along both sides of the channel provide a foraging habitat for ardeids and waders. Those birds common in Inner Deep Bay Mudflat can also be found in this section of Shenzhen River

 

Open Field

 

6.4.30           This habitat type refers to those open areas with compacted and exposed soil where limited coverage of vegetation is found. Dominant plant species usually are those common weeds such as Rhynchelytrum repens, Bidens alba, Panicum maximum, Mikania micrantha and Cynodon dactylon.

 

Developed Area

 

6.4.31           These are habitats under heavy human disturbance and mainly consist of village houses, residential estates, infrastructures, construction sites and container yards.

 

6.4.32           This is the dominant land use type in the Assessment Area at Shenzhen.

 

Ecological Profile of the Four Proposed Sections

 

6.4.33           Ecological profiles of each section of the proposed alignment are described below separately.

 

Ecological Profile of Section 1 (Mai Po-San Tin)

 

Habitat & Vegetation

 

6.4.34           As shown in Figure 6.1- 6.4, this section runs on the existing boundary patrol road at Mai Po-San Tin area. This Mai Po-San Tin area is characterized by the high dominance of the pond habitat.

 

6.4.35           Ponds (fishponds) are the major habitats within the Assessment Area of this section. Almost all of the ponds in this section are within the Wetland Conservation Area designated by Town Planning Board to promote preservation of the integrity of the ecological function of these ponds. These ponds are recognised important feeding and roosting grounds for a variety of waterbird species. A few ponds are located within the boundary of Mai Po Nature Reserve, Mai Po Marsh SSSI and Mai Po Inner Deep Bay Ramsar Site at the west end of the Assessment Area.

 

6.4.36           Few gei wais are located at the western end of the Assessment Area. These gei wais are now managed by World Wide Fund Hong Kong (WWF) to maintain the ecological value of the nature reserve.

 

6.4.37           Beside from gei wai, wetland habitat found in this section also include fishpond associated habitat such as abandoned fishponds originated marshes and artificially modified streams. Although these habitats are not naturally established, they could provide refuge and feeding grounds for some waterbirds such as White-breasted Waterhen and Green Sandpiper.

 

6.4.38           The channelised Shenzhen River runs along the Hong Kong – Shenzhen Boundary and the proposed project alignment. Another drainage channel is the Shek Sheung River east of the Lok Ma Chau MTR Station.

 

6.4.39           Open fields are areas of exposed soil and dominated by common wasteland weeds such as Rhynchelytrum repens, Bidens alba and Cynodon dactylon. Developed areas in this section refer to the existing roads, the Lok Ma Chau MTR station, the Shenzhen Town and some rural villages.

 

6.4.40           The Project Area of this section is proposed on the existing boundary patrol road from the existing Pak Hok Chau Check point to Lok Ma Chau Railway Station (Figure 6.3-6.4). In terms of habitat type, the Project Area will cover mainly developed area (i.e. road) and some open fields (i.e. some exposed soil vegetated with roadside plants). A total of 74 species were identified within the Project Area of Section 1. Dominant species include Panicum maximum, Bidens alba, Cynodon dactylon, Pennisetum purpureum, Brachiaria mutica, Hibiscus tiliaceus, Leucaena leucocephala, Cleistocalyx operculatus and Casuarina equisetifolia. Ipomoea cairica, Paederia scandens and Mikania micrantha are common climbers along this section.

 

6.4.41           Neither protected nor rare plant species were identified. The plant list of the Project Area of Section 1 is presented in Table F-1a in Appendix F.

 

Fauna

 

6.4.42           This section covers the area of Mai Po (T1_MP refer to Figure F1 of Appendix F) and San Tin (T2_SPS). The ecological baseline findings of fauna survey are described below.

 

Mammals

 

6.4.43           A total of three mammal species was recorded in the Mai Po fishponds and Ecological Mitigation Area at Lok Ma Chau during mammal surveys. Two bat species were seen during night-time surveys foraging over the fishponds and 10 Brown Rat Rattus norvegicus were found dead along the footpaths at fishpond bunds on 20 June 2008.

 

6.4.44           The Brown Rat is an introduced species and human commensal throughout urban areas. It is widespread and prefers moist habitat types (Shek, 2006).

 

6.4.45           The two bat species were suspected to be Japanese Pipistrelle Pipistrellus abramus and Lesser Yellow Bat Scotophilus kuhlii which were previously recorded in the Mai Po Nature Reserve (Chan and Shek, 2006). Japanese Pipistrelle, a very common bat species in wetland countryside and urban areas of Hong Kong, is not of conservation importance. Lesser Yellow Bat is an uncommon species but with common roosting preferences as Japanese Pipistrelle that often roosts in the attics of houses. They also roosts under modified fronds of palm trees, holes in walls or abandoned bird nest (Chan and Shek, 2006). This species has a fairly wide distribution in Hong Kong, the colony sizes range from a few to hundreds of individuals (Shek, 2006). The abundance of the bats was from few to around 30 individuals foraging over the fishponds and around the lights along the boundary patrol road.

 

6.4.46           The previous records of Eurasian Otter Lutra lutra chinensis in the Mai Po Inner Deep Bay Ramsar Site and nearby region was not recorded in this study. This species has a highly restricted distribution which inhabits terrestrial areas adjacent to ponds, streams, coastal areas and rivers. It is protected under the Wild Animals Protection Ordinance (Cap. 170) and the Protection of Endangered Species of Animals and Plants Ordinance (Cap. 586). It is also listing in the IUCN Red List as Lower Risk/ Near Threatened; in the China Red Data Book as “Vulnerable” and in the CITES.

 

Birds

 

6.4.47           The avifauna in this section is dominated by wetland-dependent species as a result of wide variety of wetland habitat. Different groups of waterbirds such as ducks, ardeids, cormorant, spoonbills, bitterns and warders can be found at gei wai and mangrove inside Mai Po Nature Reserve. The nearby fishponds and channelized Shenzhen River are also rich in waterbird diversity due to its close ecology linkage to Inner Deep Bay ecosystem. Besides from waterbirds, a number of raptor species were recorded in this area including the globally threatened species Imperial Eagle Aquila heliaca. A patch of woodland in Tam Kon Chau was identified as ecological important as it is used by Chinese Pond Heron Ardeola bacchus as a breeding site, egrety.  

 

 

Results of transect survey

 

6.4.48           A total of 63 species was recorded during the transect surveys in Section 1, of which 23 species are of conservation importance including the globally threatened species Black-faced Spoonbill Platalea minor. A full list of species recorded is given in Table F-1b in Appendix F. The species recorded in the Assessment Area are mainly typical fishpond birds, of which 31 species account for 50 percent of the list are wetland-dependent birds.

 

Table 63     Mean of individuals of bird species of conservation concern and wetland-dependent bird species recorded during transect survey in Section 1 Assessment Area, Nov 2007 - Oct 2008. (Level of Concern based on Fellowes et al. 2002)

Common Name

Level of Concern

Wetland-dependent

Mean#

Little Grebe

Tachybaptus ruficollis

LC

 Y

3.11

Great Cormorant

Phalacrocorax carbo

PRC

 Y

29.67

Grey Heron

Ardea cinerea

PRC

 Y

21.00

Great Egret

Egretta alba

PRC(RC)

 Y

40.78

Intermediate Egret

Egretta intermedia

RC

 Y

0.11

Little Egret

Egretta garzetta

PRC(RC)

 Y

40.00

Cattle Egret

Bubulcus ibis

(LC)

 Y

0.11

Chinese Pond Heron

Ardeola bacchus

PRC(RC)

 Y

7.00

Black-crowned Night Heron

Nycticorax nycticorax

(LC)

 Y

0.44

Black-faced Spoonbill

Platalea minor

PGC

Y

1.00

Eurasian Wigeon

Anas penelope

RC

 Y

18.11

Common Teal

Anas crecca

RC

 Y

1.56

Northern Pintail

Anas acuta

RC

 Y

33.33

Northern Shoveler

Anas clypeata

RC

 Y

0.11

Osprey

Pandion haliaetus

RC

 Y

0.11

Black Kite

Milvus migrans

(RC)

 N

6.00

White-breasted Waterhen

Amaurornis phoenicurus

 Y

1.44

Common moorhen

Gallinula chloropus

 Y

4.22

Little Ringed Plover

Charadrius dubius

(LC)

 Y

2.22

Green Sandpiper

Tringa ochropus

 -

 Y

0.44

Wood Sandpiper

Tringa glareola

LC

 Y

2.44

Common Sandpiper

Actitis hypoleucos

 -

 Y

7.44

Pacific Swift

Apus pacificus

(LC)

 N

0.33

Little Swift

Apus affinis

 -

 Y

0.56

Pied Kingfisher

Ceryle rudis

(LC)

 Y

0.33

Common Kingfisher

Alcedo atthis

 -

 Y

1.11

White-throated Kingfisher

Halcyon smyrnensis

(LC)

 

0.89

Barn Swallow

Hirundo rustica

 -

 Y

20.00

Yellow Wagtail

Motacilla flava

 -

 Y

3.78

Grey Wagtail

Motacilla cinerea

 -

 Y

1.00

White Wagtail

Motacilla alba

 -

 Y

9.78

Red-billed Starling

Sturnus sericeus

(RC)*

 Y

33.33

Collared Crow

Corvus torquatus

LC

 Y

0.22

Level of concern follows Fellowes et al.(2002): LC=Local Concern; RC=Regional Concern; GC=Global Concern; PRC=Potential Regional Concern; PGC=Potential Global Concern. Letters in parentheses indicate that the assessment is on the basis of restrictedness in breeding and/or roosting sites rather than in general occurrence.

#Mean values given are the mean number recorded on all transects. This is included to reflect the regularity of a species in the study area.

*Red-billed Starling is considered by Fellowes et al. (2002) to be of Global Concern. Since then, the global population has been increasing and the species is not now considered globally threatened (BirdLife International 2008). A listing of Regional Concern (RC), based on the importance of the large roosts present near Deep Bay, is considered to be more appropriate.

 

Monthly monitoring of waterbirds at fishponds area by Hong Kong Bird Watching Society

 

6.4.49           The abundance and diversity of wetland-dependent birds utilizing fishponds in Deep Bay area are monthly surveyed by the Hong Kong Bird Watching Society as part of the long-term monitoring of the Ramsar Site for AFCD. The ponds within Section 1 Assessment Area largely lie into count area Tam Kon Chau (TKC), Mai Po San Tsuen (MPST), Shenzhen River A (SRA) and partially lie into count area San Tin and Mai Po Nature Reserve (MPNR). The monitoring data was used to supplement data collected on the transect surveys. Some ponds of the count area lying just outside the Assessment Area are also used for analysis as they share the same habitat to the ponds within Assessment Area. However, the count of Mai Po Nature Reserve was not used as the data mainly describe the waterbirds at core gei wai habitat of the Reserve rather than the ponds at northeast side of the Reserve which lie into the Section 1 Assessment Area.

 

6.4.50           A checklist of wetland-dependent birds utilizing the fishpond and river area at Section 1 was obtained by summarizing five years waterbird monitoring data for count area at San Tin, Tam Kong Chau, Mai Po San Tsuen and Shenzhen River A (Table 6-4). A total of 76 wetland-dependent species was recorded at the area including 5 globally threatened species Lesser White-fronted Goose Anser erythropus, Oriental Stork Ciconia boyciana, Black-faced Spoonbill Platalea minor, Greater Spotted Eagle Aquila clanga and Imperial Eagle Aquila heliaca.

 

 


Table 64     Wetland-dependent bird species recorded in the Tam Kon Chau, Mai Po San Tsuen, San Tin and Shenzhen River A count area on monthly waterbird counts conducted by the Hong Kong Bird Watching Society, April 2003 - March2008 (data from Anon 2008, Anon 2007a, Anon 2007b, Anon 2006a, Anon 2006b, Anon 2005a, Anon 2005b, Anon 2004a, Yu 2004 and Yu 2003)

Common Name

Species Name

Level of Concern

IUCN 2008

Little Grebe

Tachybaptus ruficollis

LC

Great Crested Grebe

Podiceps cristatus

RC

Great Cormorant

Phalacrocorax carbo

PRC

Lesser White-fronted Goose

Anser erythropus

GC**

VU

Greater White-fronted Goose

Anser albifrons

 -

Purple Heron

Ardea purpurea

RC

Grey Heron

Ardea cinerea

PRC

Great Egret

Egretta alba

PRC(RC)

Intermediate Egret

Egretta intermedia

RC

Little Egret

Egretta garzetta

PRC(RC)

Cattle Egret

Bubulcus ibis

(LC)

Chinese Pond Heron

Ardeola bacchus

PRC(RC)

Striated Heron

Butorides striatus

(LC)

Black-crowned Night Heron

Nycticorax nycticorax

(LC)

Yellow Bittern

Ixobrychus sinensis

(LC)

Oriental Stork

Ciconia boyciana

GC

EN

Eurasian Spoonbill

Platalea leucorodia

LC

-

Black-faced Spoonbill

Platalea minor

PGC

EN

Eurasian Wigeon

Anas penelope

RC

-

Falcated Duck

Anas falcata

RC

-

Common Teal

Anas crecca

RC

-

Greater Scaup

Aythya marila

-

-

Northern Pintail

Anas acuta

RC

-

Northern Shoveler

Anas clypeata

RC

-

Mallard

Anas platyrhynchos

RC

-

Spot-billed Duck

Anas poceilorhyncha

RC 

-

Garganey

Anas querquedula

 -

-

Tufted Duck

Aythya fuligula

LC

-

Osprey

Pandion haliaetus

RC

-

Black Kite

Milvus migrans

(RC)

-

Common buzzard

Buteo buteo

-

-

Crested Serpent Eagle

Spilornis cheela

(LC)

-

Eastern Marsh Harrier

Circus spilonotus

LC

-

Greater Spotted Eagle

Aquila clanga

GC

VU

Imperial Eagle

Aquila heliaca

GC

VU

White-bellied Sea Eagle

Haliaeetus leucogaster

GC

-

Common Kestrel

Falco tinnunculus

 -

-

Peregrine Falcon

Falco peregrinus

(LC)

-

White-breasted Waterhen

Amaurornis phoenicurus

 -

-

Common Moorhen

Gallinula chloropus

-

-

Eurasian Coot

Fulica atra

RC

-

Watercock

Gallicrex cinerea

RC

-

Pheasant-tailed Jacana

Hydrophasianus chirurgus

LC

-

Greater Painted-snipe

Rostratula benghalensis

LC

-

Black-winged Stilt

Himantopus himantopus

RC

-

Oriental Pratincole

Glareola maldivarum

LC

-

Pied Avocet

Recurvirostra avosetta

RC

-

Little Ringed Plover

Charadrius dubius

(LC)

-

Kentish Plover

Charadrius alexandrinus

RC

-

Greater Sand Plover

Charadrius leschenaultii

RC

-

Common Redshank

Tringa totanus

RC

-

Spotted Redshank

Tringa erythropus

RC

-

Common Greenshank

Tringa nebularia

RC

-

Red-necked Phalarope

Phalaropus lobatus

 -

-

Green Sandpiper

Tringa ochropus

-

-

Wood Sandpiper

Tringa glareola

 LC

-

Marsh Sandpiper

Tringa stagnatilis

RC 

-

Common Sandpiper

Actitis hypoleucos

 -

-

Common Snipe

Gallinago gallinago

-

-

Pintail Snipe

 Gallinago stenura

-

-

Swinhoe's Snipe

Gallinago megala

LC 

-

Little Stint

Calidris minuta

LC

-

Temminck's Stint

Calidris temminckii

LC

-

Long-toed Stint

Calidris subminuta

LC

-

Red-necked Stint

Calidris ruficollis

LC

-

Curlew Sandpiper

Calidris ferruginea

RC

-

Heuglin's Gull

Larus heuglini

LC

-

Black-headed Gull

Larus ridibundus

PRC

-

Whiskered Tern

Chlidonias hybridus

 -

-

Gull-billed Tern

Sterna nilotica

 -

-

Common Kingfisher

Alcedo atthis

-

-

Pied Kingfisher

Ceryle rudis

(LC)

-

White-throated Kingfisher

Halcyon smyrnensis

(LC)

-

Black-capped Kingfisher

Halcyon pileata

(LC)

-

Red-billed Starling

Sturnus sericeus

GC*

-

Collared Crow

Corvus torquatus

LC

-

Level of concern follows Fellowes et al.(2002): LC=Local Concern; RC=Regional Concern; GC=Global Concern; PRC=Potential Regional Concern; PGC=Potential Global Concern. Letters in parentheses indicate that the assessment is on the basis of restrictedness in breeding and/or roosting sites rather than in general occurrence.

*Red-billed Starling is considered by Fellowes et al. (2002) to be of Global Concern. Since then, the global population has been increasing and the species is not now considered globally threatened (BirdLife International 2008). A listing of Regional Concern (RC), based on the importance of the large roosts present near Deep Bay, is considered to be more appropriate.

**No rating was given to Lesser White-fronted Goose by Fellowes et al. (2002) but based on the estimate of its global population (BirdLife International 2008b), it is considered as Global Concern (GC).

 

 

 

 

Monitoring of Egretry

 

6.4.51           Deep Bay area is known for its importance to breeding egrets and herons (Young 1998). In 2007, the numbers of nests in the Deep Bay area accounted for 33.5% of the total in Hong Kong (Anon 2007). Active and abandoned egretries were identified and surveyed annually by the Hong Kong Bird Watching Society as part of the Ramsar Site Waterbird Monitoring Programme for AFCD. The only egretry lie within Section 1 Assessment Area is Tam Kon Chau Egretry (Figure 6.1).

 

6.4.52           Results of the monitoring data from 2003 to 2007 are summarized in Table 6-5 to review the recent history of Tam Kon Chau Egrety which lies within Section 1 Assessment Area. Only Chinese Pond Heron utilized the site for breeding although the site was sometimes occupied by other ardeids for night roost during winter. The number of nests ranged from 23 to 47 accounted for 2.2 to 5.4 percent of total number of nests in Hong Kong from 2003-2007. The status of the egretry was confirmed on 8 May and 20 June 2008, when the egretry was still actively used by Chinese Pond Heron. All nests at the Tam Kon Chau colonies were built on Banyan trees Ficus microcarpa, in which both juveniles and breeding adults of Chinese Pond Heron were observed.

Table 65     Summary of Tam Kon Chau Egretry 2003-2007 (data from Anon 2007c, Anon 2006c, Anon 2005c, Anon 2004b and Wong 2003)

 

 

2003

2004

2005

2006

2007

No. of nests

37

47

23

37

26

Percentage of nest in Hong Kong

3.2%

3.6%

2.2%

5.4%

5.1%

 

Herpetofauna

 

6.4.53           Six species of reptiles and amphibians were recorded in Section 1 during day and night surveys, in which only one species Many-banded Krait Bungarus multicinctus multicinctus is of conservation concern.  Two individuals were observed along the pond bunds with vegetation covered on 19 August 2008 during the night survey. Many-banded Krait is stated as ‘Vulnerable’ in China Red Data Book and of ‘Potential Regional Concern’ (Fellowes et al. 2002). This species is widely distributed in the New Territories, Hong Kong Island and Lantau Island (Karsen, 1998). The relative abundance of the species recorded in Section 1 is summarised in Table 6-6 below.


Table 66     Relative abundance of herpetofauna species recorded in Section 1

Species

Project Area

Assessment Area (other than Project Area)

Commonness

Level of Concern/ Protection Status

Asian Common Toad

(Bufo melanostictus)

+

+++

Widely Distributed

 

Gunther's Frog

(Rana guentheri)

++

++++

Widely Distributed

 

Chinese Gecko

(Gekko chinensis)

 

++

Widely Distributed

 

Common Blind Snake

(Ramphotyphlops braminus)

 

+

Widely Distributed

 

Many-banded Krait

(Bungarus multicinctus multicinctus)

 

+

Widely Distributed

Listed as Vulnerable in China Red Data Book; Considered as Potential Regional Concern

Red-eared Slider

(Trachemys scripta elegans)

 

+

Widely Distributed

 

Note: +- 1-3; ++- 4-6; +++- 7-10; ++++- >10.  

 

Dragonflies and Butterflies

 

6.4.54           There were ten species of odonata recorded in this Section with most of them found at wetland area such as fishpond, marshes and streams. None of them are considered as conservation concern. Table 6-7 summarised the odonata species recorded in Section 1 during November 2007 to October 2008.

 

Table 67     Odonata species recorded in Section 1

Species

Project Area

(mean no. of individual per visit)

Assessment Area Other than Project Area (mean no. of individual per visit)

Commonness

Asian Amberwing

(Brachythemis contaminata)

 

4 (0.44)

Abundant and widely distributed

Blue Dasher

(Brachydiplax chalybea flavovittata)

 

1 (0.11)

Common and widely distributed

Common Bluetail

(Ischnura senegalensis)

1 (0.11)

20 (2.22)

Abundant and widely distributed

Common Flangetail

(Ictinogomphus pertinax)

 

1 (0.11)

Abundant and widely distributed

Crimson Darter

(Crocothemis servilia servilia)

 

6 (0.67)

Abundant and widely distributed

Green Skimmer

(Orthetrum sabina sabina)

3 (0.33)

81 (9)

Common and widely distributed

Orange-tailed Sprite (Ceriagrion auranticum)

 

21 (2.33)

Abundant and widely distributed

Saddlebag Glider

(Tramea virginia)

 

9 (1)

Common and widely distributed

Variegated Flutterer

(Rhyothemis variegata)

5 (0.56)

127 (14.11)

Common and widely distributed

Wandering Glider

(Pantala flavescens)

47 (5.22)

104 (11.56)

Abundant and widely distributed

Note: Commonness follows Hong Kong Biodiversity Database (AFCD, 2006).

 

6.4.55           Eleven butterfly species were recorded in Section 1 during November 2007 to October 2008. Only 4 very common species, the Common Bluebottle, Common Grass Yellow, Indian Cabbage White and Pale Grass Blue of 1 or 2 individuals were recorded along the proposed works area. Most of the species recorded were along the riparian vegetation of fishpond bund, marshes, streams, grassland, plantation and developed area which are not within the Project Area. Most of the species recorded were along the riparian vegetation of fishpond bund, marshes, streams, grassland, plantation and developed area which are not within the Project Area. All the butterfly species recorded in this Section are common and widespread in Hong Kong. No species of conservation concern was recorded in this section. Table 6-8 below summarised the butterfly species recorded in Section 1.

 

 


Table 68     Butterfly species recorded in Section 1

Species

Project Area

(mean no. of individual per visit)

Assessment Area Other than Project Area (mean no. of individual per visit)

Commonness

Angled Castor

(Ariadne ariadne)

 

1 (0.11)

Common and widely distributed

Common Bluebottle

(Graphium sarpedon)

1 (0.11)

8 (0.89)

Common and widely distributed

Common Grass Yellow

(Eurema hecabe)

2 (0.22)

4 (0.44)

Common and widely distributed

Common Mormon

(Papilio polytes)

 

13 (1.44)

Common and widely distributed

Common Tiger

(Danaus genutia)

 

3 (0.33)

Common and widely distributed

Dark-brand Bush Brown

(Mycalesis mineus)

 

8 (0.89)

Common and widely distributed

Great Eggfly

(Hypolimnas bolina kezia)

 

4 (0.44)

Common and widely distributed

Indian Cabbage White

(Pieris canidia)

1 (0.11)

47 (5.22)

Common and widely distributed

Lemon Emigrant

(Catopsilia pomona)

 

1 (0.11)

Common and widely distributed

Pale Grass Blue

(Zizeeria maha)

1 (0.11)

 

Common and widely distributed

Red-base Jezebel

(Delias pasithoe)

 

1 (0.11)

Common and widely distributed

Note: Commonness follows Hong Kong Biodiversity Database (AFCD, 2006).

 

Aquatic Fauna

 

6.4.56           Spotted Snakehead Channa maculata, Nile Tilapia Oreochromis niloticus, Big Head Carp Aristichthys nobilis, Common Carp Cyprinus carpio and Mosquito Fish Gambusia affinis were recorded in the Mai Po fishponds. The Spotted Snakehead and Nile Tilapia were found dead on 20 February 2008. Except Mosquito Fish is exotic species, all the other species are food fish in cultivated fishponds. No rare and species of conservation concern was recorded in this section.  

 

Ecological Profile of Section 2 (Lok Ma Chau-Hoo Hok Wai)

 

Habitat & Vegetation

 

6.4.57           There are three proposed alignments within Section 2 (Figure 6.1). The green alignment is for removal of the existing boundary fence which running from Ha Wan Tsuen in Lok Ma Chau to Tak Yue Lau along the existing boundary patrol road; the short blue alignment at Ha Wan Tsuen is for construction of a secondary boundary fence; while the red Alignment is for construction of new boundary patrol road, primary and secondary boundary fence which running from Ha Wan Tsuen to Tak Yue Lau along the existing maintenance access besides the re-aligned Shenzhen River.

 

6.4.58           As shown in Figure 6.2, this Lok Ma Chau-Hoo Hok Wai area is characterised by the large area of mixed wetland habitat of fishponds and freshwater marshes which are important feeding and roosting grounds of waterbirds. Similar to Section 1, the channelised Shenzhen River runs along the Hong Kong – Shenzhen Boundary. The Lok Ma Chau Bend is the remnant of the original section of Shenzhen River after the Shenzhen River training works, which surrounding the Lok Ma Chau Loop.

 

6.4.59           As described in Section 6.3.7, the Lok Ma Chau Loop was previously used as dumping site for soft sediment, about 1 million m3 of the Loop is contaminated. It has been reinstated and largely covered with vegetation. Herbs and grasses commonly found in low-lying grassland and wasteland such as Bidens alba, Wedelia trilobata, Neyraudia reynaudiana, Imperata koenigii are dominant plant species. A freshwater marsh situated inside the Loop, which like those in Hoo Hok Wai, was derived from abandoned fishponds.

 

6.4.60           Hillside grasslands dominate the area south of the Lok Ma Chau Road. This type of habitat is maintained by frequent hill fires particularly during Ching Ming and Chung Yeung festivals. Woodlands and shrublands can be found along some downhill areas near Shun Yee San Tsuen and Liu Pok village. Common native plant species such as Cinnamomum camphora, Celtis sinensis, Schefflera heptaphylla, Sterculia lanceolata and Microcos paniculata were found. The Ma Tso Lung marsh and Liu Pok marsh were identified near these two villages. These marshes however are different from those marshes found at Hoo Hok Wai area that they are derived from abandoned agricultural lands rather than fishpond. Common plant species found in the secondary marsh include Colocasia esculenta, Hedychium coronarium and Commelina diffusa.

 

6.4.61           One area of wet agricultural land was also found within the Assessment Area south of the Lok Ma Chau Road (Figure 6.4). Ipomoea aquatica was the main crop of the agricultural land while few areas were found planting Nelumbo nucifera.

 

Green and Blue Alignment

 

6.4.62           The Project Area of the green and blue alignment runs along the existing Lok Ma Chau Road (Figure 6.1). In terms of habitat, this alignment only covers developed area (i.e. the existing Lok Ma Chau Road) (Figure 6.4-6.5).

 

6.4.63           A total of 237 plant species were identified within the Project Area of the green and blue alignment in Section 2. Dominant plant species include Microstegium ciliatum, Bidens alba, Lantana camara, Ficus hispida, Microcos paniculata, Ficus hirta, Neyraudia reynaudiana, Rhodomyrtus tomentosa, Dicranopteris pedata and Ligustrum sinense. Lygodium japonicum, Ipomoea cairica and Mikania micrantha are common climbers along the alignment.

 

6.4.64           No protected species were identified but one rare species Berchemia lineata was recorded on the roadside near Liu Pok Village (Figure 6.5). It is a climbing shrub and has distribution records in Shatin, Sheung Shui, Sai Kung, Ma Wan and Ping Chau (Mirs Bay).

 

6.4.65           The plant list of the Project Area of the green alignment in Section 2 is presented in Table F-2a in Appendix F.

 

Red Alignments

 

6.4.66           The red alignment is proposed on the exiting DSD maintenance access along the channelised Shenzhen River. Thus it will only cover one type of habitat of developed area. A total of 40 species were identified. Dominant plant species include Cynodon dactylon, Sesbania cannabina, Rhynchelytrum repens, Wedelia trilobata, Imperata koenigii, Bidens alba, Cynodon dactylon and Mimosa pudica.

 

6.4.67           Neither protected nor rare plant species were identified. The plant list of the Project Area of the green alignment in Section 2 is presented in Table F-2b in Appendix F.

 

Fauna

 

6.4.68           This section covers the area of Lok Ma Chau Loop (T3_LMCL refers to Figure F1 of Appendix F), Lok Ma Chau (T4_LMC), Shun Yee San Tsuen (T5_SYST), wetlands at Hoo Hok Wai (T6_HHW) and Ta Sha Lok (T7_TSL). The ecological survey findings for fauna species are described below.

 

Mammals

 

6.4.69           A total of five mammal species was recorded in Section 2 fishponds and ecological mitigation area at Hoo Hok Wai and Ta Sha Lok during mammal surveys. They include Brown Rat Rattus norvegicus, Domestic Ox Bos taurus, Small Asian Mongoose Herpestes javanicus, Japanese Pipistrelle Pipistrellus abramus and a bat species with small and short wing span. Two bat species of different sizes were seen during night-time surveys foraging over the fishponds. There was no literature on bat species recored in this Section, one species of bat observed is suspected to be Japanese Pipistrelle, as this species was recorded in abundant in wetland areas of Mai Po and the size is similar to it. All bat species are protected under the Wild Animals Protection Ordinance (Cap.170).

 

6.4.70           Eight sightings of Small Asian Mongoose were recorded during 7 daytime surveys around the Shenzhen River riparian vegetation and fishpond bund at Lok Ma Chau Loop, the marsh and the roadside vegetation along the existing boundary patrol road at Shun Yee Sun Tsuen and fishpond bunds at Hoo Hok Wai and Ta Sha Lok. This species was observed crossing between fishponds and the Shenzhen River meander at Lok Ma Chau Loop via the base of the existing boundary fence at Ha Wan Tsuen. The Small Asian Mongoose has a fairly wide distribution in Hong Kong and can inhabit a wide variety of habitats ranging from wetlands to open plains and open areas (Shek, 2006). It is also protected under the Wild Animals Protection Ordinance (Cap.170).

 

6.4.71           One Brown Rat Rattus norvegicus was recorded in a ditch at Lok Ma Chau during a night survey on 17 July 2008 and seven Domestic Oxes were observed foraging and resting in marsh and fishpond bunds of Ta Sha Lok. These two species are widely distributed in Hong Kong but not protected under the local legislations.

 

 

Birds

 

6.4.72           A significant portion of wetland-dependent bird species was recorded in this section as a result of large area of wetland habitat. The less disturbed and continuous wetland habitat in close proximity to hillside shrub supports a wide variety of wetland-dependent birds and a few species of raptor such as Bonelli’s Eagle Hieraaetus fasciatus.

 

Results of transect survey

 

6.4.73           A total of 75 species was recorded during the transect surveys in Section 2, of which 35 species are of conservation concern. A full list of species recorded is given in Table F-2c in Appendix F. The species recorded in this section of Assessment Area are mixture of wetland-dependent birds, shrubland birds and open country area birds. Those shrubland and open country birds recorded are common and widespread throughout Hong Kong territory while the wetland-dependent birds recorded are uncommon in Hong Kong but common throughout the Deep Bay area.

 

Table 69     Mean of individuals of bird species of conservation concern and wetland-dependent bird species recorded during transect survey in section 2 Assessment Area, Nov 2007 - Oct 2008. (Level of Concern based on Fellowes et al. 2002)

Common Name

Level of Concern

Wetland-dependent

Mean#

Little Grebe

Tachybaptus ruficollis

LC

 Y

5.22

Great Crested Grebe

Podiceps cristatus

RC

 Y

0.11

Great Cormorant

Phalacrocorax carbo

PRC

 Y

66.11

Grey Heron

Ardea cinerea

PRC

 Y

7.89

Purple Heron

Ardea purpurea

RC

 Y

0.22

Great Egret

Egretta alba

PRC(RC)

 Y

10.44

Little Egret

Egretta garzetta

PRC(RC)

 Y

13.78

Cattle Egret

Bubulcus ibis

(LC)

 Y

1.00

Chinese Pond Heron

Ardeola bacchus

PRC(RC)

 Y

10.11

Striated Heron

Butorides striatus

(LC)

 Y

0.11

Black-crowned Night Heron

Nycticorax nycticorax

(LC)

 Y

6.56

Yellow Bittern

Ixobrychus sinensis

(LC)

 Y

0.33

Cinnamon Bittern

Ixobrychus cinnamomeus

LC

 Y

0.11

Great Bittern

Botaurus stellaris

RC

 Y

0.22

Eurasian Wigeon

Anas penelope

RC

 Y

0.22

Common Teal

Anas crecca

RC

 Y

3.00

Northern Pintail

Anas acuta

RC

 Y

0.33

Tufted Duck

Aythya fuligula

LC

 Y

2.78

Osprey

Pandion haliaetus

RC

 Y

0.11

Black Kite

Milvus migrans

(RC)

 N

7.78

White-bellied Sea Eagle

Haliaeetus leucogaster

(RC)

 Y

0.11

White-breasted Waterhen

Amaurornis phoenicurus

 -

 Y

2.56

Common Moorhen

Gallinula chloropus

 -

 Y

2.44

Eurasian Coot

Fulica atra

RC

 Y

1.00

Black-winged Stilt

Himantopus himantopus

RC

 Y

0.11

Little Ringed Plover

Charadrius dubius

(LC)

 Y

10.11

Green Sandpiper

Tringa ochropus

 -

 Y

2.00

Wood Sandpiper

Tringa glareola

LC

 Y

0.78

Common Sandpiper

Actitis hypoleucos

 -

 Y

19.00

Common Snipe

Gallinago gallinago

 -

 Y

1.89

Little Swift

Apus affinis

 -

 Y

7.11

Pied Kingfisher

Ceryle rudis

(LC)

 Y

2.00

Common Kingfisher

Alcedo atthis

 Y

0.67

White-throated Kingfisher

Halcyon smyrnensis

(LC)

 Y

4.22

Barn Swallow

hirundo rustica

 -

 Y

3.78

Red-rumped swallow

Hirundo daurica

 -

 Y

1.67

Yellow Wagtail

Motacilla flava

 -

 Y

4.44

Grey Wagtail

Motacilla cinerea

 -

 Y

0.78

White Wagtail

Motacilla alba

 -

 Y

7.56

Red-throated Pipit

Anthus cervinus

LC

 N

0.11

Pallas's Grasshopper Warbler

Locustella certhiola

LC

 Y

0.11

Zitting Cisticola

Cisticola juncidis

LC

 N

1.11

Red-billed Starling

Sturnus sericeus

(RC)*

 Y

18.67

White-cheeked Starling

Sturnus cineraceus

PRC

 N

1.56

White-shouldered Starling

Sturnus sinensis

(LC)

 N

17.00

Ashy Drongo

Dicrurus leucophaeus

LC

 N

0.11

Collared Crow

Corvus torquatus

LC

 Y

0.44

Level of concern follows Fellowes et al. (2002): LC=Local Concern; RC=Regional Concern; GC=Global Concern; PRC=Potential Regional Concern; PGC=Potential Global Concern. Letters in parentheses indicate that the assessment is on the basis of restrictedness in breeding and/or roosting sits rather than in general occurrence.

#Mean values given are the mean number recorded on all transects. This is included to reflect the regularity of a species in the study area.

*Red-billed Starling is considered by Fellowes et al. (2002) to be of Global Concern. Since then, the global population has been increasing and the species is not now considered globally threatened (BirdLife International 2008a). A listing of Regional Concern (RC), based on the importance of the large roosts present near Deep Bay, is considered to be more appropriate.

 

Monthly monitoring of waterbirds at fishpond area by Hong Kong Bird Watching Society

 

6.4.74           The abundance and diversity of waterbirds utilizing fishponds in Deep Bay area are monthly surveyed by the Hong Kong Bird Watching Society as part of the long-term monitoring of the Ramsar Site for AFCD. The ponds within section 2 Assessment Area largely lie into count area Shenzhen River B.

 

6.4.75           A checklist of wetland-dependent birds utilizing the fishpond and river area at Section 2 was obtained by summarizing five years waterbird monitoring data for count area at Shenzhen River B (Table 6-10). A total of 65 wetland-dependent species was recorded at the area including two globally threatened species Greater Spotted Eagle Aquila clanga and Imperial Eagle Aquila heliaca.


Table 610   Wetland-dependent bird species recorded in the Shenzhen River B count area on monthly waterbird counts conducted by the Hong Kong Bird Watching Society, April 2003 - March2008 (Data from Anon 2008, Anon 2007a, Anon 2007b, Anon 2006a, Anon 2006b, Anon 2005a, Anon 2005b, Anon 2004a, Yu 2004 and Yu 2003)

Common Name

Species Name

Level of Concern

IUCN 2008

Little Grebe

Tachybaptus ruficollis

LC

-

Great Cormorant

Phalacrocorax carbo

PRC

-

Purple Heron

Ardea purpurea

RC

-

Grey Heron

Ardea cinerea

PRC

-

Great Egret

Egretta alba

PRC(RC)

-

Little Egret

Egretta garzetta

PRC(RC)

-

Cattle Egret

Bubulcus ibis

(LC)

-

Chinese Pond Heron

Ardeola bacchus

PRC(RC)

-

Striated Heron

Butorides striatus

(LC)

-

Black-crowned Night Heron

Nycticorax nycticorax

(LC)

-

Yellow Bittern

Ixobrychus sinensis

(LC)

-

Cinnamon Bittern

Ixobrychus cinnamomeus

LC

-

Falcated Duck

Anas falcata

RC

-

Common Teal

Anas crecca

RC

-

Greater Scaup

Aythya marila

 -

-

Gadwall

Anas strepera

 -

-

Northern Pintail

Anas acuta

RC

-

Spot-billed Duck

Anas poceilorhyncha

RC

-

Tufted Duck

Aythya fuligula

LC

-

Eurasian Wigeon

Anas penelope

RC

-

Northern Shoveler

Anas clypeata

RC

-

Mallard

Anas platyrhynchos

RC

-

Common Pochard

Aythya ferina

 -

-

Osprey

Pandion haliaetus

RC

-

Black-winged Kite

Elanus caeruleus

LC

-

Black Kite

Milvus migrans

(RC)

-

Common Buzzard

Buteo buteo

 -

-

Crested Serpent Eagle

Spilornis cheela

(LC)

-

Grey-faced Buzzard

Butastur indicus

 -

-

Pied Harrier

Circus melanoleucos

LC

-

Greater Spotted Eagle

Aquila clanga

GC

VU

Imperial Eagle

Aquila heliaca

GC

VU

Bonelli's Eagle

Hieraaetus fasciatus

(RC)

-

Besra

Accipiter virgatus

 -

-

Common Kestrel

Falco tinnunculus

 -

-

White-breasted Waterhen

Amaurornis phoenicurus

 -

-

Common Moorhen

Gallinula chloropus

 -

-

Eurasian Coot

Fulica atra

RC

-

Grey-headed Lapwing

Vanellus cinereus

LC

-

Pheasant-tailed Jacana

Hydrophasianus chirurgus

LC

-

Black-winged Stilt

Himantopus himantopus

RC

-

Oriental Partincole

Glareola maldivarum

LC

-

Pacific Golden Plover

Pluvialis fulva

LC

-

Little Ringed Plover

Charadrius dubius

(LC)

-

Kentish Plover

Charadrius alexandrinus

RC

-

Greater Sand Plover

Charadrius leschenaultii

RC

-

Green Sandpiper

Tringa ochropus

 -

-

Wood Sandpiper

Tringa glareola

LC

-

Marsh Sandpiper

Tringa stagnatilis

RC

-

Common Sandpiper

Actitis hypoleucos

 -

-

Common Snipe

Gallinago gallinago

 -

-

Pintail Snipe

Gallinago stenura

 -

-

Swinhoe's Snipe

Gallinago megala

LC

-

Red-necked Stint

Calidris ruficollis

LC

-

Temminck's Stint

Calidris temminckii

LC

-

Long-toed Stint

Calidris subminuta

LC

-

Ruff

Philomachus pugnax

LC

-

Black-headed Gull

Larus ridibundus

PRC

-

Whiskered Tern

Chlidonias hybridus

 -

-

Gull-billed Tern

Sterna nilotica

 -

-

Common Kingfisher

Alcedo atthis

 -

-

Pied Kingfisher

Ceryle rudis

(LC)

-

White-throated Kingfisher

Halcyon smyrnensis

(LC)

-

Red-billed Starling

Sturnus sericeus

GC*

-

Collared Crow

Corvus torquatus

LC

-

Level of concern follows Fellowes et al. (2002): LC=Local Concern; RC=Regional Concern; GC=Global Concern; PRC=Potential Regional Concern; PGC=Potential Global Concern. Letters in parentheses indicate that the assessment is on the basis of restrictedness in breeding and/or roosting sites rather than in general occurrence.

*Red-billed Starling is considered by Fellowes et al. (2002) to be of Global Concern. Since then, the global population has been increasing and the species is not now considered globally threatened (BirdLife International 2008a). A listing of Regional Concern (RC), based on the importance of the large roosts present near Deep Bay, is considered to be more appropriate.

 

Herpetofauna

 

6.4.76           A total of 14 amphibian and reptile species were recorded during daytime and night surveys. Most of them were found at the fishponds, marshes, streams, agricultural lands and developed area. Four snake species are considered of conservation concern namely Burmese Python Python molurus, Chinese Cobra Naja atra, Chinese Water Snake Enhydris chinensis and Common Rat Snake Ptyas mucosus. Burmese Python considered as Potential Regional Concern (Fellows et al., 2002), was recorded hibernating at riparian vegetation of Lok Ma Chau fishpond bund in vicinity to the Project Area (Figure 6.4 and Plate F16) on 14 February 2008. Burmese Python was stated as ‘Critically Endangered’ in the China Red Data Book and was protected under the Wild Animals Protection Ordinance (Cap. 170) and listed in Protection of Endangered Species of Animals and Plants Ordinance (Cap. 586). This species is widely distributed in the Hong Kong territory, including all major islands (Karsen, 1998).

 

6.4.77           One Chinese Cobra was recorded on 5 September 2008 at riparian vegetation of fishpond bund during night survey at Lok Ma Chau (Plate F17). Chinese Cobra is considered as Potential Regional Concern (Fellowes et al., 2002). It also listed as vulnerable species in the China Red Data Book and protected under Cap. 586. Another snake species Chinese Water Snake was recorded at Lok Ma Chau stream on 13 August 2008. It is listed as ‘Least Concern’ in the China Red Data Book. This species distributed in freshwater or brackish wetlands in central and northern New Territories (Karsen, 1998). A Common Rat Snake listed as “Endangered” in the China Red Data Book, protected under Cap. 586 and considered as Potential Regional Concern was recorded in a stream at Lok Ma Chau during a daytime survey on 25 September 2008. This species is common in open habitats throughout Hong Kong.

 

6.4.78           Seven frog species were recorded in Section 2. The most abundant species are Asian Common Toad Bufo melanostictus and Günther’s Frog Rana guentheri. Most of them were observed or heard in riparian vegetation along fishpond bunds. Few of them were recorded around the existing boundary fence, patrol road and developed area of the Project Area. Table 6-11 summarises the relative abundance of herpetofauna species recorded in Section 2.

Table 611   Relative abundance of herpetofauna species recorded in Section 2

Species

Project Area

Assessment Area (other than Project Area)

Commonness

Level of Concern/ Protection Status

Asian Common Toad

(Bufo melanostictus)

++

 

++++

 

Widely Distributed

 

Asiatic Painted Frog

(Kaloula pulchra pulchra)

+

++

Widely Distributed

 

Brown Tree Frog

(Polypedates megacephalus)

 

+

Common and Abundant, Widespread throughout Hong Kong

 

Günther's Frog

(Rana guentheri)

++

++++

Widely Distributed

 

Ornate Pigmy

(Microhyla ornata)

+

 

Widely Distributed

 

Paddy Frog

(Rana limnocharis)

+

++

Widely Distributed

 

Spotted Narrow-mouthed Frog

(Kalophrynus interlineatus)

+

+

Widely distributed from low to moderate altitudes in northern and central New Territories

 

Chinese Gecko

(Gekko chinensis)

+

++

Widely Distributed

 

Chinese Waterside Skink (Tropidophorus sinicus)

 

+

Widely distributed in streams

 

Burmese Python

(Python molurus)

+

 

Widely Distributed

Protected under Cap. 170 & Cap. 586; Listed as Critically Endangered in China Red Data Book; Listed in IUCN 2008 as Lower Risk/near threatened; Considered as Potential Regional Concern in Fellowes et al. (2002)

Chinese Cobra

(Naja atra)

 

+

Widely Distributed

Protected under Cap. 586; Listed as Vulnerable in China Red Data Book; Considered as Potential Regional Concern

Chinese Water Snake

(Enhydris chinensis)

 

+

Distributed in freshwater or brackish wetlands in central and northern New Territories

Listed as Least Concern in China Red Data Book

Common Rat Snake

(Ptyas mucosus)

 

+

Widely distributed

Protected under Cap. 586; Listed as Endangered in China Red Data Book; Considered as Potential Regional Concern

Taiwan Kukri Snake

(Oligodon formosanus)

 

+

Widely distributed

 

Note: +- 1-3; ++- 4-6; +++- 7-10; ++++- >10

 

Dragonflies and Butterflies

 

6.4.79           There were 23 species of odonata recorded in Section 2. Most of them were found at wetland area including the fishpond margin, grassland and streams. Only 8 species with mean number less than 1 individual per visit were recorded within the Project Area. The most abundant species recorded within the Assessment Area is Variegated Flutterer Rhyothemis variegata, with mean number of individual recorded per visit as 85. All species recorded are either abundant or common in wetland habitats. One species Scarlet Basker Urothemis signata of local concern was recorded mostly in the fishponds with 3.44 mean number of individual per visit. This species becomes common in New Territories as many fishponds have been abandoned and choked with aquatic vegetation to which the dragonfly fond. Table 6-12 summarises the odonata species recorded in Section 2.

Table 612   Odonata species recorded in Section 2

Species

Project Area

(mean no. of individual per visit)

Assessment Area Other than Project Area (mean no. of individual per visit)

Commonness

Level of Concern

Amber-winged Glider

(Hydrobasileus croceus)

 

2 (0.22)

Common and widely distributed

 

Asian Amberwing

(Brachythemis contaminata)

6 (0.67)

142 (15.78)

Abundant and widely distributed

 

Asian Pintail

(Acisoma panorpoides panorpoides)

 

38 (4.22)

Common and widely distributed

 

Blue Dasher

(Brachydiplax chalybea flavovittata)

1 (0.11)

2 (0.22)

Common and widely distributed

 

Blue Percher

(Diplacodes trivialis)

 

2 (0.22)

Abundant and widely distributed

 

Common Bluetail

(Ischnura senegalensis)

 

1 (0.11)

Abundant and widely distributed

 

Common Flagetail

(Ictinogomphus pertinax)

 

6 (0.67)

Abundant and widely distributed

 

Common Red Skimmer

(Orthetrum pruinosum neglectum)

 

14 (1.56)

Abundant and widely distributed

 

Crimson Darter

(Crocothemis servilia servilia)

2 (0.22)

41 (4.56)

Abundant and widely distributed

 

Crimson Dropwing

(Trithemis aurora)

 

5 (0.56)

Abundant and widely distributed

 

Evening Skimmer

(Tholymis tillarga)

 

2 (0.22)

Common and widely distributed

 

Green Skimmer

(Orthetrum sabina sabina)

2 (0.22)

50 (5.56)

Common and widely distributed

 

Lesser Blue Skimmer

(Orthetrum Triangulare)

 

2 (0.22)

Common and widely distributed

 

Orange-faced Sprite

(Pseudagrion rubriceps rubriceps)

1 (0.11)

3 (0.33)

Common and widely distributed in ponds

 

Orange-tailed Midget

(Agriocnemis femina oryzae)

 

1 (0.11)

Abundant and widely distributed

 

Orange-tailed Sprite (Ceriagrion auranticum)

 

25 (2.78)

Abundant and widely distributed

 

Pale-spotted Emperor

(Anax guttatus)

 

1 (0.11)

Abundant and widely distributed

 

Pied Percher

(Neurothemis tullia tullia)

 

14 (1.56)

Common and widely distributed

 

Pied Skimmer

(Pseudothemis zonata)

 

20 (2.22)

Common and widely distributed

 

Saddlebag Glider

(Tramea virginia)

2 (0.22)

8 (0.89)

Common and widely distributed

 

Scarlet Basker

(Urothemis signata)

 

31 (3.44)

Common in areas with abundant fishponds

Considered as Local Concern

Variegated Flutterer

(Rhyothemis variegata)

6 (0.67)

765 (85)

Common and widely distributed

 

Wandering Glider

(Pantala flavescens)

8 (0.89)

423 (47)

Abundant and widely distributed

 

Note: Commonness follows Hong Kong Biodiversity Database (AFCD, 2006).

 

6.4.80           Baron Euthalia aconthea with conservation status defined as ‘Local Concern’ (Fellows et al, 2002) was recorded at the grassland of Lok Ma Chau Loop on 17 July 2008. This species is uncommon in Hong Kong and was recorded from Tai Po Kau, Shing Mun, Pat Sin Leng, Plover Cove and Sai Kung West (Lo and Hui 2005).

 


Table 613   Butterfly species recorded in Section 2

Species

Project Area

(mean no. of individual per visit)

Assessment Area Other than Project Area (mean no. of individual per visit)

Commonness

Level of Concern

Angled Castor

(Ariadne ariadne)

1 (0.11)

 

1 (0.11)

Common and widely distributed

 

Banana Skipper

(Erionota torus)

2 (0.22)

3 (0.33)

Common and widely distributed in agricultural field

 

Baron

(Euthalia aconthea)

 

1 (0.11)

 

Uncommon but widely distributed in woodland

Considered as Local Concern

Black Prince

(Rohana parisatis)

 

14 (1.56)

Common and widely distributed in woodland

 

Blue Admiral

(Kaniska canace canace)

 

2(0.22)

Common and widely distributed

 

Blue Pansy

(Junonia orithya)

 

1(0.11)

Uncommon

 

Blue-spotted Crow

(Euploea midamus)

 

1(0.11)

Common and widely distributed

 

Chinese Dart

(Potanthus confucius confucius)

 

1 (0.11)

Common and widely distributed in Grassland

 

Common Bluebottle

(Graphium sarpedon)

1 (0.11)

14 (1.56)

Common and widely distributed

 

Common Five-ring

(Ypthima baldus)

 

8 (0.89)

Common and widely distributed in Grassland

 

Common Grass Yellow

(Eurema hecabe)

2 (0.22)

49 (5.44)

Common and widely distributed

 

Common Hedge Blue

(Acytolepis puspa)

 

1 (0.11)

Common and widely distributed

 

Common Indian Crow

(Euploea core)

1 (0.11)

6 (0.67)

Common and widely distributed

 

Common Jay

(Graphium doson)

 

1 (0.11)

 

Uncommon but widely distributed

 

Common Mime

(Chilasa clytia)

2 (0.22)

3 (0.33)

Common and widely distributed

 

Common Mormon

(Papilio polytes)

16(1.78)

34(3.78)

Common and widely distributed

 

Common Sailer

(Neptis hylas)

1(0.11)

2(0.22)

Common and widely distributed

 

Common Sergeant

(Athyma perius)

3(0.33)

14(1.56)

Common and widely distributed

 

Common Straight Swift

(Parnara guttata)

 

2(0.22)

Common and widely distributed in Grassland

 

Common Tiger

(Danaus genutia)

1(0.11)

4(0.44)

Common and widely distributed

 

Dark-brand Bush Brown

(Mycalesis mineus)

 

28(3.11)

Common and widely distributed

 

Gram Blue

(Euchrysops cnejus)

 

1(0.11)

Common and widely distributed

 

Great Eggfly

(Hypolimnas bolina kezia)

 

9(1)

Common and widely distributed

 

Great Mormon

(Papilio memnon)

2(0.22)

3(0.33)

Common and widely distributed

 

Indian Cabbage White

(Pieris canidia)

11(1.22)

95(10.56)

Common and widely distributed

 

Large Faun

(Faunis eumeus)

 

1(0.11)

Common and widely distributed

 

Lemon Emigrant

(Catopsilia pomona)

 

5(0.56)

Common and widely distributed

 

Lesser Grass Blue

(Zizina otis)

 

5(0.56)

Common and widely distributed

 

Lime Butterfly

(Papilio demoleus)

 

1(0.11)

Common and widely distributed

 

Long-tailed Blue

(Lampides boeticus)

 

3(0.33)

Common and widely distributed in abandoned field

 

Pale Grass Blue

(Zizeeria maha)

 

37(4.11)

Common and widely distributed

 

Paris Peacock

(Papilio paris)

4(0.44)

9(1)

Common and widely distributed

 

Peacock Pansy

(Junonia almana)

 

6(0.67)

Common and widely distributed

 

Plum Judy

(Abisara echerius)

 

1(0.11)

Common and widely distributed

 

Purple Sapphire

(Heliophorous epicles phoenicoparyphus)

 

2(0.22)

Common and widely distributed

 

Red-base Jezebel

(Delias pasithoe)

 

3(0.33)

Common and widely distributed

 

Rustic

(Cupha erymanthis)

 

2(0.22)

Common and widely distributed

 

Swallowtail

(Papilio xuthus)

 

1(0.11)

Uncommon

 

 

White-edged Blue Baron

(Euthalia phemius seitzi)

 

2(0.22)

Common and widely distributed

 

Note: Commonness follows Hong Kong Biodiversity Database (AFCD, 2006).

 

Aquatic Fauna

 

6.4.81           Six freshwater fish species were recorded in this section. Most of them are food fish, such as Spotted Snakehead, Chinese Catfish and Common Carp, cultivated in the active fishponds around Lok Ma Chau and Ta Sha Lok. Three introduced species namely Nile Tilapia, Mosquito Fish and Redbelly Tilapia, were recorded in the abandoned meander of Shenzhen River at Lok Ma Chau Loop and small streams and ditches around Shun Yee San Tsuen and Ta Sha Lok. No rare and species of conservation concern recorded in this section. Table 6-14 summarises the freshwater fish species recorded in Section 2.


Table 614   Freshwater fish species recorded in Section 2

Species

Relative Abundance

Habitat

Status

Chinese Catfish

(Clarias fuscus)

++++

Shenzhen River, fishponds, marsh, ditch

Common

Nile Tilapia

(Oreochromis niloticus)

++++

Shenzhen River

Common and widespread, introduced species

Mosquito Fish

(Gambusia affinis)

++++

Stream

Common, introduce species.

Redbelly Tilapia

(Tilapia zillii)

++++

Ditch

Common, introduce species.

Spotted Snakehead

(Channa maculata)

+

Fishpond

Food fish and cultivated in fishponds

Common Carp

(Cyprinus carpio)

++

Fishpond

Cultivated in fishponds as food fish or for aquarium

Note: Status follows Lee et al. (2004).

 

Ecological Profile of Section 3 (Man Kam To-Ta Kwu Ling-Pak Fu Shan-Lin Ma Hang)

 

Habitat & Vegetation

 

6.4.82           This is the longest section of the Project (Figure 6.1), running from Lo Wu to Lin Ma Hang via Man Kam To, Ta Kwu Ling and Pak Fu Shan. Most of the proposed alignment will be along the existing boundary road (i.e. the blue alignment) with two short sections of red and green alignments near Pak Fu Shan.

 

6.4.83           Two mitigation areas of the Shenzhen River Regulation Project Stage III were identified at Yuen Leng Chai and Nam Hang (Figure 6.6). As described in Section 6.3.6, Yuen Leng Chai Mitigation Area was established by restoration of two fishponds after the completion of the Shenzhen River Regulation Project. The Nam Hang Mitigation Area was established as a compensatory woodland for the Shenzhen River Regulation Project but its vegetation cover currently is dominated by grasses and herbs such as Sesbania javanica, Mimosa pudica, Pennisetum purpureum, Neyraudia reynaudiana, Rhynchelytrum repens and Ipomoea cairica with few mitigation shrub and tree plantings such as Cinnamomum camphora, Liquidambar formosana, Acacia confusa, Ficus superba, Gardenia jasminoides and Rhaphiolepis indica. Therefore the habitat is shown as grassland (i.e. Abandoned Agricultural Land/ Low-lying Grassland) rather than woodland in the habitat map.

 

6.4.84           The Nam Hang woodland east of these two mitigation areas and west of the Man Kam To Boundary Crossing is the largest woodland within the Assessment Area of Section 3. Sterculia lanceolata, Celtis sinensis, Cinnamomum camphora, Bridelia tomentosa, Microcos paniculata and Macaranga tanarius are the dominant plant species. Its close proximity to the two fishponds establishes an ecological linkage between the two habitats.

 

6.4.85           Lin Ma Hang Stream SSSI and Lin Ma Hang Lead Mines SSSI are located within the Assessment Area near the eastern end of the alignment of Section 3. Lin Ma Hang Lead Mines SSSI is located more than 100m away from the proposed alignment. Lin Ma Hang Stream SSSI is in close proximity to the proposed blue alignment where the existing primary boundary fence and boundary patrol road situated. It is a semi-natural stream with some modification due to its surrounding agricultural land use in the past. The proposed secondary boundary fence will be on the opposite side of the primary boundary fence and thus further away from the stream.

 

6.4.86           Three fung shui woods at Kan Tau Wai, Tsung Yuen Ha and Lin Ma Hang were identified within the Assessment of Section 3. Cinnamomum camphora, Celtis sinensis, Aquilaria sinensis, Schima superba, Aporosa dioica and Syzygium levinei are the dominant species. Other woodlands found within the Assessment Area are secondary woodlands. Dominant species include Aquilaria sinensis, Aporusa dioica, Celtis sinensis, Cinnamomum camphora, Cratoxylum cochinchinense, Mallotus paniculatus, Schefflera heptaphylla and Schima superba.

 

6.4.87           Hillside grassland is a common habitat at Nam Hang and Lin Ma Hang (Figure 6.2). Arundinella sp., Ischaemum sp. and Dicranopteris pedata are common dominant species of the habitat. Shrublands were found on some hillsides, Rhodomyrtus tomentosa, Melastoma candidum, Melastoma sanguineum, Ficus hirta, Litsea rotundifolia, Ilex asprella, Phyllanthus reticulates and Desmos chinensis are the common plant species recorded in this habitat.

 

6.4.88           The Ta Kwu Ling area (Figure 6.7) is a large low-lying flatland where a large numbers of scattered abandoned agricultural lands / low-lying grasslands, active agricultural lands, marsh, plantations, ponds, roads and villages distributed. Apart from the downstream section west of the Ping Yuen River, the Shenzhen River found in this section is un-channelised. The river is in very close proximity to the highly urbanised Shenzhen Town.

 

6.4.89           Wet agricultural land can be found in the area west of Ping Yuen River. Other than the crop Ipomoea aquatica, common wetland species such as Panicum repens, Eclipta prostrata, and Ammannia areneria can also be found in the edges of the farmlands.

 

Blue and Green Alignment

 

6.4.90           The Project Area of the blue and green alignment in Section 3 is proposed on the existing Boundary Patrol Road and therefore in terms of habitat, it will only cover developed area.

 

6.4.91           A total of 270 species were identified. Dominant plant species include Sesbania javanica, Mimosa pudica, Cynodon dactylon, Imperata koenigii, Brachiaria mutica, Eleusine indica, Flueggea virosa, Phyllanthus reticulates, Pennisetum purpureum, Vitex negundo, Bidens alba, Mallotus apelta, Neyraudia reynaudiana, Dicranopteris pedata and Microstegium ciliatum. Mikania micrantha, Paederia scandens, Lygodium japonicum and Ipomoea cairica are common climbers along the existing patrol road.

 

6.4.92           One young individual of Aquilaria sinensis (of height less than 1.5m) was found within the proposed Project Area (roadside along a section of Lin Ma Hang Road northwest of Wang Lek, Figure 6.8). Aquilaria sinensis is scheduled under the under Protection of Endangered Species of Animals and Plants Ordinance (Cap 586) which aims to restrict the import, export and possession of certain animals and plants. It is also listed as Near Threatened (NT) in Mainland China. In Hong Kong, it is a common tree species with wide spreading distribution.

 

6.4.93           The plant list of the Project Area of the blue and green alignment in Section 3 is presented in Table F-3a in Appendix F.

 

Red Alignments

 

6.4.94           The whole red alignment runs through the riparian grassland along the unchannelised Shenzhen River and therefore dominated by common riparian plant species Bidens alba, Panicum maximum and Pennisetum purpureum. A total of 32 species were identified.

 

6.4.95           Neither protected nor rare plant species were identified. The plant list of the Project Area of the red alignment in Section 3 is presented in Table F-3b in Appendix F.

 

Fauna

 

6.4.96           Section 3 covers the area of Yuen Leng Chai and Nam Hang (T8_YLC&NH refers to Figure F1 of Appendix F), Ta Kwu Ling (T9_TKLV), Pak Fu Shan (T10_PFS) and Lin Ma Hang (T11_LMH). The ecological survey findings for fauna species are described below.

 

Mammals 

 

6.4.97           Mammals recorded in this section are dominated by bats emerged after sunset. From literature review, Lin Ma Hang Lead Mines SSSI was recognized as the most important resting and breeding roost site for Greater Bent-winged Bat Miniopterus magnater and Lesser Bent-winged Bat Miniopterus pusillus. Endangered species Common Bent-winged Bat Miniopterus schreibersii listed in IUCN and China Red Data Book was also recorded (Shek and Chan, 2005). Other uncommon species to be found in the area included Intermediate Horseshoe Bat Rhinolophus affinus, Least Horseshoe Bat Rhinolophus pusillus, Rickett's Big-footed Bat Myotis ricketti and Chinese Myotis Myotis chinensis (Shek and Chan, 2005). Himalayan Leaf-nosed Bat Hipposideros armiger, Japanese Pipistrelle Pipistrellus abramus and Lesser Bamboo Bat Tylonycteris pachypus were also recorded by mist netting surveys conducted by Agriculture, Fisheries and Conservation Department (AFCD) in 2005 (Shek, 2006).

 

6.4.98           Five mammal species Malayan Porcupine Hystrix brachyuran, Wild Boar Sus scrofa, Ferret Badger Melogale moschata, Indian Muntjac Muntiacus muntjak and Small Indian Civet Viverra indica were recorded by infrared camera trapping under A Pilot Biodiversity Study of the Eastern Frontier Closed Area and North East New Territories (KFBG, 2004). Among these species, Indian Muntjac and Malayan Porcupine are considered as “Potential Regional Concern” and “Potential Global Concern” (Fellowes et al., 2002). Apart from the five mammal species recorded above, the rare species Crab-eating Mongoose Herpestes urva and Yellow-bellid Weasel Mustela kathiah considered as “Local Concern” were also recorded in woodland habitats of Lin Ma Hang by camera trapping (AFCD, 2006). The Ferret Badger, Small Indian Civet and Crab-eating Mongoose are protected under Cap. 170.

 

6.4.99           Night surveys conducted during July to October 2008 recorded two non-flying mammals which include Roof Rat Rattus rattus recorded in abundant around the existing boundary fence and patrol road adjacent to a chicken farm at Pak Fu Shan and a few individuals of Brown Rat Rattus norvegicus in grassland of Pak Fu Shan. Roof Rat is largely commensal with human and lives in close association with people, while Brown Rat favours moist habitats and compete with Roof Rat for habitat.

 

6.4.100       Small Asian Mongoose Herpestes javanicus is also common in this section. Three individuals were recorded at the Ping Yuen River and one individual was recorded sneaking out the existing boundary fence at Pak Fu Shan during daytime surveys. This species is protected under the Wild Animals Protection Ordinance (Cap. 170) but has a fairy wide distribution in wetland and open plains (Shek, 2006).

 

6.4.101       Domestic sheep of 20 individuals and a domestic cat were recorded in Lin Ma Hang and Yuen Leng Chai respectively. No other species of conservation concern is recorded other than the bats species which are all protected under Cap.170.          

 

Birds

 

6.4.102       A mixture of wetland and agriculture land birds was recorded in this section. Most of the birds recorded are common in Hong Kong territory. A few of woodland bird species were recorded in the woodland habitat of this section, which include a conservation concerned species Orang-headed Thrush Zoothera citrina in Lin Ma Hang secondary forest.  

 

Results of transect survey

 

6.4.103       A total of 66 species was recorded during the transect surveys in Section 3, of which 20 species are of conservation concern including the globally threatened species Greater Spotted Eagle Aquila clanga. A full list of species recorded is given in Table F-3c in Appendix F. The species recorded in this section of Assessment Area are mixture of wetland-dependent birds, shrubland birds and open country area birds as the area comprise of wide diversity of habitat. Among these, 20 species account for 30 percent of the list are of conservation importance.

Table 615   Mean of individuals of bird species of conservation concern and wetland-dependent bird species recorded during transect survey in Section 3 Assessment Area, Nov 2007- Oct 2008. (Level of Concern based on Fellowes et al. 2002)

Common Name

Level of Concern

Wetland-dependent

Mean#

Grey Heron

Ardea cinerea

PRC

Y

1.11

Great Egret

Egretta alba

PRC(RC)

Y

1.22

Little Egret

Egretta garzetta

PRC(RC)

Y

5.22

Cattle Egret

Bubulcus ibis

(LC)

Y

0.44

Chinese Pond Heron

Ardeola bacchus

PRC(RC)

Y

5.11

Black-crowned Night Heron

Nycticorax nycticorax

(LC)

Y

0.56

Yellow Bittern

Ixobrychus sinensis

(LC)

Y

0.11

Cinnamon Bittern

Ixobrychus cinnamomeus

LC

Y

0.11

Black Kite

Milvus migrans

(RC)

N

0.89

Common buzzard

Buteo buteo

-

Y

0.11

Greater Spotted Eagle

Aquila clanga

GC

Y

0.11

White-breasted Waterhen

Amaurornis phoenicurus

-

Y

0.89

Little Ringed Plover

Charadrius dubius

(LC)

Y

3.78

Common Greenshank

Tringa nebularia

RC

Y

0.11

Green Sandpiper

Tringa ochropus

-

Y

1.78

Wood Sandpiper

Tringa glareola

LC

Y

1.56

Common Sandpiper

Actitis hypoleucos

-

Y

1.67

Common Snipe

Gallinago gallinago

-

Y

0.11

Pacific Swift

Apus pacificus

(LC)

N

0.44

Little Swift

Apus affinis

-

Y

1.56

Pied Kingfisher

Ceryle rudis

(LC)

Y

0.11

Common Kingfisher

Alcedo atthis

-

Y

0.44

White-throated Kingfisher

Halcyon smyrnensis

(LC)

Y

1.00

Barn Swallow

H irundo rustica

-

Y

7.44

Yellow Wagtail

Motacilla flava

-

Y

1.00

Grey Wagtail

Motacilla cinerea

-

Y

0.56

White Wagtail

Motacilla alba

-

Y

9.33

Red-throated Pipit

Anthus cervinus

LC

N

0.33

Zitting Cisticola

Cisticola juncidis

LC

N

0.22

Red-billed Starling

Sturnus sericeus

(RC)*

Y

0.22

Collared Crow

Corvus torquatus

LC

N

0.11

Level of concern follows Fellowes et al. (2002): LC=Local Concern; RC=Regional Concern; GC=Global Concern; PRC=Potential Regional Concern; PGC=Potential Global Concern. Letters in parentheses indicate that the assessment is on the basis of restrictedness in breeding and/or roosting sites rather than in general occurrence.

#Mean values given are the mean number recorded on all transects. This is included to reflect the regularity of a species in the study area.

*Red-billed Starling is considered by Fellows et al. (2002) to be of Global Concern. Since then, the global population has been increasing and the species is not now considered globally threatened (BirdLife International 2008a). A listing of Regional Concern (RC), based on the importance of the large roosts present near Deep Bay, is considered to be more appropriate.

 

Pilot Biodiversity Study at the Eastern Frontier Closed Area by Kadoorie Farm and Botanic Garden

 

6.4.104       A pilot ecological study was conducted in 2003 at the Eastern Frontier Closed Area and North Easet New Territories by various expertises of Kadoorie Farm and Botanic Garden. The Study Area at Lin Ma Hang fung shui woods and secondary forest are situated within the Assessment Area of this proposed project. The bird survey result can be used to supplement the transect survey data.

 

6.4.105       A total of 48 bird species were recorded in the visual surveys and camera trapping. Among these, four species are of conservation concern although most of the species are common and widespread. Also, a few of woodland specialist birds were recorded at the area reflecting the high ecological value of the woodland. Key finding on bird survey is an Orange-headed Thrush recorded by camera trapping in July 2003. Orange-headed Thrush is a scarce passage migrant as well as local breeder with limited distribution in Hong Kong woodland. More sighting record of this species in recent years at other locations reveal the regularity of its migratory pattern but the one recorded in the study at summer is a potential breeder and of conservation concern.

Table 616   Record of conservation concerned species and woodland specialist at Lin Ma Hang fung shui wood and secondary woodland in the pilot biodiversity study conducted by Kadoorie Fam and Botanic Garden. (Data from Kadoorie Farm and Botanic Garden 2004; Level of Concern based on Fellowes et al. 2002)

Common Name

Species Name

Woodland Specialist

Level of Concern

Chinese Pond Heron

 

Ardeola bacchus

 

N

PRC(RC)

Crested Serpent Eagle

 

Spilornis cheela

 

Y

(LC)

 

Crested Goshawk

Accipiter trivirgatus

 

Y

 

Grey Bushchat

 

Saxicola ferrea

 

N

LC

 

Greater Necklaced Laughingthrush

Garrulax pectoralis

 

Y

 

Black-throated Laughingthrush

Garrulax chinensis

 

Y

 

Orange-headed Thrush

 

Zoothera citrina

 

Y

LC

 

Striated Yuhina

Yuhina castaniceps

 

Y

 

Asian Stubtail

Urosphena squameiceps

 

Y

 

Level of concern follows Fellowes et al. (2002): LC=Local Concern; RC=Regional Concern; GC=Global Concern; PRC=Potential Regional Concern; PGC=Potential Global Concern. Letters in parentheses indicate that the assessment is on the basis of restrictedness in breeding and/or roosting sites rather than in general occurrence.

 

Herpetofauna

 

6.4.106       Among the 8 species of herpetofauna recorded in Section 3, all of them are common and widespread (Karsen, 1998) and are not of conservation concern. Five Brown Tree Frog Polypedates megacephalus were recorded resting on the existing boundary fence at Pak Fu Shan during a night survey on 3 October 2008. Other species recorded are mainly in plantation, grassland, stream and marsh off-site of the proposed Project Area. Table 6-17 summarises the Herpetofauna species recorded in Section 3. 

Table 617   Herpetofauna recorded in Section 3

Species

Project Area

Assessment Area (other than Project Area)

Commonness

Asian Common Toad

Bufo melanostictus

 

++++

Widely Distributed

Asiatic Painted Frog

Kaloula pulchra pulchra

 

++

Widely Distributed

Brown Tree Frog

(Polypedates megacephalus)

++

+

Common and Abundant, Widespread throughout Hong Kong

Günther's Frog

Rana guentheri

 

++++

Widely Distributed

Paddy Frog

Rana limnocharis

 

+

Widely Distributed

Spotted Narrow-mouthed Frog

Kalophrynus interlineatus

 

++

Widely distributed from low to moderate altitudes in northern and central New Territories

Chinese Gecko

Gekko chinensis

 

++++

Widely Distributed

Reeve’s Smooth skink

Scincella reevesii

 

++

Widely Distributed

Note: +- 1-3; ++- 4-6; +++- 7-10; ++++- >10

 

Dragonflies and Butterflies

 

6.4.107       Twenty-nine species of dragonflies were recorded in Section 3. All species recorded are common or abundant and widely distributed in Hong Kong. Two dragonfly species, the Sapphire Flutterer Rhyothemis triangularis and Scarlet Basker Urothemis signata of local concern were recorded in Yuen Leng Chai marsh and pond adjacent to the proposed Project Area respectively (Fellows et al, 2002). However, these two species are common and widely distributed in weedy ponds, sluggish rivers and marshes in Hong Kong (Wilson, 2003). Only 4 species Common Blue Skimmer, Red-faced Skimmer, Variegated Flutterer and Wandering Glider of mean number of individual less than 1 were recorded around the proposed alignment. All these species are not of conservation concern and are widely distributed in Hong Kong. Table 6-18 summarises the odonata species recorded in Section 3.

Table 618   Odonata species recorded in Section 3

Species

Project Area

(mean no. of individual per visit)

Assessment Area Other than Project Area (mean no. of individual per visit)

Commonness

Level of Concern

Asian Amberwing

(Brachythemis contaminata)

 

3 (0.33)

Abundant and widely distributed

 

Asian Pintail

(Acisoma panorpoides panorpoides)

 

39 (4.33)

Common and widely distributed

 

Black-kneed Featherlegs

(Copera ciliata)

 

6 (0.67)

Abundant and widely distributed

 

Black Threadtail

(Prodasineura autumnalis)

 

5 (0.56)

Abundant and widely distributed

 

Blue Dasher

(Brachydiplax chalybea flavovittata)

 

15 (1.67)

Common and widely distributed

 

Chinese Greenwing

(Neurobasis chinensis chinensis)

 

1 (0.11)

Common and widely distributed

 

Common Bluetail

(Ischnura senegalensis)

 

20 (2.22)

Abundant and widely distributed

 

Common Blue Jewel

(Rhinocypha perforata perforata)

 

5 (0.56)

Abundant and widely distributed

 

Common Blue Skimmer

(Orthetrum glaucum)

1 (0.11)

11 (1.22)

Abundant and widely distributed

 

Common Red Skimmer

(Orthetrum pruinosum neglectum)

 

50 (5.56)

Abundant and widely distributed

 

Crimson Darter

(Crocothemis servilia servilia)

 

34 (3.78)

Abundant and widely distributed

 

Crimson Dropwing

(Trithemis aurora)

 

35 (3.89)

Abundant and widely distributed

 

Green Skimmer

(Orthetrum sabina sabina)

 

30 (3.33)

Common and widely distributed

 

Indigo Dropwing

(Trithemis festiva)

 

12 (1.33)

Abundant and widely distributed

 

Lesser Blue Skimmer

(Orthetrum Triangulare)

 

1 (0.11)

Common and widely distributed

 

Marsh Skimmer

(Orthetrum luzonicum)

 

18 (2)

Abundant and widely distributed

 

Orange-tailed Midget

(Agriocnemis femina oryzae)

 

1 (0.11)

Abundant and widely distributed

 

Orange-tailed Sprite (Ceriagrion auranticum)

 

16 (1.78)

Abundant and widely distributed

 

Pale-spotted Emperor

(Anax guttatus)

 

4 (0.44)

Abundant and widely distributed

 

Pied Percher

(Neurothemis tullia tullia)

 

85 (9.44)

Common and widely distributed

 

Pied Skimmer

(Pseudothemis zonata)

 

3 (0.33)

Common and widely distributed

 

Red-faced Skimmer

(Orthetrum chrysis)

1 (0.11)

4 (0.44)

Common and widely distributed

 

Russet Percher

(Neurothemis fulvia)

 

1 (0.11)

Abundant and widely distributed

 

Saddlebag Glider

(Tramea virginia)

 

17 (1.89)

Common and widely distributed

 

Sapphire Flutterer

(Rhyothemis triangularis)

 

17 (1.89)

Common and widely distributed

Considered as Local Concern

Scarlet Basker

(Urothemis signata)

 

10 (1.11)

Common in areas with abundant fishponds

Considered as Local Concern

Variegated Flutterer

(Rhyothemis variegata)

1 (0.11)

134 (14.89)

Common and widely distributed

 

Wandering Glider

(Pantala flavescens)

7 (0.78)

247 (27.4)

Abundant and widely distributed

 

Yellow Featherlegs

(Copera marginipes)

 

10 (1.11)

Abundant and widely distributed

 

 

6.4.108       Fifty-one species of butterfly were recorded in Section 3. Nineteen of them were recorded around the existing fence and roadside vegetation along the proposed Project Area. All these species are common and widely distributed in Hong Kong. Three species recorded off-site are considered as having conservation concern. They include the uncommon species Baron Euthalia aconthea of Local Concern (Fellows et al, 2002) recorded at ditch, stream and developed area of Lin Ma Hang and Nam Hang and an uncommon species of Danaid Eggfly Hypolimnas misippus of Local Concern (Fellows et al, 2002) recorded in grassland of Pak Fu Shan. The dominant species recorded in Section 3 are Indian Cabbage White and Common Grass Yellow, which have a wide range of habitat preference, mostly occur in degraded grassland or abandoned field.  Table 6-19 summarises the butterfly species recorded in Section 3.

 

6.4.109       Literature review of other study also recorded two local concern species on the forest edge and fung shui woods of Lin Ma Hang. They are Glassy Bluebottle Graphium cloanthus and Small Grass Yellow Eurema brigitta (KFBG, 2004). These two species were not recorded during this study.

Table 619   Butterfly species recorded in Section 3

Species

Project Area

(mean no. of individual per visit)

Assessment Area Other than Project Area (mean no. of individual per visit)

Commonness

Level of Concern

Angled Castor

(Ariadne ariadne)

2 (0.22)

 

14 (1.56)

Common and widely distributed

 

Banana Skipper

(Erionota torus)

 

2 (0.22)

Common and widely distributed in agricultural field

 

Banded Tree Brown

(Lehte confusa)

 

2 (0.22)

Common and widely distributed in woodland

 

Baron

(Euthalia aconthea)

 

5 (0.55)

 

Uncommon but widely distributed in woodland

Considered as Local Concern

Black Prince

(Rohana parisatis)

 

13 (1.44)

Common and widely distributed in woodland

 

Blue Tiger

(Tirumala limniace)

 

1 (0.11)

Common and widely disturbuted

 

Blue-spotted Crow

(Euploea midamus)

 

13 (1.44)

Common and widely distributed

 

Ceylon Blue Glassy Tiger

(Ideopsis similis)

 

2 (0.22)

Common and widely disturbuted

 

Chinese Dart

(Potanthus confucius confucius)

 

1 (0.11)

Common and widely distributed in Grassland

 

Colour Sergeant

(Athyma nefte)

 

2 (0.22)

Common and widely disturbuted

 

Common Bluebottle

(Graphium sarpedon)

2 (0.22)

12 (1.33)

Common and widely distributed

 

Common Five-ring

(Ypthima baldus)

 

3 (0.33)

Common and widely distributed in Grassland

 

Common Grass Yellow

(Eurema hecabe)

8 (0.89)

117 (13)

Common and widely distributed

 

Common Hedge Blue

(Acytolepis puspa)

 

1 (0.11)

Common and widely distributed

 

Common Indian Crow

(Euploea core)

 

5 (0.56)

Common and widely distributed

 

Common Jay

(Graphium doson)

 

1 (0.11)

 

Uncommon but widely distributed

 

Common Mapwing

(Cyrestis thyodamas)

 

2 (0.22)

Common and widely distributed in woodland area

 

Common Mime

(Chilasa clytia)

5 (0.56)

4 (0.44)

Common and widely distributed

 

Common Mormon

(Papilio polytes)

42 (4.67)

80 (8.89)

Common and widely distributed

 

Common Sailer

(Neptis hylas)

1(0.11)

7 (0.78)

Common and widely distributed

 

Common Sergeant

(Athyma perius)

 

8 (0.89)

Common and widely distributed

 

Common Straight Swift

(Parnara guttata)

 

1 (0.11)

Common and widely distributed in Grassland

 

Common Tiger

(Danaus genutia)

 

12 (1.33)

Common and widely distributed

 

Common Tree Brown

(Lethe rohria permagnis)

1 (0.11)

8 (0.89)

Uncommon and widely distributed in woodland

 

Danaid Eggfly

(Hypolimnas misippus)

 

1 (0.11)

Uncommon

Local Concern

Dark-brand Bush Brown

(Mycalesis mineus)

 

 50 (5.56)

Common and widely distributed

 

Glassy Tiger

(Parantica aglea)

 

2 (0.22)

Common and widely distributed

 

Gram Blue

(Euchrysops cnejus)

1(0.11)

 

Common and widely distributed

 

Great Eggfly

(Hypolimnas bolina kezia)

4 (0.44)

23 (2.56)

Common and widely distributed

 

Great Mormon

(Papilio memnon)

6 (0.67)

24 (2.67)

Common and widely distributed

 

Great Orange Tip

(Hebomoia glaucippe)

 

8 (0.89)

Common and widely distributed

 

Grey Pansy

(Junonia atlites)

 

5 (0.56)

Common and widely distributed in abandoned grassland and abandoned agricultural field

 

Indian Cabbage White

(Pieris canidia)

18 (2)

227 (25.22)

Common and widely distributed

 

Indian Red Admiral

(Vanessa indica)

 

1 (0.11)

Common and widely distributed

 

Large Faun

(Faunis eumeus)

 

6 (0.67)

Common and widely distributed

 

Lemon Emigrant

(Catopsilia pomona)

1 (0.11)

32 (3.56)

Common and widely distributed

 

Long-tailed Blue

(Lampides boeticus)

 

2 (0.22)

Common and widely distributed

 

Mottled Emigrant

(Catopsilia pyranthe)

 

4 (0.44)

Common and widely distributed

 

Pale Grass Blue

(Zizeeria maha)

 

57 (6.33)

Common and widely distributed

 

Paris Peacock

(Papilio paris)

5 (0.56)

8 (0.89)

Common and widely distributed

 

Peacock Pansy

(Junonia almana)

1 (0.11)

9 (1)

Common and widely distributed

 

Plum Judy

(Abisara echerius)

1 (0.11)

9 (1)

Common and widely distributed

 

Purple Sapphire

(Heliophorous epicles phoenicoparyphus)

2 (0.22)

 

Common and widely distributed

 

Red Helen

(Papilio helenus)

1 (0.11)

 

Common and widely distributed

 

Red Ring Skirt

(Hestina assimilis)

 

1 (0.11)

Common and widely distributed in woodland

 

Red-base Jezebel

(Delias pasithoe)

4 (0.44)

1 (0.11)

Common and widely distributed

 

Rustic

(Cupha erymanthis)

 

1 (0.11)

Common and widely distributed

 

Slate Flash

(Rapala manea)

 

1 (0.11)

Common and widely distributed

 

Staff Sergeant

(athyma selenophora)

1 (0.11)

 

Common and widely distributed

 

Straight Five-ring

(Ypthima lisandra)

 

1 (0.11)

Common and widely distributed

 

White-edged Blue Baron

(Euthalia phemius seitzi)

 

2 (0.22)

Common and widely distributed

 

Note: Commonness follows Hong Kong Biodiversity Database (AFCD, 2006).  

 

Aquatic Fauna

 

6.4.110       Fifteen species of aquatic fauna were recorded in Section 3 during the study period. The most concern aquatic fauna in this section are those recorded in Lin Ma Hang Stream SSSI. The stream supports 15 species of primary freshwater fishes including several species of conservation concern Channa asiatica, Mastacembelus armatus, Rasbora steineri and Rasborinus lineatus (DSD, 2007). The ecological baseline survey in this study recorded three species of conservation concern including Chinese Rasbora Rasbora steineri, Precedaceous Chub Parazacco spilurus and Topmouth Gudgeon Pseudorasbora parva (Figure 6.8).They are considered as Global Concern, Vulnerable in China and Local Concern (Fellowes et al., 2002 and Lee et al., 2004) respectively.

 

6.4.111       Topmouth Gudgeon was found at downstream of Lin Ma Hang on 6 December 2007. This species is uncommon in Hong Kong mainly distributed in several streams in North District (Lee et al., 2004). The fish is considered as a pest in Mainland China and is available on market as fish feed. Predaceous chub was recorded in abundant in Lin Ma Hang Stream. This species is common, widely distributed and occurs in most unpolluted hill streams in both upper and lower courses (Lee et al 2004). However, this species is considered as ‘Vulnerable’ in China Red Data Book since the population in China decreases due to habitat loss.

 

6.4.112       Chinese Rasbora is a rare species only recorded in North District and Kam Tin (Lee et al., 2004). This primary freshwater fish occurs in both hill streams and lower reaches of lowland streams. Both juvenile and adult of this fish were recorded in Lin Ma Hang Stream during the study period.

 

6.4.113       Other species recorded in large abundance at streams, ditches and ponds in this section are either common and widespread or introduced species of no conservation concern. Table 6-20 summarises the aquatic fauna species recorded in Section 3. 

Table 620   Aquatic fauna species recorded in Section 3

Species

Relative Abundance

Habitat

Status

Chinese Barb

(Puntius semifasciolatus)

++++

Streams, ponds and drainage channel

Common and widely distributed

Chinese Catfish

(Clarias fuscus)

+

Marsh

Common

Chinese Rasbora

(Rasbora steineri)

++

Lin Ma Hang Stream

Rare; considered as Global Concern

Goldfish

(Carassius auratus)

+++

Stream and pond

Not common in streams but cultivated in fishponds

Guppy

(Poecilia reticulata)

++++

Ditch

Common and occurs in large numbers in many local streams and ponds

Nile Tilapia

(Oreochromis niloticus)

++++

Marsh, pond and river

Common and widespread, introduced species

Mosquito Fish

(Gambusia affinis)

++++

Stream and ditches

Common, introduce species.

Paradise Fish

(Macropodus opercularis)

++

Lin Ma Hang Stream

Common

Predaceous Chub

(Parazacco spilurus)

++++

Lin Ma Hang Stream

Common and widespread; considered as “Vulnerable” in China

Goby

(Rhinogobius duospilus)

+

Lin Ma Hang Stream

Common and widely distributed

Topmouth Gudgeon

(Pseudorasbora parva)

++++

Lin Ma Hang Stream

Uncommon in streams; considered as Local Concern

Common Carp

(Cyprinus carpio)

++++

Fishponds and ponds

Cultivated in fishponds as food fish or for aquarium

Apple Snail

(Pomacea lineata)

++++

Ditches

Exotic species common in drainage channel or irrigation ditches

Freshwater Shrimp

(Caridina cantonensis)

++++

Streams

Common and widespread

Freshwater Shrimp

(Macrobrachium hainanence)

+

Stream

Abundant in pools and breeds in estuaries

Note: Status follows Lee et al. (2004).

 

Ecological Profile of Section 4 (Sha Tau Kok)

 

Habitat & Vegetation

 

6.4.114       The whole alignment of Section 4 will be within the urban area at Sha Tau Kok (Figure 6.9). Apart from the developed area, woodland, marsh and abandoned agricultural land / low-lying grassland are the three largest habitats within the Assessment Area.

 

6.4.115       Woodlands at Sheung Tam Shui Hang, Shan Tsui, and Muk Min Tau are distant with the proposed alignment of nearly 200m. The largest marsh was identified at Shan Tsui are derived from abandoned agricultural land. Colocasia esculenta, Commelina diffusa, Leersia hexandra and Cyclosorus interruptus are dominant species identified within the marsh.

 

6.4.116       Large area of abandoned agricultural land / low-lying grassland was found at west of the Tam Shui Hang Tsuen and the channalised Tam Shui Hang Stream divides the habitat roughly into two halves. Microstegium ciliatum, Ipomoea cairica, Panicum maximum, Imperata koenigii and the common weed climber Mikania micrantha are dominant species.

 

6.4.117       Two small pieces of mangrove were identified at west of the Sha Tau Kok Town. Mangrove species include Kandelia obovata, Avicennia marina and Aegiceras corniculatum. Two fishponds were found adjacent to these mangrove habitats.

 

6.4.118       The whole Section 4 will be within the urban area at Sha Tau Kok. Plants identified within the Project Area are dominated by common landscaping planting typical to similar environments with few weed species. Amenity species include Acacia confusa, Delonix regia, Grevillea robusta, Lagerstroemia speciosa and Elaeocarpus hainanensis are recorded.

 

6.4.119       Neither protected nor rare plant species was identified. A total of 56 species was identified. The plant list of the Project Area of the Section 4 is presented in Table F-4a in Appendix F.

 

Fauna

 

6.4.120       Section 4 covers the Sha Tau Kok alignment and area within 500m from the proposed works boundary. Ecological baseline surveys for fauna species include those areas of ecological interest, such as Tam Shui Hang and Shan Tsui (T12_HTSH&ST refers to Figure F1 of Appendix F).

 

Mammals

 

6.4.121       Apart from bat species recorded foraging over streams, mangrove and marshes are protected under Cap. 170, only Domestic Cats Felis catus and House Mouse Mus musculus were recorded in drainage channels of Sha Tau Kok.

 

6.4.122       From literature review, four bat species were recorded by mist netting or roost census conducted by AFCD in 2003 to 2005 (Shek, 2006). They include Himalayan Leaf-nosed Bat Hipposideros armiger, Japanese Pipistrelle Pipistrellus abramus, Short-nosed Fruit Bat Cynopterus sphinx and Lesser Bamboo Bat Tylonycteris pachypus. The later two species are listed in the China Red Data Book and considered of having local concern but abundant in Hong Kong.

 

Birds

 

6.4.123       Bird species found in this section are all common and widespread in Hong Kong including four conservation concerned species. Pacific swift recorded in this area is of uncommon species but this sky-high gliding species has very little ecological linkage to the habitat.  

 

Results of transect survey

 

6.4.124       A total of 28 species was recorded during the transect surveys in Section 4, of which 5 species are of conservation concern. A full list of species recorded is given in Table F-4b in Appendix F. A high proportion of generalist birds recorded at the transect survey as a result of a dominance of anthropogenic habitat at the Assessment Area in which all the birds recorded are common and widespread in Hong Kong.

Table 621   Mean of individuals of bird species of conservation concern and wetland-dependent bird species recorded during transect survey in Section 4 Assessment Area, Nov 2007- Oct 2008. (Level of Concern based on Fellowes et al. 2002)

Common Name

Level of Concern

Wetland-dependent

Mean#

Black-crowned Night Heron

Nycticorax nycticorax

(LC)

Y

0.25

Black Kite

Milvus migrans

(RC)

N

0.25

White-breasted Waterhen

Amaurornis phoenicurus

 -

Y

0.13

Pacific Swift

Apus pacificus

(LC)

N

0.25

Little Swift

Apus affinis

 -

Y

2.13

White-throated Kingfisher

Halcyon smyrnensis

(LC)

Y

0.75

White Wagtail

Motacilla alba

 -

Y

0.13

Red-billed Starling

Sturnus sericeus

(RC)*

Y

0.50

Level of concern follows Fellowes et al. (2002): LC=Local Concern; RC=Regional Concern; GC=Global Concern; PRC=Potential Regional Concern; PGC=Potential Global Concern. Letters in parentheses indicate that the assessment is on the basis of restrictedness in breeding and/or roosting sites rather than in general occurrence.

#Mean values given are the mean number recorded on all transects. This is included to reflect the regularity of a species in the study area.

*Red-billed Starling is considered by Fellowes et al. (2002) to be of Global Concern. Since then, the global population has been increasing and the species is not now considered globally threatened (BirdLife International 2008a). A listing of Regional Concern (RC), based on the importance of the large roosts present near Deep Bay, is considered to be more appropriate.

 

Herpetofauna

 

6.4.125       Two species of amphibians and six species of reptiles were recorded in Section 4. They include 3 conservation concerned species: Burmese Python Python mourus bibittatus, Common Rat Snake Ptyas mucosus and Chinese Soft-shelled Turtle Pelodiscus sinensis. A Burmese Python juvenile was recorded at a drainage channal near Sha Tau Kok Village during a night survey on 10 September 2008. This conservation concerned species is listed as “Lower Risk/ Near Threatened” in IUCN Red Data List (2008) and as potential regional concern in Fellowes at el. (2002) although it is widely distributed in Hong Kong. Common Rat Snake, a common and widespread species in Hong Kong could be found in a wide variety of habitats, is listed as “Vulnerable” species in China Red Data Book. Chinese Soft-shelled Turtle is a globally threatened species, listed as “Vulnerable” in IUCN Red Data List (2008). This species is rare and localized in Hong Kong but also a common food item sold in Hong Kong markets. Sighting record of this species outside Deep Bay fishponds is thought to be released by the local people (Karsen et al. 1998). The record in Tam Shui Hang Channel in this study was found near a local village is thereby considered as a released individual.  Table 6-22 summarises the herpetofauna recorded in Section 4.


Table 622   Herpetofauna recorded in Section 4

Species

Assessment Area (other than Project Area)

Commonness

Level of Concern/ Protection Status

Asian Common Toad

Bufo melanostictus

+++

Widely Distributed

 

Günther's Frog

Rana guentheri

++++

Widely Distributed

 

Burmese Python

Python mourus bivittatus

+

Widely Distributed

Protected under Cap. 170 & Cap. 586; Listed as Critically Endangered in China Red Data Book; Listed in IUCN 2008 as Lower Risk/near threatened; Considered as Potential Regional Concern in Fellowes et al. (2002)

Chinese Gecko

Gekko chinensis

++

Widely Distributed

 

Chinese Soft-shelled Turtle

Pelodiscus sinensis

+

Locally found in reservoirs and fishponds in Deep Bay area

Listed as Vulnerable in IUCN 2008 and China Red Data Book;

Protected under Cap. 170; Considered as Global Concern in Fellowes et al. (2002)

 

Common Rat Snake

Ptyas mucosus

+

Widely Distributed

Listed as Vulnerable in China Red Data Book;

Protected under Cap. 586

Greater Green Snake

Cyclophiops major

+

Widely Distributed

 

 

Spotted Narrow-mouthed Frog

Kalophrynus interlineatus

+

Widely distributed from low to moderate altitudes in northern and central New Territories

 

Note: (1) +- 1-3; ++- 4-6; +++- 7-10; ++++- >10

           (2) No record within Project Area.

 

Dragonflies and Butterflies

 

6.4.126       Eighteen species of dragonflies were recorded in Section 4 during the study period. All species are recorded off-site at drainage channel and marsh. No species of conservation concern were recorded in this Section. Table 6-23 summarises the odonata species recorded in Section 4.  


Table 623   Odonata species recorded in Section 4

Species

Assessment Area Other than Project Area (mean no. of individual per visit)

Commonness

Asian Amberwing

(Brachythemis contaminata)

4(0.44)

Abundant and widely distributed

Asian Pintail

(Acisoma panorpoides panorpoides)

39(4.33)

Common and widely distributed

Black Threadtail

(Prodasineura autumnalis)

2(0.22)

Abundant and widely distributed

Black-kneed Featherlegs

(Copera ciliata)

4(0.44)

Abundant and widely distributed

Common Blue Skimmer

(Orthetrum glaucum)

32(3.56)

Abundant and widely distributed

Common Bluetail

(Ischnura senegalensis)

1(0.11)

Abundant and widely distributed

Common Red Skimmer

(Orthetrum pruinosum neglectum)

45(0.5)

Abundant and widely distributed

Crimson Darter

(Crocothemis servilia servilia)

3(0.33)

Abundant and widely distributed

Crimson Dropwing

(Trithemis aurora)

14(1.56)

Abundant and widely distributed

Green Skimmer

(Orthetrum sabina sabina)

4(1.44)

Common and widely distributed

Indigo Dropwing

(Trithemis festiva)

8(0.89)

Abundant and widely distributed

Marsh Skimmer

(Orthetrum luzonicum)

34(3.78)

Common and widely distributed

Orange-tailed Midget

(Agriocnemis femina oryzae)

2(0.22)

Abundant and widely distributed

Orange-tailed Sprite

(Ceriagrion auranticum)

2(0.22)

Abundant and widely distributed

Red-faced Skimmer

(Orthetrum chrysis)

2(0.22)

Common and widely distributed

Russet Percher

 (Neurothemis fulvia)

3(0.33)

Abundant and widely distributed

Wandering Glider

(Pantala flavescens)

186(20.67)

Abundant and widely distributed

Yellow Featherlegs

(Copera marginipes)

2(0.22)

Abundant and widely distributed

Note:    (1) Commonness follows Hong Kong Biodiversity Database (AFCD, 2006).

(2) No record within Project Area.

 

6.4.127       Eighteen species of butterfly were recorded in Section 4. All the species recorded are at off-site habitats from the Project Area with status common and widespread in Hong Kong. No species of conservation concern was recorded. Table 6-24 summarises the butterfly species recorded in Section 4.

Table 624   Butterfly species recorded in Section 4

Species

Assessment Area Other than Project Area (mean no. of individual per visit)

Commonness

Banana Skipper

(Erionota torus)

1(0.11)

Common and widely distributed in agricultural field

Black Prince

(Rohana parisatis)

3(0.33)

Common and widely distributed in woodland

Common Bush Brown

(Mycalesis zonata)

1(0.11)

Common and widely distributed in woodland

Common Five-ring

(Ypthima baldus)

2(0.22)

Common and widely distributed in Grassland

Common Grass Yellow

(Eurema hecabe)

8(0.89)

Common and widely distributed

Common Mormon

(Papilio polytes)

9(1.00)

Common and widely distributed

Common Sergeant

(Athyma perius)

12(1.33)

Common and widely distributed

Common Tiger

(Danaus genutia)

1(1.00)

Common and widely distributed

Dark-brand Bush Brown

(Mycalesis mineus)

30(3.33)

Common and widely distributed

Five-bar Swordtail

(Pathysa antiphates)

1(0.11)

Common and widely distributed

Great Mormon

(Papilio memnon)

2(0.22)

Common and widely distributed

Great Orange Tip

(Hebomoia glaucippe glaucippe)

1(0.11)

Common and widely distributed

Indian Cabbage White

(Pieris canidia)

46(5.11)

Common and widely distributed

Lemon Pansy

(Junonia lemonias lemonias)

2(0.22)

Uncommon

Mottled Emigrant

(Catopsilia pyranthe)

2(0.22)

Common and widely distributed

Pale Grass Blue

(Zizeeria maha)

8(0.89)

Common and widely distributed

Peacock Pansy

(Junonia almana)

5(0.56)

Common and widely distributed

Rustic

(Cupha erymanthis)

2(0.22)

Common and widely distributed

Note:    (1) Commonness follows Hong Kong Biodiversity Database (AFCD, 2006).

(2) No record within Project Area.

 

Aquatic Fauna

 

6.4.128       Freshwater fishes recorded in Ha Tam Shui Hang Channel include Predaceous Chub Parazacco spilurus (Figure 6.9), Chinese Barb Puntius semifasciolatus, Barcheek Goby Rhinogobius giurinus, Swordtail Xiphophorus hellerii and Mud Carp Cirrhinus molitorella. Water Skater Ptilomera tigrina and Mitten Crab Eriocheir japonicus were also recorded in this stream. Exotic Apple Snail Pomacea lineata was recorded in irrigation ditches around Tam Shui Hang. Apart from Predaceous Chub is considered as “Vulnerable” in China Red Data Book, no other species of conservation concern was recorded in this section.

 

6.4.129       Fiddler Crabs Uca arcuata and Perisesarma bidens and Mudskipper Periophthalmus modestus were recorded in large abundance in the mangrove at Sha Tau Kok. They are common species recorded in mangrove and mudflat of Hong Kong (Fong et al., 2005).     

 

6.5                   Ecological Value of Project Area / habitats within the Assessment Area

 

6.5.1              Habitats identified within the Assessment Area were evaluated according to the guidelines set out in Annex 8 of the EIAO-TM. Overall ecological values for each habitat type were ranked. Rankings starting with the highest ecological value range from:

 

                      High

                      Moderate-high

                      Moderate

                      Moderate-low

                      Low

Very Low

 

Evaluation of the Project Areas

 

6.5.2              Evaluation of the Project Areas in different Sections was presented in the following tables:

 

Section 1

 

6.5.3              The whole proposed Project Area will be within the existing boundary patrol road running from Pak Hok Chau check point to Lok Ma Chau control point near the Lok Ma Chau railway station. Common roadside plants and streetscape plantings can be found along this section.

 

6.5.4              The Project Area will only cover two artificial habitats of developed area and open field. However as it is within or in close proximity to several sites of conservation importance (WCA, Mai Po Inner Deep Bay Ramsar Site, Mai Po Nature Reserve and Mai Po Marshes SSSI), the ecological linkage between the Project Area and these sites has also been taken into account during the preparation of the evaluation.

 

6.5.5              Due to the low naturalness (man-made) of habitats to be affected and the narrow profile (road) of the Project Area, ecological linkage and potential value to species as breeding or feeding grounds are not expected. All birds found in the area were flying across or temporary roosting at road side vegetation.

 

6.5.6              The overall ecological value is considered to be very low.


Table 625   Ecological Evaluation of Project Area in Section 1

Criteria

 

Naturalness

Man-made habitat (existing road and some open fields)

Size

approx. 4.1km in length

Diversity

Low in both flora and fauna species

Rarity

Common habitat. No species of conservation concern were identified depending on these habitats

Re-creatability

Readily re-creatable

Fragmentation

No fragmentation

Ecological linkage

Although the Project Area is within the WCA and in close proximity to Mai Po Inner Deep Bay Ramsar Site, Mai Po Nature Reserve and Mai Po Marshes SSSI, no significant ecological linkage was identified

Potential value

Low

Nursery/ breeding ground

Potential for nursery / breeding grounds is low

Age

No available information

Abundance/ Richness of wildlife

Low in wildlife abundance

Ecological value

Very Low

 

Section 2

 

Red Alignment

 

6.5.7              The Project Area at the red alignment in Section 2 will be within the existing maintenance services road of Drainage Services Department.

 

6.5.8              This alignment runs along the northern boundary of the Hoo Hok Wai and Ta Sha Lok wetlands which provide important habitats for various waterbirds, amphibians and dragonflies species. The concrete paved Project Area and its narrow landform greatly limit the ecological linkage with these offsite habitats. All birds found in the area were flying across or temporary roosting at road side vegetation.

 

6.5.9              No species of conservation concern were identified depending on this man-made habitat. The overall ecological value is considered very low.

 

Table 626   Ecological Evaluation of Project Area at Red Alignment in Section 2

Criteria

 

Naturalness

Man-made habitat (existing DSD maintenance access)

Size

approx. 5.6km in length

Diversity

Low in both flora and fauna species

Rarity

Common habitat; no species of conservation concern were identified depending on this Project Area

Re-creatability

Readily re-creatable

Fragmentation

No fragmentation

Ecological linkage

No significant ecological linkage was identified despite its close proximity to the Hoo Hok Wai and Ta Sha Lok wetlands

Potential value

Low

Nursery/ breeding ground

Potential for nursery / breeding grounds is low

Age

No available information

Abundance/ Richness of wildlife

Low in wildlife abundance

Ecological value

Very Low

 

Blue and Green Alignment

 

6.5.10           The Project Area at the blue and green alignments in Section 2 will be within the existing boundary patrol road.

 

6.5.11           These two alignments run along the southern boundary of the Lok Ma Chau, Hoo Hok Wai and Ta Sha Lok wetlands. Similar to the red alignment in Section 2, the concrete paved Project Area and its narrow landform greatly limit the ecological linkage with these offsite habitats. All birds found in the area were flying across or temporary roosting at road side vegetation.

 

6.5.12           No species of conservation concern were identified depending on this man-made habitat. The overall ecological value is considered very low.

Table 627   Ecological Evaluation of Project Area at Blue and Green Alignments in Section 2

Criteria

 

Naturalness

Man-made habitat (existing Boundary Patrol Road)

Size

approx. 6km in length

Diversity

Low in both flora and fauna species

Rarity

Common habitat; one rare plant Berchemia lineata was recorded;

One Burmese Python was found on roadside but not depends on this habitat as roosting ground.

Re-creatability

Readily re-creatable

Fragmentation

No fragmentation

Ecological linkage

No significant ecological linkage was identified despite its close proximity to the Lok Ma Chau, Hoo Hok Wai and Ta Sha Lok wetlands

Potential value

Low

Nursery/ breeding ground

Potential for nursery / breeding grounds is low

Age

No available information

Abundance/ Richness of wildlife

Low in wildlife abundance

Ecological value

Very Low

 

 

 

Section 3

 

Red Alignment

 

6.5.13           The Project Area at the red alignment in Section 3 will be within some riparian grasslands south of the unchannelised Shenzhen River which is heavily polluted. The northern side of the river is the highly urbanised Shenzhen Town.

 

6.5.14           No species of conservation concern were identified depending on this habitat. The overall ecological value is considered as low.

 

Table 628   Ecological Evaluation of Project Area at Red Alignment in Section 3

Criteria

 

Naturalness

Habitats derived from abandoned agricultural lands and dominated by exotic flora species;

Adjacent to the heavily polluted Shenzhen River

Size

Approx. 4km in length

Diversity

Low

Rarity

Common habitat

Re-creatability

Re-creatable

Fragmentation

No fragmentation

Ecological linkage

No significant ecological linkage with recognised site or species of conservation concern

Potential value

Low

Nursery/ breeding ground

Potential breeding grounds of amphibians

Age

No available information

Abundance/ Richness of wildlife

Low

Ecological value

Low

 

Blue and Green Alignments

 

6.5.15           The Project Area along the blue and green alignments in Section 3 will be within the existing boundary patrol road from Ng Tung River to Lin Ma Hang. Offsite habitats of conservation interest include Yuen Leng Chai fishponds, Nam Hang mitigation area and Lin Ma Hang Stream.

 

6.5.16           However, like those alignments in Section 1 and 2, ecological linkage is not expected for its artificial habitat nature and narrow profile. The overall ecological value is considered very low.


Table 629   Ecological Evaluation of Project Area at Blue and Green Alignments in Section 3

Criteria

 

Naturalness

Man-made habitat (existing Boundary Patrol Road)

Size

approx. 7.5km in length

Diversity

Low in both flora and fauna species

Rarity

Common habitat; One young individual of Aquilaria sinensis was recorded which is listed under the Protection of Endangered Species of Animals and Plants Ordinance (Cap 586);

No uncommon fauna species was recorded.

Re-creatability

Readily re-creatable

Fragmentation

No fragmentation

Ecological linkage

No significant ecological linkage was identified

Potential value

Low

Nursery/ breeding ground

Potential for nursery / breeding grounds is low

Age

No available information

Abundance/ Richness of wildlife

Low in wildlife abundance

Ecological value

Very Low

 

Section 4

 

6.5.17           The whole proposed Project Area will be within the urban areas at Sha Tau Kok.

Table 630   Ecological Evaluation of Project Area in Section 4

Criteria

 

Naturalness

Man-made habitat

Size

approx. 0.5km in length

Diversity

Low in both flora and fauna species

Rarity

Common habitat

Re-creatability

Readily re-creatable

Fragmentation

No fragmentation

Ecological linkage

No ecological linkage was identified

Potential value

Low

Nursery/ breeding ground

Potential for nursery / breeding grounds is low

Age

No available information

Abundance/ Richness of wildlife

Low in wildlife abundance

Ecological value

Very Low

 

Evaluation of Habitats (Offsite) within the Assessment Area

 

6.5.18           Evaluation of offsite (i.e. areas outside the proposed Project Area) habitats within the Assessment Area is presented in Tables F-5-F19 in Appendix F.

 

6.6                   Potential Ecological Impacts 

 

Introduction

 

6.6.1              The following sections identified and evaluated the potential ecological impacts as a result of the project in detail. It identified potential impacts on habitats and their associated species, caused by the proposed boundary fence construction works during the construction and operational phases. As far as possible, any direct, indirect, on-site and off-site ecological impacts have been identified and assessed.

 

6.6.2              The potential impacts described in the sections below were assessed and evaluated in accordance with the requirements stipulated in the EIAO-TM. Impact levels were ranked using the 6 point range “severe”, “severe-moderate”, “moderate”, “moderate-minor”, “minor” and “negligible”.

 

Potential Construction Phase Impacts

 

6.6.3              During the construction phase the major potential impacts on ecology would include the direct impacts of habitat loss, ecological barrier, impact on onsite species of conservation concern and disturbance to off-site habitats and species.

 

Potential Operational Phase Impacts

 

6.6.4              During operational phase, the major potential impacts on ecology would include the direct impacts of habitat loss and ecological barrier.

 

Mitigation Measures

 

6.6.5              Practical and effective mitigation measures would be proposed if adverse impacts were identified. The order of priority of the mitigation measures will be avoidance, minimizing and compensation.

 

6.6.6              As an avoidance measure, alignments are proposed along the existing boundary patrol roads and maintenance access as far as possible since as shown in Figure 6.1-6.9, other alternatives could only be established by creating new pathways in adjacent habitats which would inevitably cause adverse ecological impacts. Therefore the currently proposed alignment is considered to be a preferred option in terms of ecological avoidance measure.

 

6.6.7              Other mitigation measures recommended for particular impact are detailed below.

 

Habitat Loss

 

6.6.8              According to the project footprint (i.e. proposed Project Area for the boundary fence works), the construction of the proposed primary / secondary boundary fence and patrol road would cause the permanent loss of part of the existing habitats within the Project Area.

 

Section 1

 

6.6.9              The Project Area of this section includes only the habitat of developed area and open field of 4.6 ha in total (i.e. the existing boundary patrol road, exposed grounds along the road and the roadside vegetation).

 

6.6.10           Proposed works will be the construction of a secondary boundary fence on one side of the boundary patrol road. No fishponds are proposed to be filled. As the potential habitat loss will only involve habitat of low ecological value, the impact level is considered to be negligible. The evaluation of the impact is summarised in Table 6-31.

 

Section 2 (Red Alignment)

 

6.6.11           The Project Area of this Section includes only the habitat of developed area (i.e. the existing maintenance service access of DSD). Proposed works will be the construction of primary and secondary boundary fence along the two sides of the road. As the potential habitat loss will only involve habitat of low ecological value, the impact level is considered to be negligible. The evaluation of the impact is summarised in Table 6-31.

 

Section 2 (Blue and Green Alignment)

 

6.6.12           The Project Area of this Section includes only the habitat of developed area (i.e. the existing boundary patrol road and the roadside vegetation). Proposed works will be the construction of secondary boundary fence (along blue aligment) and removal of the existing primary boundary fence (along green alignment) along the either side of the road. As the potential habitat loss will only involve habitat of low ecological value, the impact level is considered to be negligible. The evaluation of the impact is summarised in Table 6-31.

 

Table 631   Potential Ecological Impacts of Habitat Loss at Section 1 and 2

Criteria

Section 1

Section 2 (Red Alignment)

Section 2 (Blue & Green Alignment)

Receivers

Habitats of low ecological value

Habitats of low ecological value

Habitats of low ecological value

Size

Small in area (4.6ha) but medium in length (4.1km)

Small in area (5ha) but medium in length (5.6km)

Small in area (2.4ha) but medium in length (6km)

Duration

During construction period

During construction period

During construction period

Reversibility

Reversible (as the lost man-made habitat will be reinstated after the completion of the Project)

Reversible (as the lost man-made habitat will be reinstated after the completion of the Project)

Reversible (as the lost man-made habitat will be reinstated after the completion of the Project)

Magnitude

Low; as only fence construction works is involved

Low; as only fence construction works is involved

Low; as only fence construction works (blue alignment)  and fence removal works is involved

Impact Severity before Mitigation

Negligible

Negligible

Negligible

Recommended Mitigation

None

None

None

 

 

 

Section 3 (Red Alignment)

 

6.6.13           The Project Area of this Section includes the habitat of low-lying grassland. Proposed works will be the construction of a new section of boundary patrol road, primary and secondary boundary fences. The potential habitat loss would involve the habitat of moderate-low ecological value, the impact level is considered to be moderate-minor. The evaluation of the impact is summarised in Table 6-32.

 

Section 3 (Blue and Green Alignment)

 

6.6.14           The Project Area of this Section includes only the habitat of developed area (i.e. the existing boundary patrol road and the roadside vegetation). Proposed works will be the construction of secondary boundary fence (along blue aligment) and removal of the existing primary boundary fence (along green alignment) along the either side of the road. As the potential habitat loss will only involve habitat of low ecological value, the impact level is considered to be negligible. The evaluation of the impact is summarised in Table 6-32.

 

Section 4

 

6.6.15           The Project Area of this Section includes only the habitat of developed area (i.e. the existing Sha Tau Kok Town and roadside vegetation). Proposed works will be the construction of a secondary boundary fence along the proposed alignment. As the potential habitat loss will only involve habitat of low ecological value, the impact level is considered to be negligible. The evaluation of the impact is summarised in Table 6-32.

 

6.6.16           Direct impact to bird species and butterflies is expected to be of low significance due to the high disturbance and low ecological value of the artificial habitat. Major affected species are those common grassland species utilizing the road side grassess such as Yellow-bellied Prinia Prinia flaviventris and Scaly-breasted Munia Lonchura punctulata, Common Grass Yellow Eurema hecabe, Common Mormon Papilio polytes and Indian Cabbage White Pieris canidia.

 

Table 632   Potential Ecological Impacts of Habitat Loss at Section 3 and 4

Criteria

Section 3 (Red)

Section 3 (Blue & Green)

Section 4

Receivers

Habitat of low ecological value

Habitats of low ecological value

Habitats of low ecological value

Size

Small in area (5.9ha) and medium in length (4km)

Small in area (6.7ha) but long in length (7.5km)

Small in area (0.3ha) and short in length (0.5km)

Duration

During construction and operational periods

During construction period

During construction period

Reversibility

Not reversible (as the riparian grassland will be permanently changed to man-made habitat)

Reversible (as the lost man-made habitat will be reinstated after the completion of the Project)

Reversible (as the lost man-made habitat will be reinstated after the completion of the Project)

Magnitude

Moderate

Low

Low

Impact Severity before Mitigation

Moderate-minor

Negligible

Negligible

Recommended Mitigation

None

None

None

 

Ecological Barrier

 

6.6.17           The effect of ecological barrier would arise when a continuous natural ecosystem is cut across by artificial barrier. The impacts may include fragmentation of population and interference of daily foraging activities of fauna species. As the new secondary fence will be in same design to the existing primary fence, the current situation at Mai Po and other frontier area could be used as a reference for predicting potential impact of new boundary.  

 

6.6.18           The existing border fence stretches from west (Tsim Bei Tsui) to east (Sha Tau Kok) for approximately 32km. Although no research has been conducted on the ecological barrier effect caused from the boundary fence, no significant impact caused by the boundary fence on local ecosystem was observed. This is supported by an evident that a high diversity of various wildlife groups was found in both gei wai and intertidal mangrove area which are separated by the existing boundary fence within the Mai Po Nature Reserve but without any significant ecological barrier effect. Moreover, the daily movement of thousands of wintering waterbirds from gei wai to Inner Deep Bay intertidal mudflat and vice versa were not obstructed by the existing boundary fence.

 

6.6.19           For the proposed secondary boundary fence which will run along the existing border fence in Section 1 and 2, the ecological barrier effect is not expected to exceed the existing boundary fence as similar design was adopted. During this Study, Small Asian Mongoose and domestic dog were observed creeping across the existing boundary fence between fishponds and rivers, which demonstrated that the boundary fence could not stop the free movement of the medium-sized mammals between different habitats.

 

Section 1 & Blue Alignment of Section 2

 

6.6.20           The proposed secondary boundary fence will separate the fishpond habitat on the southern side from the channelized river on the northern side. Due to the channelized nature of Shenzhen River, it is not favourable to most of the wildlife species inhabiting adjacent fishpond habitat, except wetland-dependent bird species. The movement of non-flying wildlife between the fishponds and the channalized river is expected to be in very low frequency. For the wetland-dependent species which could be affected, they showed good adaptability to the existing boundary fence and no significant obstruction to their flight line was observed during field observation. Thereby, the new secondary boundary fence is not expected to cause significant additional barrier effect to the highly mobile birds.

 

Section 2

 

Red Alignment

 

6.6.21           A new section of the boundary patrol road with a primary fence and a secondary fence will be constructed at the north of Lok Ma Chau Loop and Hoo Hok Wai. At the Lok Ma Chau Loop sub-section, the proposed boundary fence will separate the habitat of low-lying grassland at south from the channelized river at north. As these two habitats are utilized by bird of different foraging groups, the ecological linkage among these two habitats is considered to be weak. The construction of the boundary fence will cause interference to the short distance movement of low-flying generalist bird such as Common Tailorbird, and butterfly species such as Common Grass Yellow and Indian Cabbage White. Furthermore, the interference to the bird’s flight path of crossing Shenzhen River is thought to be low as most of the habitats at the opposite river side are developed area which is not an attractive habitat for the wetland-dependent birds. In view of the low frequency of inter-habitat movement of the common species, the ecological barrier effect caused by the new boundary fence is expected to be insignificant.

 

6.6.22           For the Hoo Hok Wai sub-section, the proposed boundary fence will separate the fishpond habitat at the south from the channelized river at the north. The potential affected species would be the waterbirds using both types of wetland habitat such as ducks, ardeids and waders. The short-distance movement of waterbirds from fishponds to channelized river or vice versa will be interfered by the boundary fence. However, the existence of obstruction will be habituated by the waterbirds and the effect to their behaviour is in considered as minor. Habituation to obstruct was shown in a study of bird collision with man-made structures in Hong Kong (Ove, 2002). All birds would react to obstruct by changing altitude or changing flight direction. In finer scale, changing flight altitude to avoid boundary fence was commonly observed in Mai Po Nature Reserve. As the new boundary fence would be in same design as the existing boundary fence, similar habituating behaviour of bird is expected to happen at this section.

 

Green Alignment

 

6.6.23           After the removal of the existing section of primary boundary fence between Ha Wan Tsuen and Tak Yuet Lau, the physical barrier between fishpond area at north and hillside shrubland at the south will be eliminated. This will facilitate the flight path of flying animals and insects at understorey habitat and the movement of small mammals, butterflies and herpetofauna between the habitats of the removed fence. Although the effect of ecological enhancement is in low significant as the existing boundary fences do not impose significant ecological barrier effect to these fauna group, the removal of physical barrier is still beneficial to these fauna as they do not need to alter the flight path or finding a corridor for the movement between habitats.

 

Section 3

 

Blue Alignment

 

6.6.24           Most of the existing boundary fences separate the abandoned agricultural land in south from the Shenzhen River and developed area at north. The abundance of bird species at this section of Shenzhen River is relatively low as a result of high disturbance from the adjacent developed area in Shenzhen. The ecological barrier effect of the existing primary fence to the birds is considered as low significant due to the low density and diversity of birds. No additional barrier effect is expected to be imposed in addition to the existing one.

 

Red Alignment

 

6.6.25           For the construction of two new sections of the boundary patrol road with a primary boundary fence and a secondary boundary fence along the Shenzhen River to the north of Pak Fu Shan and northwest of Lin Ma Hang Village, new boundary fence will separate the abandoned agricultural land at south from the unchannelized section of Shenzhen River at north. The proposed boundary patrol road and boundary fences would interfere with the short distance movement of birds from river area to abandoned agricultural land or vice versa. However, in considering the low density of birds at the existing unchannelized Shenzhen River section as a result of high disturbance from the adjacent developed area in Shenzhen, the barrier effect of the new boundary fence is considered to be of low significant.

 

6.6.26           Bat species of conservation concern recorded in this section will not be affected by the construction of new boundary fence along the Shenzhen River due to their high mobility of flying behaviour that allows the free movement from both sides of the fence.

 

Green Alignment

 

6.6.27           The removal of two sections of boundary fences at northwest of Pak Fu Shan and Lin Ma Hang would eliminate the physical barrier. This will facilitate the flight path of flying animals and insects at understorey habitat. However the effect of ecological enhancement is in low significant as the existing boundary fences do not impose significant ecological barrier effect.

 

Section 4

 

6.6.28           The boundary fence at this section is located at a highly disturbed urban area beside a lorry parking area. All bird species recorded in this area are dominated by common generalist of low ecological value. The construction of secondary boundary fence would interfere with the movement of those birds from urban area to the shrubs in the village area. In consideration of low density of bird in this type of habitat and the low ecological value of those species to be affected, the effect of ecological barrier is considered to be insignificant.

Table 633   Potential Ecological Impacts of Ecological Barrier on Section 1, Blue Alignments of Section 2 and Section 4

Criteria

Section 1, blue alignments of Section 2 and Section 4

Receivers

Birds

Size

Section 1: 4.1km;

Blue alignment of Section 2: 0.4km;

Section 4: 0.5km.

Duration

Operational phase

Reversibility

Irreversible

Magnitude

Low

Impact Severity before Mitigation

Minor

Recommended Mitigation Measures

None

 

 

 

 

Table 634   Potential Ecological Impacts of Ecological Barrier on Red and Green Alignments of Section 2

Criteria

Red Alignment in Section 2

Green Alignment in Section 2

Receivers

Waterbirds utilizing the offsite habitats at Lok Ma Chau, Hoo Hok Wai and Ta Sha Lok and the channelized Shenzhen River

Low-flying generalist bird, open country area bird and butterfly species utilizing the grassland and riparian vegetation of fishponds, Burmese Python

Size

The alignment is 5.6km in length

The alignment is 4km in length

Duration

In the operational phase

In the operational phase

Reversibility

Irreversible

Irreversible

Magnitude

Low

Medium-low (positive)

Impact Severity before Mitigation

Minor

Minor (positive)

Recommended Mitigation Measures

None

None

 

Table 635   Potential Ecological Impacts of Ecological Barrier on Blue Alignment of Section 3

Criteria

Blue Alignment in Section 3

Receivers

Low abundance of waterbirds

Size

The alignment is 7.5km in length

Duration

In the operational phase

Reversibility

Irreversible

Magnitude

Low

Impact Severity before Mitigation

Minor

Recommended Mitigation Measures

None

 

Table 636   Potential Ecological Impacts of Ecological Barrier on Red and Green Alignments of Section 3

Criteria

Red Alignment in Section 3

Green Alignments in Section 3

Receivers

Low abundance of waterbirds, bats of conservation concern and butterflies

Shrubland birds, bats of conservation concern, Brown Tree Frog and Danaid Eggfly

Size

The alignment is 4km in length

The alignment is 1.6km in length

Duration

In the operational phase

In the operational phase

Reversibility

Irreversible

Irreversible

Magnitude

Low

Medium-low (positive)

Impact Severity before Mitigation

Minor

Minor (positive)

Recommended Mitigation Measures

None

None

 

 

 

 

Direct Loss of Onsite Species of Conservation Importance

 

Flora

 

6.6.29           One rare climber shrub Berchemia lineata was recorded along the boundary patrol road in Section 2 northeast of Liu Pok village (Figure 6.5) and one young individual of Aquilaria sinensis was recorded on the roadside near a village house along a section of the patrol road northwest of Wang Lek (Figure 6.8).

 

6.6.30           Evaluation of the two species are summarised below:

 

Table 637   Ecological Evaluation of Floral Species within Proposed Project Area

Species

Location

Protection Status

Distribution

Rarity

Aquilaria sinensis

Roadside near a village house

Scheduled under Protection of Endangered Species of Animals and Plants Ordinance  (Cap 586);

Listed as Near Threatened in China. (1)

Common in Hong Kong (3)

Common (3)

Berchemia lineata

Roadside near Liu Pok village

Not protected in Hong Kong

Shatin, Sheung Shui, Sai Kung, Ma Wan and Ping Chau (Mirs Bay) (2)

Rare (3)

Reference source:     (1) Rare and Precious Plants of Hong Kong;

                                (2) Hong Kong Plant Check List 2001;

                                (3) Corlett’s study “Hong Kong Vascular Plants: Distribution and Status”.

 

6.6.31           Works in these two sections will only involve the removal of the existing boundary fence and no works will be carried out on the opposite side of the road. As both individuals situate on the non-works area, adverse impact is considered to be avoidable if proper protection measure during the construction period can be provided. Erection of protective fencing together with a sign indicating the protection requirement for the plant is an effective measure to avoid plant damage during the construction period.

 

6.6.32           The proposed protective fencing can be made of ordinary metal poles (for supporting) and plastic orange fence as shown in Plate F19, which allows penetration of sunlight and rainfall. Its establishment could also raise the awareness of personnel on the presence and protection requirement of the plants.

 

6.6.33           In addition, since only one individual (each species) will be involved, adverse impact on the community of the species is not anticipated.


Table 638   Potential Ecological Impacts on Floral Species of Conservation Concern

Criteria

 

Receivers

One individual of each species Berchemia lineata and Aquilaria sinensis were recorded.

Berchemia lineata is not protected in Hong Kong but is a rare plant.

Aquilaria sinensis is listed as Near Threatened in Mainland China. In Hong Kong, it is a common species but has been scheduled under Protection of Endangered Species of Animals and Plants Ordinance (Cap 586).

Abundance

One individual of each species

Duration

Impacted during construction period;

No further impact during operational period.

Reversibility

Not reversible

Magnitude

Minor

Impact Severity before Mitigation

Minor

Recommended Mitigation Measure

Avoidance: in-situ preservation of the plants

Minimizing: Erection of protective fencing to protect the plant during construction period

Compensation: N/A

Impact Severity after Mitigation

Negligible

 

Fauna

 

6.6.34           One Burmese Python was recorded in vicinity to the proposed works area along the green alignment (Lok Ma Chau Road) in Section 2 (Figure 6.4). The fence removal works may cause direct impact on this species of conservation concern if it is present in vicinity to the proposed works area during construction phase. Potential impacts may include direct injury and disturbance to this species during construction. However taking into account this snake will avoid construction activities and the small scale of works to be undertaken, no unacceptable impact is anticipated with good site practice and avoid direct disturbance to this protected species.

 

6.6.35           As the works will only involve the removal of the boundary fence, no operational impact is expected.

Table 639   Potential Ecological Impacts on Fauna Species of Conservation Concern

Criteria

 

Receivers

One individual of Burmese Python was recorded in riparian vegetation along the existing boundary patrol road in Section 2.

This species is common in Hong Kong but is listed as “Critically Endangered” in the China Red Data Book and protected under Cap. 170 and Cap. 586

Abundance

One individual was recorded

Duration

Impacted during construction period;

No further impact during operational phase.

Reversibility

Irreversible for direct injury

Magnitude

Moderate for direct injury but Minor for direct disturbance

Impact Severity before Mitigation

Negligible as the snakes will avoid the construction area

Recommended Mitigation Measure

Avoidance: good site practice to avoid direct injury of wildlife.

 

Impact on Offsite Habitats

 

6.6.36           As the proposed fencing works run along the long boundary, a variety of offsite habitats were included. Ecologically sensitive areas would be those sites of conservation importance including wetlands in WCA, WBA, wetlands in Hoo Hok Wai and Ta Sha Lok, Mai Po and Inner Deep Bay Ramsar Site, Mai Po Nature Reserve, Mai Po Marshes SSSI, Inner Deep Bay SSSI, Ecological Mitigation Area at Yuen Leng Chai / Nam Hang, Lok Ma Chau Mitigation Area, Lin Ma Hang Lead Mines SSSI and Lin Ma Hang Stream SSSI.

 

6.6.37           As an avoidance measure, all the alignments along these sites of conservation importance are proposed on the existing boundary patrol roads rather than creating new paths in these sensitive areas. All the works will be confined on the roads to avoid direct impact on these offsite habitats.

 

6.6.38           Impacts would include: construction impact on air and water quality of these habitats, and disturbance to species of conservation concern utilizing these habitats.

 

Impacts on Air and Water Quality of Offsite Habitats

 

6.6.39           Site of conservation importance in close proximity to the works area including Lin Ma Hang Stream SSSI is sensitive to water pollution through silt runoff or non-point source discharge to the water body and human disturbance to wildlifes of conservation concern utilizing the habitats (such as fish species of conservation concern: Rasbora steineri, Rasborinus lineatus, Pseudorasbora parva, Channa asiatica and Mastacembelus armatus). The increase in suspended sediment in the water column will affect the gill breathing fish from increasing the metabolic rate to expel the silt in excess. Further increase in sediment loading will eventually make the fish suffocate to die. The impact significant is anticipated to be low with the implementation of water quality and dust mitigation measures.

 

6.6.40           As the proposed works only involve construction and removal of the existing boundary fences, potential impacts on these offsite habitats would be the generation of site runoff during construction period and dust deposition on vegetation of adjacent habitats.

 

6.6.41           Due to the simple nature of the works of erection and removal of metal fencing, these impacts can be mitigated effectively by the strict implementation of good site practices for air and water quality detailed in Section 2.5 and 4.7 (including avoid stockpiles adjacent to the streams and wetlands, covering of stockpiles by impervious sheeting, the control of vehicle speed to reduce spreading of dust and no discharge of silty water into the rivers, streams or drainage channels) and clear definition of works limit.

 

Table 640   Potential Ecological Impacts on Offsite Habitats

Criteria

Site Runoff and Dust Deposition

Receivers

Various types of habitats include woodland, shrubland, plantation, marsh, agricultural land, grassland, pond, hillside grassland, stream and drainage channel within sites of conservation importance.  The associated species of conservation concern especially those utilizing the adjacent streams and wetlands (such as  Rasbora steineri, Rasborinus lineatus, Pseudorasbora parva, Channa asiatica and Mastacembelus armatus).

Size/Abundance

All these habitats along the alignment of 21.7km;

The species of conservation concern recorded are in low abundance.

Duration

During the construction period; no impact during operational period

Reversibility

Reversible

Magnitude

Minor as only fence construction and removal works are involved

Impact Severity before Mitigation

Minor

Recommended Mitigation Measure

Avoidance and Minimizing:

Good site practices for controlling the dust and water quality (avoid stockpiles adjacent to wetlands, covering the stockpiles with impervious sheeting, control of vehicle speed, no discharge of silty water to the rivers, streams and drainage channels);

Clear definition of works limit to avoid impact on adjacent habitats.

Compensation: N/A

Impact Severity after Mitigation

Negligible

 

Disturbance to Species of Conservation Concern in the Assessment Area

 

Impacts on Mammal Species of Conservation Concern

 

6.6.42           Bat species of conservation concern especially those foraging around the fishponds and marshes in Section 1 and 2 and those around Pak Fu Shan and Lin Ma Hang in Section 3 may be disturbed by the construction works. However, the active period of those bat species are mainly after sunset when most of the construction works stop, and the long distance of the roosting site from the construction activities, it is anticipated that disturbance impacts to these bat species will be negligible.

Table 641   Potential Ecological Impacts on Offsite Disturbance to Mammals of Conservation Concern

Criteria

Disturbance Impact to Mammals of Conservation Concern

Receivers

Bat species of conservation concern foraging around the fishponds, marshes and wetland habitats adjacent to the proposed works area

Size/Abundance

Moderate abundance of bat species

Duration

During the construction period; no impact during operational period

Reversibility

Reversible

Magnitude

Negligible as the bat species are nocturnal species that active after sunset when the construction works stop at night

Impact Severity before Mitigation

Negligible

Recommended Mitigation Measure

None

 

Impacts on Wetland-Dependent Birds, Raptors and Terrestrial Birds

6.6.43           The potential impact on the conservation concerned waterbirds would be the noise and visual disturbance arise from construction site and the associated worker and vehicles. The construction work involves mainly three phases, which are excavation, footing construction and fence installation. If without mitigation measures, the major noise disturbance would be the use of breaker during excavation phase. Continual construction noise could disturb birds from their roosting or foraging habitats.

6.6.44           A large variety of habitats in the Assessment Area are used by a high diversity of birds, of which 76 species are listed by Fellowes et al. (2002) as species of conservation concern. The abundance of the birds would increase in winter when a large amount of wintering population arrives. In general, no large aggregation of wintering birds was found roosting at the project area or the habitat closely nearby except at the western end of Section 1, which lies in close proximity to the Mai Po Nature Reserve. The gei wais inside the Reserve is an important habitat for migratory waterbirds, notably the globally endangered Black-faced Spoonbill, and thereby large aggregation of them is often found especially during winter. Besides, the fishponds within the WCA are also important habitat to the migratory waterbirds.  Major potential impact imposes on the waterbirds roosting at the gei wais in the Mai Po Nature Reserve and the fishponds in the WCA would be the noise disturbance arises from the construction work especially during excavation phase.

6.6.45           To mitigate the potential impact on the surrounding environment, a quiet breaker (the quietest available on the construction market) will be employed for excavation works. The noise level would be further reduced by installing a movable noise barrier on the breaker. The disturbance level would be within acceptable level under the implementation of good working practices including avoidance of feeding the wildlife by the workers, switching off the powered mechanical devices whenever not in use and site confinement to minimize the construction noise, uncontrolled surface runoff and discharge as far as possible. Details of mitigation measures for noise control are presented in Section 3 - Noise Impact and Section 4 –Water Quality Impact respectively.

6.6.46           Apart from these measures, all construction works involving the use of Power Mechanical Equipments (PMEs) within Wetland Conservation Area (Section 1 and western 150m of Section 2 of the project area) should be avoided during the bird migratory season (from 15th November to 15th March) in order to further avoid the potential noise disturbance to the wintering waterbirds roosting in the wetland habitats in the Mai Po Nature Reserve and the WCA. With the implementation of all the recommended measures, potential impacts on these ecological sensitive receivers will not be significant.

 

6.6.47           All the species of conservation concern recorded are categorized into wetland-dependent birds, raptors or terrestrial birds according to their use of habitat for a systematic presentation of impact assessment which are listed in Table 6-42 to Table 6-44.

 

Table 642   Potential disturbance Impacts to wetland-dependent birds of conservation concern in Assessment Area.

Criteria

Disturbance Impact to Water-dependent birds of Conservation Concern

Receivers

60 wetland-dependent bird species of conservation concern recorded on the fishponds, gei wai, mangrove, wet agricultural land, river and stream, including: Little Grebe ,Great Crested Grebe, Great Cormorant, Lesser White-fronted Goose, Grey Heron, Purple Heron, Great Egret, Intermediate Egret, Little Egret, Cattle Egret, Chinese Pond Heron, Striated Heron, Black-crowned Night Heron, Yellow Bittern, Cinnamon Bittern, Oriental Stork, Eurasian Spoonbill, Black-faced Spoonbill, Eurasian Wigeon, Falcated Duck, Common Teal, Mallard, Spot-billed Duck, Northern Pintail, Northern Shoveler, Tufted Duck, Eurasian Coot, Watercock, Pheasant-tailed Jacana, Greater Painted-snipe, Black-winged Stilt, Grey-headed Lapwing, Oriental Pratincole, Pied Avocet, Pacific Golden Plover, Little Ringed Plover, Kentish Plover, Greater Sand Plover, Common Redshank, Spotted Redshank,  Common Greenshank, Marsh Sandpiper, Wood Sandpiper, Swinhoe's Snipe, Little Stint, Temminck's Stint, Long-toed Stint, Red-necked Stint, Curlew Sandpiper, Heuglin's Gull, Black-headed Gull, Pied Kingfisher, White-throated Kingfisher, Black-capped Kingfisher, Pallas’s Grasshopper Warbler, Red-throated Pipit, Zitting Cisticola, White-cheeked Starling, White-shouldered Starling, Red-billed Starling and Collared Crow.

Size/Abundance

High abundance of some species, notably Great Cormorant, Little Egret and Red-billed Starling

Duration

Disturbance arises at construction phase of the project.

Reversibility

Construction phase disturbance would be temporary and will fade out when construction end.

Impact Severity before Mitigation

Moderate-minor. The major source of the impact is the noise disturbance arises from excavation phase of the construction work. Habitat with large aggregation of wintering waterbirds, mainly the Mai Po Nature Reserve and the fishponds in the WCA, would be the most sensitive area to the disturbance especially during winter when greater amount of wetland-dependent birds are present.

Degree of disturbance to waterbirds at other area is relatively low because of low likelihood of large aggregation of waterbirds.  

Recommended Mitigation Measure

Avoidance and Minimizing:

Environmental sensitive areas are avoided as far as possible in consideration of alternative alignment as described in Section 1.6;

Good working practices at site (detailed in Section 3.8.14 of the noise assessment) include switching off unused equipment, keep minimum number of powered mechanical equipment in operation at the same period, avoidance of feeding the wildlife to cause disturbance and site confinement to minimize construction noise, uncontrolled surface runoff and discharge of silts. Installation of a movable noise barrier to the breaker to reduce the noise level during excavation phase;

Avoidance of construction works involving the use of PMEs within the WCA during bird migratory season (15th November – 15th March).

Compensation: N/A

Impact Severity after Mitigation

Construction phase disturbance to wetland-dependent birds is considered to be minor due to the small scale of construction works, reduced noise level after mitigation and avoidance of construction works in WCA during the bird migratory season.

 

Table 643  Potential Disturbance Impacts to raptors of conservation concern in Assessment Area.

Criteria

Disturbance Impact to Raptors of Conservation Importance

Receivers

11 raptor species of conservation importance recorded in Assessment Area, including: Osprey, Black Kite, Black-winged Kite, Crested Serpent Eagle, Greater Spotted Eagle, Imperial Eagle, Bonelli's Eagle, Eastern Marsh Harrier, Pied Harrier, White-bellied Sea Eagle and Peregrine Falcon.

These species were observed using the open area at fishponds, agricultural lands and shurbland areas.

Size/Abundance

Low abundance for all raptor species

Duration

Disturbance would arise at construction phase of the project.

Reversibility

Construction phase disturbance would be temporary and will fade out when construction end.

Impact Severity before Mitigation

Minor. The impact to the conservation concerned species is mainly caused by noise and human disturbance which will become larger in winter when migratory species are present

Recommended Mitigation Measure

Avoidance and Minimizing:

Environmental sensitive areas are avoided as far as possible in consideration of alternative alignment as described in Section 1.6.

Good working practices at site to minimize construction noise, uncontrolled surface runoff and discharge of silts. Installation of a movable noise barrier to the breaker to reduce the noise level during excavation phase.

Compensation: N/A

Impact Severity after Mitigation

Construction phase disturbance to raptors is considered to be minor due to the small scale of construction works and low abundance of conservation concerned raptors.

 

Table 644   Potential Disturbance Impacts to terrestrial birds of conservation concern in Assessment Area.

Criteria

Disturbance Impact to Terrestrial birds of Conservation Importance

Receivers

Pacific Swift, Grey Bushchat, Orange-headed Thrush and Ashy Drongo recorded in patchy shrublands

Size/Abundance

Low abundance

Duration

Disturbance confine in construction phase of the project. Disturbance would be reduced after construction work completes.

Reversibility

Construction phase disturbance would be temporary and will fade out when construction end.

Impact Severity before Mitigation

Minor. The impact to the conservation concerned species is mainly caused from noise and human disturbance.

Recommended Mitigation Measure

Avoidance and Minimizing:

Environmental sensitive areas are avoided as far as possible in consideration of alternative alignment as described in Section 1.6.

Good working practices at site to minimize construction noise, uncontrolled surface runoff and discharge of silts. Installation of a movable noise barrier to the breaker to reduce the noise level during excavation phase.

Compensation: N/A

Impact Severity after Mitigation

Construction phase disturbance to terrestrial birds of conservation concern is considered to be minor due to small scale of works and low abundance of the concerned species.

 

             Impacts to Egretry

 

6.6.48      The western end of the proposed secondary boundary fence alignment at Mai Po is located within 100m from the Tam Kon Chau Egretry. Assessment of the potential impacts to this egretry is given in Table 6-45. Construction of the boundary fence would not cause loss of foraging grounds for breeding Chinese Pond Heron or obstruction of flight path between egretry and important foraging grounds. The only potential impact to the egretry will be the noise disturbance from working site during construction phase. However, it is predicted that the construction noise generated from the work sites will not cause severe impact or abandonment of the egretry due to the low level of noise generated and high tolerance of the egretry. The high tolerance of the egretry to noise and human disturbances can be observed from ardeid response to the activities of holiday visitors. Every public holiday, more than a hundred people visit Mai Po Nature Reserve would pass through the egretry. The disturbances caused by the visitors walking underneath and the parking of coaches in close proximity did not cause significant impact to the egretry. The breeding success of the ardeids in the past few years indicates the egretry could tolerate a moderate level of noise and human disturbances.

 

6.6.49      To mitigate the potential noise disturbance to the breeding ardeids, excavation works within a 150m buffer zone from the egretry (approximately the first 100m of Section 1 of the project area) should be avoided during ardeid breeding season (1st March to 31st July).  The egretries in the northwest New Territories have shown high tolerance to moderate level of noise disturbance. Both Mai Po Village and Tung Shing Lei egretries subjected to a close (less than 100m distance) and continual noise disturbance arise from road traffic and railway respectively were not significantly affected. Same to these two egretries, the Tam Kong Chau egretry is used by Chinese Pond Heron and receives continual noise disturbance from human activities and traffic. The noise disturbance arise from the proposed construction works at 150m apart would unlikely impose a significant impact to the breeding Chinese Pond Heron.

 

6.6.50      When construction works commence within the 150m buffer zone of the egretry in August, the egretry will be inspected to ensure all the breeding ardeids have already left. Besides, AFCD’s agreement should be obtained prior to the commencement of works should it be started in August.


 

Table 645   Potential Ecological Impacts to Tam Kon Chau Egretry.

Criteria

Impacts to Tam Kon Chau Egretry

Receivers

Chinese Pond Herons at Tam Kon Chau Egretry

Size/Abundance

26 pairs of Chinese Pond Heron in 2007

Duration

Impacts would be confined to the breeding season of ardeids, between March and July. Noise disturbance at the egret would be confined to the construction phase. Disturbance cease when the project finishes.

Reversibility

Abandonment of an egretry would be difficult to reverse

Impact Severity before Mitigation

Moderate severity of noise disturbance will occur at working site 100m apart from the egretry during excavation period.

Recommended Mitigation Measure

Avoidance and Minimizing:

Environmental sensitive areas are avoided as far as possible in consideration of alternative alignment as described in Section 1.6.

Good working practices at site (detailed in Section 3.8.14 of the noise assessment) include switching off unused equipment, keep minimum number of powered mechanical equipment in operation at the same period, the use of stockpiles and other structures to form noise barriers where practicable installation of a movable noise barrier to the breaker to reduce the noise level during excavation phase. 

Restriction of excavation work within a 150m buffer zone from the egretry to ardeid non-breeding season (from August to February).

Compensation: N/A

Impact Severity after Mitigation

Minor due to minor noise disturbance after avoidance of construction work within a 150m buffer zone from the egretry during ardeid breeding season and tolerance of the egretry to moderate noise levels.   

 

 

6.7                   Cumulative Impact

 

6.7.1              There are three projects proposed to be constructed in the FCA: Liantang / Heung Yuen Wai BCP in Section 3, Advance Works in River Training in Section 3 and Proposed New Wave Wall / Modification to Existing Wave Wall in Section 2.

 

Liantang/Heung Yuen Wai Boundary Control Point in Section 3

 

6.7.2              A new BCP is proposed at Heung Yuen Wai.  Civil Engineering and Development Department has been informed that the part of Section 3 not affected by the new BCP will be completed by end 2012.

 

Advance Works for River Training in Section 3

 

6.7.3              In association with the proposed BCP at Heung Yuen Wai, Drainage Service Department (DSD) will carry out advance works for the river training from Ping Yuen River to Pak Fu Shan.  As advised by DSD, the works would commence in mid-2012 and its exact extent could only be confirmed after a study at the end of 2009. As DSD’s advance works is at a preliminary stage during the study period of this EIA, the cumulative impact cannot at present be predicted. Instead, when the scope of the river training has been confirmed, an impact assessment would be carried out to identify potential cumulative impact and to recommend mitigation measures if necessary.

 

Proposed New Wave Wall / Modification to Existing Wave Wall in Section 2

 

6.7.4              The works in Section 2 will have interface with DSD’s proposed modification of the existing wave wall and construction of a new wave wall alongside the Shenzhen River in Section 2.  As the proposed works will involve only simple works of building the wave wall and be confined within DSD’s existing maintenance access, no cumulative impact is expected.

 

 

6.8                   Residual Impact

 

6.8.1              With the implementation of the recommended mitigation measures detailed in Section 6.6, no residual ecological impacts are anticipated.

 

6.9                   Environmental Monitoring and Audit Requirements

 

6.9.1              The implementation of the ecological mitigation measures stated in Section 6.6 should be checked as part of the environmental monitoring and audit procedures during the construction period as presented in the separate Environmental Monitoring and Audit Manual.  No other ecology-specific measures are considered necessary.

 

6.10               Conclusions

 

6.10.1           An Ecological Impact Assessment had been conducted for the proposed project. Ecological surveys were carried out in November 2007 to October 2008 which covered both wet and dry seasons.

 

6.10.2           A total of 15 habitat types were identified within the Assessment Area, including woodland, shrubland, plantation, gei wai, mangrove, pond, marsh, wet agricultural land, dry agricultural land, abandoned agricultural land / low-lying grassland, hillside grassland, stream / river, drainage channel, open field and developed area.

 

6.10.3           Two individuals of flora species of conservation interest, Berchemia lineata and Aquilaria sinensis were recorded within the Project Area at Section 2 and Section 3 respectively. In-situ preservation and providing protective fencing during construction period are recommended to avoid potential impact on these plants.

 

6.10.4           The construction works at WCA without mitigation measures would have adverse impact on the ecology of the area notably the wetland-depended birds roosting in the Mai Po Nature Reserve and the surrounding fishponds. To avoid the potential disturbance to these ecological sensitive receivers, avoidance of construction works using PMEs in WCA during the wintering period (15th November – 15th March) is recommended.

 

6.10.5           Excavation works at Mai Po during the ardeid breeding season (from 1st March to 31st July) should not be carried out to prevent potential disturbance to the Tam Kon Chau egretry.

 

 

6.11               References

 

Agriculture, Fisheries and Conservation Department, Search Hong Kong Biodiversity (2006) Retrieved Sept 2008 from http://www.afcd.gov.hk/english/conservation/hkbiodiversity/hkbiodiversity.html

 

Anon, 2004a. Summer 2004 Report on Waterbird Monitoring at the Mai Po Inner Deep Bay Ramsar Site. Report by Hong Kong Bird Watching Society to the Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.

 

Anon, 2004b. Summer 2004 Report: Egretry Counts in Hong Kong with particular reference to the mai Po Inner Deep Bay Ramsar Site. Reported by Hong Kong Bird Watching Society to the Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.

 

Anon, 2005a. Winter 2004-05 Report on Waterbird Monitoring at the Mai Po Inner Deep Bay Ramsar Site. Report by Hong Kong Bird Watching Society to the Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.

 

Anon, 2005b. Summer 2005 Report on Waterbird Monitoring at the Mai Po Inner Deep Bay Ramsar Site. Report by Hong Kong Bird Watching Society to the Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.

 

Anon, 2005c. Summer 2005 Report: Egretry Counts in Hong Kong with particular reference to the mai Po Inner Deep Bay Ramsar Site. Reported by Hong Kong Bird Watching Society to the Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.

 

Anon, 2006a. Winter 2005-06 Report on Waterbird Monitoring at the Mai Po Inner Deep Bay Ramsar Site. Report by Hong Kong Bird Watching Society to the Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.

 

Anon, 2006b. Summer 2006 Report on Waterbird Monitoring at the Mai Po Inner Deep Bay Ramsar Site. Report by Hong Kong Bird Watching Society to the Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.

 

Anon, 2006c. Summer 2006 Report: Egretry Counts in Hong Kong with particular reference to the mai Po Inner Deep Bay Ramsar Site. Reported by Hong Kong Bird Watching Society to the Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.

 

Anon, 2007a. Winter 2006-07 Report on Waterbird Monitoring at the Mai Po Inner Deep Bay Ramsar Site. Report by Hong Kong Bird Watching Society to the Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.

 

Anon, 2007b. Summer 2007 Report on Waterbird Monitoring at the Mai Po Inner Deep Bay Ramsar Site. Report by Hong Kong Bird Watching Society to the Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.

 

Anon, 2007c. Summer 2007 Report: Egretry Counts in Hong Kong with particular reference to the mai Po Inner Deep Bay Ramsar Site. Reported by Hong Kong Bird Watching Society to the Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.

Anon, 2008. Winter 2007-08 Report on Waterbird Monitoring at the Mai Po Inner Deep Bay Ramsar Site. Report by Hong Kong Bird Watching Society to the Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.

 

BirdLife International 2008a Species factsheet: Sturnus sericeus. Downloaded from http://www.birdlife.org on 31/10/2008

 

BirdLife International 2008b Species factsheet: Anser erythropus. Downloaded from http://www.birdlife.org on 31/10/2008

 

Corlett, R.T., Xing, F.W., Ng, S.C., Chau, L.K.C. and Wong, L.M.Y, 2000. Hong Kong Vascular Plants: Distribution and Status. Memoirs of the Hong Kong Natural History Society 23:1-157.

 

Drainage Services Department, 2007. Drainage Improvement in Northern New Territories – Package C EIA.

 

Fellowes, J.R., Lau, M.W.N., Dudgeon, D., Reels, G.T., Ades, G.W.J., Carey, G.J., Chan, B.P.L., Kendrick, R.C., Lee, K.S., Leven, M.R., Wilson, K.D.P and Yu, Y.T. 2002. Wild Animals to Watch: Terrestrial and Freshwater Fauna of Conservation Concern in Hong Kong. Memoirs of the Hong Kong Natural History Society, 25, 123-160.

 

IUCN 2008. 2008 IUCN Red List of Threatened Species. <www.iucnredlist.org>. Downloaded on 31 October 2008.

 

Kadoorie Farm and Botanic Garden. 2004. A Pilot Biodiversity Study of the eastern Frontier Closed Area and North East New Territories, Hong Kong, June-December 2003. Kadoorie Farm and Botanic Garden Publication Series No.1. Kadoorie Farm and Botanic Garden, Hong Kong Special Administrative Region.

 

Karsen, S. J., Lau, M.W.N, & Bogadek, A. 1998. Hong Kong Amphibians and Reptiles (2nd Edition). Provisional Urban Council Hong Kong.

 

Lee, V. L. F., Lam, S. K. S., Ng, F. K. Y., Chan, T. K. T. and Young, M. L. C., 2004. Field Guide to the Freshwater Fish of Hong Kong. Agriculture, Fisheries and Conservation Department, Friends of the Country Parks and Cosmos Books Ltd., Hong Kong.

 

Lee, W.H., Wong, E.Y.H., Chow, G.K.L. and Lai, P.C.C., 2007. Review of Egretries in Hong Kong. Hong Kong Biodiversity Agriculture, Fisheries and Conservation Department Newsletter 14:1-6. Hong Kong.

 

Lo, P.Y.F. and Hui, W., 2005 Hong Kong Butterflies, Fisheries and Conservation Department, Friends of the Country Parks and Cosmos Books Ltd., Hong Kong.

 

Ove Arup & Partners Hong Kong Ltd. 2002. Agreement No. CE 39/2001 Shenzhen Western corridor-Investigation and Planning. EIA Report. Highways Department, HKSAR.

 

Shek, C.T. and Chan, S.M., 2005. Roost Censuses of Cave Dwelling Bats of Hong Kong. Hong Kong Biodiversity Agriculture, Fisheries and Conservation Department Newsletter 10:1-8. Hong Kong.

 

Town Planning Board, 1999 Guidelines for Application for Developments within Deep Bay Area under Section 16 of the Town Planning Ordinance. Planning Department, Hong Kong.

 

Tsim S.T., Lock N.Y. 2002. Knowing Ramsar Site. Agriculture, Fisheries and Conservation Department, Friends of the Country Parks and Cosmos Books Ltd., Hong Kong.

 

Wilson, K.D.P., Tam, T.W., Kwan, S.P., Wu, K.Y., Wong, S.F., Wong, K. 2003. Field Guide to the Dragonflies of Hong Kong. Agriculture, Fisheries and Conservation Department, Hong Kong.

 

Wong, L.C. and Woo, C.K. 2003. Summer 2003 Report on Egretry Counts in Hong Kong, with particular reference to the Mai Po Inner Deep Bay Ramsar site. Hong Kong Bird Watching Society, Hong Kong.

 

Young, L. 1998 The importance to ardeids of the Deep Bay fish ponds, Hong Kong. Biological Conservation 84 No. 3, pp. 293-300. UK.

 

Yu, Y.T. 2003. Summer 2003 Report on Waterbird Monitoring at the Mai Po Inner Deep Bay Ramsar Site. The Hong Kong Bird Watching Society Limited. Hong Kong.

 

Yu, Y.T. 2004. Winter 2003-04 Report on Waterbird Monitoring at the Mai Po Inner Deep Bay Ramsar Site. The Hong Kong Bird Watching Society Limited. Hong Kong.

 


7                        Landscape and Visual Impact

 

7.1                   Introduction

 

7.1.1              This Chapter describes the preliminary findings of the interim draft landscape and visual impact assessment arising from the construction of the Secondary Boundary Fence and New Sections of Primary Boundary Fence and Patrol Road. In accordance with the criteria and guidelines as stated in Annex 10 and 18 of the TM and EIAO, Cap. 449, any potential landscape and visual impacts in the project resulted from both construction and operational phases will be assessed.

 

7.1.2              This aim of this report is to outline the landscape baseline conditions of existing landscape resources (LRs) and landscape character area (LCAs), the visual amenity, visually sensitive receivers (VSRs) and the planning and development control frameworks. Any potential impacts arsing from the proposed engineered structures will be identified in detail.  Finally the report concluded by making recommendation of mitigation measures to alleviate the impact and residual effect apparent after mitigation will be discussed.

 

7.2                   Environmental Legislation, Standards, Guidelines and Criteria

 

7.2.1              Legislation, Standards, Guidelines and Criteria relevant to the consideration of landscape and visual impacts in this report include the following:

 

·         Environmental Impact Assessment Ordinance (Cap.499.S.16) and the Technical Memorandum on EIA Process (EIAO-TM), particularly Annexes 10 and 18;

·         Environmental Impact Assessment Ordinance Guidance Note 8/2002;

·         Town Planning Ordinance (Cap 131);

·         Land Administration Office Instruction (LAOI) Section D-12 - Tree Preservation;

·         HyDTC No. 10/2001 – Visibility of Directional Signs;

·         WBTC No. 25/92 - Allocation of Space for Urban Street Trees;

·         WBTC No. 7/2002 - Tree Planting in Public Works;

·         ETWB TCW No. 2/2004 - Maintenance of Vegetation and Hard Landscape Features;

·         ETWB TCW No. 29/2004 - Registration of Old and Valuable Trees, and Guidelines for their Preservation;

·         ETWB No. 36/2004 - Advisory Committee on the Appearance of Bridges and Associated Structures (ACABAS);

·         ETWB TCW No. 3/2006 - Tree Preservation;

·         Hong Kong Planning Standards and Guidelines Chapter 4 and Chapter 10; and

·         Study on Landscape Value Mapping of Hong Kong.

 

7.3                   Assessment Methodology

 

7.3.1              The Project is a designated project under the EIAO and the methodology adopted for the Project conforms to the requirements of the EIAO. The methodology consists of the following tasks:

·         Review of the Planning and Development Control Framework;

·         Baseline study of landscape and visual resources;

·         Landscape impact assessment;

·         Visual impact assessment;

·         Recommendation on landscape and visual mitigation measures; and

·         Identification of residual impacts.

 

Landscape Baseline Review and Impact Assessment

 

7.3.2              The assessment of the potential impacts of a proposed scheme on the existing landscape comprises two distinct sections namely the baseline survey and the landscape impact assessment. Landscape Impact Assessment (LIA) Study Area is taken to include all areas within 500m of the site boundary.

 

7.3.3              A baseline survey of the existing landscape resources and landscape character has been undertaken based on a combination of desktop studies and site surveys. The landscape elements which contribute to the landscape character include:

·         Local topography;

·         Woodland extent and type;

·         Other vegetation types;

·         Built form (including scale and appearance);

·         Patterns of settlement;

·         Land use;

·         Scenic spots;

·         Details of local materials, styles, streetscapes, etc.;

·         Prominent watercourses; and

·         Cultural and religious identity.

 

7.3.4              The process of landscape characterisation draws on the information gathered in the desk top and site survey and provides an analysis of the way in which the elements including the identified landscape resources (LRs) interact to create the character of the landscape. The Study Area is then divided into broadly homogenous units of similar character which are called Landscape Character Areas (LCAs).

 

7.3.5              The sensitivity of the individual LRs and LCAs to change is rated using low, medium or high depending on the following factors:

·         Condition, quality and maturity (maturity in this context refers to the age of the LR or LCA relative to its constituent components therefore a woodland containing mature trees would be considered to have a high level of maturity) of the LRs / LCAs;

·         Importance and rarity of special landscape elements (rarity being of either local, regional, national or global importance) and the significance of change to these LRs / LCAs from a local and regional/ LCAs from a local and regional perspective (therefore the sensitivity of a LR or LCA which is either rare in a local or regional context is greater than one which is common place);  

·         Ability of the LRs / LCAs to accommodate change; and

·         Statutory or regulatory requirements relating to the landscape including its resources.

 

7.3.6              The next stage of the assessment process is the identification of the assessment of the magnitude of change (rated as negligible, small, intermediate or large) arising from the implementation of the proposals and the principal sources of impact based on the following factors:

·         Scale of the development and proposed access road;

·         Compatibility of the project with the surrounding landscape;

·         Duration of impacts (temporary or permanent) under construction and operational phases; and

·         Reversibility of change.

 

7.3.7              The degree of significance of landscape impact is derived from the magnitude of change which the proposals will cause to the existing landscape context and its ability to tolerate the change, i.e. its condition / quality and sensitivity. This makes a comparison between the landscapes which would have existed in the absence of the proposals with that predicted as a result of the implementation of the proposals. The significance threshold for impacts to LRs and LCAs is rated as significant, moderate, slight or negligible. The impacts may be beneficial or adverse.

 

7.3.8              The significance threshold is derived from the following matrix:

 

Magnitude of Change caused by Proposals

Large

Moderate Impact

Moderate / Significant Impact

Significant Impact

Intermediate

Slight or Moderate Impact

Moderate Impact

Moderate or Significant Impact

Small

Slight Impact

Slight or Moderate Impact

Moderate Impact

Negligible

Negligible

Negligible

Negligible

 

Low

Medium

High

 

Sensitivity of Landscape to Change

 

7.3.9              The above matrix will apply in the assessment of the majority of situations, however, in certain cases a deviation from this may occur, e.g. the impact may be so major that a significant impact may occur to a LCA or LR with a low sensitivity to change.

 

Visual Baseline Review and Impact Assessment

 

7.3.10           The assessment of the potential visual impact of the scheme comprises two distinct parts:

·         Baseline survey; and,

·         Visual impact assessment which includes the identification of the sources of visual impact, and their magnitude, that would be generated during construction and operational phases of the proposed scheme; and, identification of the principal visual impacts primarily in consideration of the degree of change to the baseline conditions.

 

7.3.11           The assessment area for the Visual Impact Assessment (VIA) in accordance with the study brief, is defined by the Visual Envelope (VE) which includes all areas from which the scheme proposals can be seen, or the area forms the view shed formed by natural / manmade features such as existing ridgelines, built development and for example areas of woodland / large trees.  Within the VE a number of Zones of Visual Influence (ZVIs) are identified to demonstrate the visibility of various aspects of the scheme proposals.  This is achieved through a combination of detailed walkover surveys, and desk-top study of topographic maps and photographs, and preparation of cross-sections to determine visibility of the improvement works from various locations.

 

7.3.12           The baseline survey of all views towards the proposals is undertaken by identifying:

·         The VE and ZVIs as has been described above and may contain either wholly or partially within views. This must also include indirect effects such as offsite construction activities; and

·         The visually sensitive receivers (VSRs) within the visual envelope whose views will be affected by the scheme.

 

7.3.13           The potential receivers are considered as four groups:

·         Views from residences – the most sensitive of receivers due to the high potential of intrusion on the visual amenity and quality of life;

·         View from workplaces / institutional and educational buildings  – less sensitive than above due to visual amenity being less important within these environments;

·         Views from recreational landscapes – including all areas apart from the above, e.g., public parks, recreation grounds, footpaths, cultural sites etc. Sensitivity of this group depends on the length of stay and nature of activity, e.g. sitting in a park as opposed to an active sporting pursuit; and

·         Views from public roads and railways – including vehicle travellers with transitory views.

 

7.3.14           The assessment of sensitivity is also based on the quality and extent of the existing view. Therefore a view from a residential property, which would normally be considered the most sensitive view, may be less so if for example it is degraded by existing development or partially screened by intervening visual obstacles such as existing vegetation. Factors affecting the sensitivity of receivers for evaluation of visual impacts:

·         Value and quality of existing views;

·         Availability and amenity of alternative views;

·         Type of receiver population and estimated number of affected receiver population;

·         Duration or frequency of view; and,

·         Degree of visibility.

 

7.3.15           The location and direction of its view relative to the scheme also influences the sensitivity of each group. Typical viewpoints from within each of the visually sensitive groups are identified and their views described. Both present and future (planned visually sensitive receivers (PVSRs) are considered.

 

7.3.16           The factors affecting the magnitude of change for assessing the visual impacts include the following:

·         Scale of the proposed scheme;

·         Compatibility of the project with the surrounding landscape forming the view; extent of visibility (level of potential blockage of the view);

·         Viewing distance;

·         Duration of impacts under construction and operational phases; and

·         Reversibility of change.

 

7.3.17           Views available to the identified VSRs are rated according to their sensitivity to change using low, medium or high. The magnitude of change to the views will be classified as follows:

·         Large: e.g. major change in view;

·         Intermediate: e.g. moderate change in view;

·         Small: e.g. minor change in view; and

·         Negligible: e.g. no discernible change in view.

 

7.3.18           The significance threshold for visual impact is rated in a similar fashion to the landscape impact, i.e. significant, moderate, slight and negligible. The impacts may be beneficial or adverse.

7.3.19           Therefore the impact is derived from the magnitude of change which the proposals will cause to the existing landscape context and its ability to tolerate the change, i.e. its quality and sensitivity.  

 

7.3.20           The significance threshold is derived from the following matrix:

 

Magnitude of Change caused by Proposals

Large

Moderate Impact

Moderate / Significant Impact

Significant Impact

Intermediate

Slight / Moderate Impact

Moderate Impact

Moderate / Significant Impact

Small

Slight Impact

Slight / Moderate Impact

Moderate Impact

Negligible

Negligible

Negligible

Negligible

 

Low

Medium

High

 

Sensitivity of View to Change

 

7.3.21           The above matrix will apply in the assessment of the majority of situations, however, in certain cases a deviation from this may occur, e.g. the impact may be so major that a significant impact may occur to a view with a low sensitivity to change.

 

7.3.22           Table 7-1 below provides an explanation of the degree of impact for both landscape and visual aspects of the project.

Table 71     Degree of Impact

Impact

Description

Significant

Adverse / beneficial impact where the proposal would cause significant deterioration or improvement in existing landscape quality or visual amenity.

Moderate

Adverse / beneficial impact where the proposal would cause a noticeable deterioration or improvement in existing landscape quality or visual amenity.

Slight

Adverse / beneficial impact where the proposal would cause a barely perceptible deterioration or improvement in the existing landscape quality or visual amenity.

Negligible

No discernible change in the existing landscape quality or visual amenity.

 

Identification of Potential Landscape and Visual Impact Mitigation Measures

 

7.3.23           The purpose of mitigation is to avoid, reduce, and where possible remedy or offset any adverse effects on the environment arising from the proposed development. The ideal strategy for identifiable adverse impacts is avoidance. If this is not possible, alternative strategies of reduction, remediation and compensation should be explored.

 

7.3.24           Mitigation measures may be considered under two categories:

·         Primary mitigation measures that intrinsically comprise part of the development design through an iterative process. This form of mitigation is generally the most effective; and

·         Secondary mitigation measures designed to specifically address the remaining (residual) adverse effects of the final development process.

 

7.3.25           Primary mitigation measures form integrated mainstream components of the project design focusing on the adoption of alternative designs or revisions to the basic engineering and architectural design to prevent and/or minimise adverse impacts including siting, access, layout, buildings and structures etc.  The design philosophy can also describe the benefits to the design of alternative solutions, introduced to reduce potential adverse impacts, and indicate how these have been addressed.

 

7.3.26           Secondary mitigation measures are specifically designed to mitigate the adverse impacts of the final development and are considered in the assessment of the landscape and visual impacts.  These may take the form of remedial measures such as colour and textural treatment of building features; and compensatory measures such as the implementation of landscape design measures (e.g. tree planting, creation of new open space etc) to compensate for unavoidable adverse impacts and to attempt to generate potentially beneficial long-term impacts.

 

7.3.27           The agencies responsible for the funding, implementation, management of the mitigation measures have been identified and their approval-in-principle will be sought

 

Residual Impacts

 

7.3.28           The Residual impacts are those, which remain after the proposed mitigation measures, have been implemented. This has been assessed both during the construction period and during the design year which is often taken to be 10 to 15 years after the proposed scheme has been opened to normal operation when the soft landscape mitigation measures are deemed to have reached a level of maturity which allows them to perform their original design objectives.

7.3.29           The level of impact is derived from the magnitude of change which the proposals will cause to the view which would have existed during this period if the proposed scheme had not been constructed and its ability to tolerate change, i.e. its quality and sensitivity taking into account the beneficial effects of the proposed mitigation. The significance threshold is derived from the matrices described separately above for the landscape and visual impacts.

 

7.3.30           In accordance with Annex 10 of the EIAO-TM a final conclusion is also made of the residual landscape and visual impacts attributable to the proposed scheme. The degree of residual impact is considered in accordance with the Residual Impact Significance Threshold Matrix in Table 7.2 below.

Table 72     Residual Impact Significance Threshold Matrix

Residual Impact

Description

Beneficial

The project will complement the landscape and visual character of its setting, will follow the relevant planning objectives and will improve overall and visual quality.

Acceptable

There will be no significant effects on the landscape and no significant visual effects caused by the appearance of the project, or no interference with key views.

Acceptable with mitigation

There will be some adverse effects, but these can be eliminated, reduced or offset to a large extent by specific measures.

Unacceptable

The adverse affects are considered too excessive and are would not be reduced to an acceptable level by mitigation.

Undetermined

Significant adverse effects are likely but the extent to which they may occur or may be mitigated cannot be determined from the study. Further detailed study will be required for the specific effects in question.

 

Graphic Presentation of Mitigation Measures

 

7.3.31           In order to illustrate these landscape and visual impacts and to demonstrate the effectiveness of the proposed landscape and visual mitigation measures, photomontages at selected representative viewpoints, agreed with Planning Department at the outset of the study, have been prepared to illustrate:

·         Existing conditions;

·         Day 1 of Operation Phase without Landscape Mitigation Measures;

·         Day 1 of Operation Phase with Landscape Mitigation Measures; and

·         Year 10 of Operation Phase with Landscape Mitigation Measures.

 

7.3.32           It is assumed that funding, implementation, management and maintenance of the mitigation proposals can be satisfactorily resolved according to the principles in WBTC 14/2002. All mitigation proposals in this report are practical and achievable within the known parameters of funding, implementation, management and maintenance. The suggested agents for the funding and implementation (and subsequent management and maintenance, if applicable) are indicated in Tables 7.13 and 7.14.  Approval-in-principle to the implementation, management and maintenance of the proposed mitigation measures will be sought from the appropriate authorities.

 

 

7.4                   Project Description

 

7.4.1              The Project mainly comprises the construction of an SBF along the southern edge of the existing BPR (approximately 21.7km) from west (Pak Hok Chau) to east (Sha Tau Kok).  For sections where the existing PBF runs along the southern edge of the BPR, a new fence with sensor alarm system will be constructed on the northern edge of the BPR as part of the PBF whereas the existing PBF will become the SBF.  The project also includes the conversion of the existing maintenance services road along the Shenzhen River bank to the north of the Lok Ma Chau Loop and Hoo Hok Wai into a new section of the BPR with a PBF and an SBF; and construction of two new sections of the BPR with a PBF and an SBF along the Shenzhen River side to the north of Pak Fu Shan and northwest of Lin Ma Hang Village.  In addition, the Project includes the construction of a checkpoint at the entrance to the Sha Tau Kok town (i.e. location of “Gate One”) and replacement of the existing checkpoint at Pak Hok Chau, removal of the existing checkpoints at Lok Ma Chau, Sha Ling, Ping Che and Shek Chung Au, and removal of the existing PBF along those sections of the existing BPR which will be replaced by new sections of the BPR.

 

7.4.2              The height of the proposed PBF will be 4.5m and the SBF 3.5m. The approximate size of the proposed one storey checkpoints are as follows:

·         The checkpoint at Gate 1 (9m long x 6.5m wide x 3.5m high);

·         Sha Tau Kok (3.5m long x 3m wide x 3m high); and

·         Pak Hok Chau – prefabricated type (3.5m long x 3m wide x 3m high).

 

7.4.3              The entire length of the Project is about 21.7km from west of Pak Hok Chau to east of Sha Tau Kok and is divided into four sections as shown in Figure 1.1.  The project scope of each section is described below.

 

Section 1 – Mai Po to Lok Ma Chau Control Point

 

(i)    To erect an SBF along the existing BPR (approximately 4.1km); and

 

(ii)   To replace the existing checkpoint at Pak Hok Chau.

 

Section 2 – Lok Ma Chau Control Point to Ng Tung River

 

(i)    To convert the maintenance services road of Drainage Services Department along the Shenzhen River bank to the north of the Lok Ma Chau Loop and Hoo Hok Wai into a new section of the BPR (approximately 5.6km);

 

(ii)   To erect a new PBF with the sensor alarm system and an SBF respectively along the northern and southern side of the converted road;

 

(iii)  To remove the original PBF and the sensor alarm system thereon along the existing BPR south of the Lok Ma Chau Loop and Hoo Hok Wai; and

 

(iv)  To remove the existing checkpoint at Lok Ma Chau Road.

 

 

 

Section 3 – Ng Tung River to Lin Ma Hang Village

 

(i)    To erect an SBF along the existing BPR except the sections to the north of Pak Fu Shan and northwest of Lin Ma Hang Village (approximately 7.5km); 

 

(ii)   To construct new sections of the BPR along the Shenzhen River side to the north of Pak Fu Shan and northwest of Lin Ma Hang Village without necessitating river training (approximately 4.0km);

(iii)  To erect a new PBF with the sensor alarm system and an SBF along the northern and southern sides of the new sections of BPR respectively;

 

(iv)  To remove the original PBF and the sensor alarm system thereon along the existing BPR near Pak Fu Shan and Lin Ma Hang Village; and

 

(v)   To remove the existing checkpoints at Sha Ling and Ping Che.

 

Section 4 – Lin Ma Hang Village to Sha Tau Kok

 

(i)    To erect an SBF from the entrance of the Sha Tau Kok town (i.e. the location of “Gate One”) to the Sha Tau Kok Control Point (approximately 0.5km);

 

(ii)   To provide a new checkpoint at “Gate One”; and

 

(iii)  To remove the existing checkpoint at Shek Chung Au.

 

7.5                   Review of Planning and Development Control Framework

 

7.5.1              A review of the existing planning studies and documents has been undertaken to gain an insight into the planned role of the site, its context and to help to determine if the project fits into the wider landscape context. The assessment does not consider all of the areas zoned on the OZP but focus on only those might be affected by the proposed works or encroach to the 500M Study Area.  The locations of these areas are shown on Figure 7-1. This review considered the following aspects of the identified planning designations:

·         Zoning areas which would be physically affected by the proposals, that is where the implementation of the proposal works would lead to the actual loss of an area; 

·         The potential degradation of the landscape setting of an area which might effect the viability of it’s landscape planning designation but not result in a loss of zoning area;

·         The visual amenity enjoyed by future residents or users; and 

·         The general fit of the proposals into this future landscape.

 

7.5.2              The assessment covers areas shown on the following Outline Zoning Plans:

·         S/NE-KTN/8 Kwu Tung North;

·         S/YL-MP/6 Mai Po and Fairview Park;

·         S/YL-NSW/8 Nam Sang Wai; and

·         S/YL-ST/8 San Tin,

·         S/NE-FTA/10 Fu Tei and Sha ling

 

7.5.3              This review has found the following impacts on identified planning designations. Areas that would only be physically affected by the implementation of the proposed secondary fence and adjustment of patrol road and removal of sections of existing boundary fence that are located at existing Border Road at Tam Kon Chau to Lo Wo and alongside of Shenzhen River where encroach to individual zoning boundaries. The majority of the proposed works will not directly affect the existing land uses within 500M Study Area, with exception of the following:

·         Conservation Area (CA) zone at Mai Po Tam Kon Chau – the road embankment of existing Border Road at the peripheries of this zoning.

·         Conservation Area (CA) zone at Sam Po Shue – the road embankment of existing Border Road at the peripheries of this zoning.

·         Other Specified Uses  (RAILWAY TERMINUS AND PUBLIC TRANSPORT TERMINUS) zone at Lok Ma Chau Railway Station - the road embankment of existing Border Road at the peripheries of this zoning.

 

7.5.4          Although some of zonings are encroached to the 500M Study Area as shown in Figure 7-1, the proposed works will not directly affected the areas within these zonings, hence are not contained in the assessment in Table 7-4.

 

7.5.5          Although there are some impacts to zoned areas, the proposed works would not degrade the overall landscape setting of the area or affect its viability or existing character. New tree planting at selected locations along the new boundary fence alignment will also provide screening and enhance the landscape value along the patrol road as well as the interface encroaching to individual zoning areas. 

 

7.5.6          In addition, the removal sections of existing fence between Lok Ma Chau and Lo Wu and along Lin Ma Hang Road will enhance the rural landscape and integration of landscape components within individual zonings.

 

7.5.7          Given the above summary and detailed review in Table 7‑3, the proposed works largely fits into the planning and development control framework and integrates with the future outlook of the rural landscape context.

 

7.5.8          Since a section of the proposed excavation works will fall within the Conservation Area (CA) on the two Outline Zoning Plans (OZP) viz. the approved Mai Po and Fairview Park OZP No. S/YL-MP/6 and the approved San Tin OZP No. S/YL-ST/8 as well as the Wetland Conservation Area (WCA) on the western portion of the alignment beginning from the
Pak Hok Chau Checkpoint, a planning application will be submitted for the Town Planning Board's consideration.

 

7.5.9          In addition, a planning study was undertaken on 2007 by Planning Department regarding to the feasibility of introducing a new cross-border facility connecting Hong Kong Lin Ma Hang and Shenzhen Liantang. Although this proposal is still under planning stage, the proposed works have been taking into account this proposal in the development of secondary boundary fence and patrol road and allow flexibility for the development of new cross-border facilities.


Table 73     Review of Existing Planning and Development Control Framework

Land Use Zonings

Landscape Planning, Design and                Conservation Intention of Zoning

Potential Impacts/Approx. Area Affected by the Proposed Works / Total Zoning Area

Mitigation Measures and Future Outlook of the Area with the Proposed Works

Outline Zoning Plan number S/YL-MP/6 Mai Po and Fairview Park

1.     Conservation Area (CA)

This zone encompasses the fish pond areas to the north of Tam Kon Chau and Mai Po Villages to the east of Mai Po Nature Reserve. This zone is intended primarily for the conservation of the wetland and fish ponds which form the integral part of the wetland ecosystem in the Deep Bay Area and function as a substantial source of food supply for birds and as an important habitat for roosting and foraging of waterbirds. Agriculture and Nature Conservation uses always permitted to enhance the ecology value of the area.

The proposed secondary boundary fence runs parallel to the existing boundary fence alongside of the Border Road which located at the northern boundary of this “CA” zone. The proposed works requires slightly modification of the Border Road and construction of the secondary boundary fence on existing road embankment, no fish pond area will be affected.

1.5 ha/277 ha (<1%)

Given that the proposed secondary boundary fence only occupies a small portion of this zone adjacent to the existing Border Road, and largely aligns with existing fence, this fence is designed for territory security purposes; hence the proposed works are compatible to the planning intention for this Closed Area. Given the limitation of land acquisition to minimise impact to fish ponds and scattered village houses in this area, and clearance requirement along Border Road between existing and proposed fences, new tree planting is proposed at selected areas where space is allowed, this planting proposal will make a better integration to the rural landscapes.

Outline Zoning Plan number S/YL-ST/8 San Tin

2.     Conservation Area (CA)

This zone encompasses the fish pond areas at Sam Po Shue to the north of San Tin Villages and to the east of Lok Ma Chau Railway Station. This zone is intended primarily for the conservation of the wetland and fish ponds which form the integral part of the wetland ecosystem in the Deep Bay Area and function as a substantial source of food supply for birds and as an important habitat for roosting and foraging of water birds. Agriculture and Nature Conservation uses always permitted to enhance the ecology value of the area.

The proposed secondary boundary fence runs parallel to the existing boundary fence alongsides of the Border Road which located at the northern boundary of this “CA” zone. The proposed works requires slightly modification of the Border Road and construction of the secondary boundary fence on existing road embankment, no fish pond area will be affected. Besides the existing boundary fence section between Lok Ma Chau Village and Lo Wu Tak Yuet Lau along Border Road is proposed to be removed and reprovision of new boundary fence and patrol road alignment to the further north, this proposal will enhance the rural landscape along existing border road by removal on engineering structures in this zone.

1.4ha/182 ha (<1%)

Given that the proposed secondary boundary fence only occupies a small portion of this zone adjacent to the existing Border Road, and largely aligns with existing fence, this fence is designed for territory security purposes; hence the proposed works are compatible to the planning intention for this Closed Area. Given the limitation of land acquisition to minimise impact to fish ponds and scattered village houses in this area, and clearance requirement along Border Road between existing and proposed fences, new tree planting is proposed at selected areas where space is allowed, this planting proposal will make a better integration to the rural landscapes.

3.  Other Specified Uses  (RAILWAY TERMINUS AND PUBLIC TRANSPORT TERMINUS)

This zone encompasses the cross-border infrastructure facilities including the Lok Ma Chau Railway Terminal and public transport interchange. This zone is reserved for cross-border infrastructure facility uses.

The proposed secondary boundary fence runs parallel to the existing boundary fence alongside of the Border Road which located at the northern boundary of this “OU” zone. The proposed works requires slightly modification of the Border Road and construction of the secondary boundary fence on existing road embankment, only limited to the western portion of this zone, no existing cross-border infrastructure facilities will be affected. The new compensatory wetland area located to the eastern portion of this zone will not be affected.

0.12ha/6.3 ha (<1%)

Given that the proposed secondary boundary fence only occupies a small portion of this zone along existing Border Road, and largely aligns with existing fence, this fence is designed for territory security purposes; hence the proposed works are compatible to the planning intention for the cross-border facilities. Given the proposed works do not encroach to the railway station and cross border facilities for security and operation reasons, the infrastructure landscape will remain unchanged. 

 

 


7.6                   Landscape and Visual Baseline Study

 

Baseline Conditions

 

7.6.1              This section describes the baseline study which reviews of the existing landscape establishes broad characteristics, identifies landscape resources, landscape character and visual amenity of Study Area. Any changes which are raised by the construction works during the construction and operational phase will be assessed. 

 

7.6.2              The baseline Figure 7-2A shows the existing LRs found within the 500m Study Area, Figures 7-2B to H provide provide a photographic record of the typical LRs found within the Study Area . In terms of landscape character Figures 7-3A to D show the extent of identified LCAs and Figures 7-4A to F demonstrate the quality of LCAs with site photographs.

 

Existing Trees

 

7.6.3              The proposed works will where possible avoid disturbance to the existing trees as far as practicable within the works areas. A full tree survey and felling application will be undertaken and submitted for approval by the relevant government departments in accordance with ETWB TCW No. 3/2006, ‘Tree Preservation’ during the detailed design phase of the project.

 

Landscape Resources (LRs)

 

7.6.4              The important determinants of the landscape character within the Study Area include a combination of fishponds, agricultural fields, village settlements and open storage intersected by road corridors and remnants of natural upland landscapes. These landscape resources (LRs) are shown on Figure 7-2.  The following LRs are identified within the Study Area:

 

LR1 Cross Border Infrastructure and Facilities

 

7.6.5              The Cross Border Infrastructure and Facilitates include the border crossings at Lok Ma Chau, Lo Wu and Man Kam To and characterised by the extensive concrete apron areas and their associated security and immigration structures. Lok Ma Chau and Lo Wu also include the structures associated with the rail crossings for the MTCR East Rail lines. These areas are heavily modified by human activity and so are considered to have a low sensitivity to further change.

 

LR2 Village Settlements 

 

7.6.6              There are six main concentrations of village settlements located at Tam Kan Chau, Shun Yee San Tsuen, Lui Pok, Ta Kwu Ling Village / Kan Tau Wai / Ka Liu Village Lin Ma Hang and Sha Tau Kok Tsuen.  The village settlements are scattered alongside of the road corridors and the adjacent lowland rural landscape. They are characterized as extensive groups of 3-storey town houses which form the settlement pattern within the lowland landscape. The existing building forms include a combination of traditional dwellings although the majority of the buildings consist of newer type developments connected by narrow lanes and footpaths. This LR is considered to have a relatively low value and sensitivity to further development.

 

LR3 Mixed Woodland

 

7.6.7              The majority of the woodlands within the Assessment Area are secondary woodland, with a small number of Fung Shui woodlands being located adjacent to the existing rural village settlements. In addition several of the secondary woodlands located alongside the existing patrol roads, which include woodlands near Liu Pok, Man Kam To Boundary Crossing and Pak Fu Shan. Five Fung Shui woodlands are located within the Study Area and these are woodlands preserved by the villagers for traditional Fung Shui beliefs. These Fung Shui woodlands are situated behind the rural villages of Kan Tau Wai, Tsung Yuen Ha, Sheung Tam Shui Hang, Shan Tsui and Lin Ma Hang. For the large part these Fung Shui woodlands are located at some distance from the proposed alignment (typically at least 200m) although the woodland at Shan Tsui fung shui wood is located at a distance of about 150m.  The dominant species within these areas are native tree and shrub species such as Aquilaria sinensis, Aporusa dioica, Celtis sinensis, Cinnamomum camphora, Cratoxylum cochinchinense, Mallotus paniculatus, Schefflera heptaphylla, Schima superba, Psychotria asiatica and Uvaria macrophylla. Due to the unique nature of the woodlands which form this resource they are thought to be locally significant and hence their sensitivity to change is considered to be high.

 

LR4 Plantation Woodland

 

7.6.8              Plantation Woodlands are largely located with sections 1-3 of the proposed scheme are typically associated with the major infrastructural developments including the border crossing at Lok Ma Chau and Man Kam To, and in buffer areas between Ta Sha Lok and Sheung Ma Lei Yue, on the hill slopes to the northeast of Sandy Ridge, and in a number of extensive plantations to the north of the border at Chuk Yuen, to the northwest of Pau Fu Shan and north of Wen Lek. The main value of these resources is in their contribution to the landscape as a group not as individual trees due to majority of the tree species being fast growing non-native species, commonly found in plantation woodlands in Hong Kong and across the border. The plantations are normally planted at close planting distances in rows to create an instant effect. Plantation is forest dominated by planted species for either reforestation, landscape or fruit production purposes and include species such as Acacia auriculiformis, Acacia confusa, Lophostemon confertus, Casuarina equisetifolia, Clausena lansium, Dimocarpus longan, Litchi chinensis and Syzygium jambos. It is considered that this resource has less ecological and landscape value than the mixed woodland and is reasonably tolerate to change, hence it is considered to have a medium sensitivity to change.

 

LR5 Shrubland

 

7.6.9              The Study Area contains six main concentrations of Shrubland located on the lower hill slopes to the west and north of Tai Shek Mo, to the north of Sandy Ridge, to the north of Lo Shue Ling, and a more extensive area to the north of Pau Fu Shan. This resource forms a succession stage of grassland as it becomes colonised by tree and shrub species and within the Study Area is typically located on lower hill slopes. The common shrub spcies found within these areas include Rhodomyrtus tomentosa, Melastoma candidum, Melastoma sanguineum, Ficus hirta, Litsea rotundifolia, Ilex asprella, Phyllanthus reticulates and Desmos chinensis. This resource has a relatively low significance within this landscape context and reasonably tolerant to changes regarding to their immature nature, hence it is considered to have a medium sensitivity to change.

 

LR6 Grassland

 

7.6.10           The Study Area contains an extensive coverage of grassland, which is the dominant landscape resource on the hill slopes to the south and within the meander formed by the Sham Chun River to the north of Lok Ma Chau.   The hill slopes include the northern sides of Fung Kong Shan, Tai Shek Mo, Sandy Ridge, Lo Shue Ling, Wong Mau Shan, and the hillside slopes to the west of Sha Tau Kok. This resource forms the green backdrop to many of the views available in locations within the Study Area to the north and south of the border. These areas are the dominant habitat on the hill ranges along the southern edge of the Study Area and are maintained by frequent hill fires and can be rapidly replaced by shrubs when fires are prevented. Common grass species include Arundinella sp, Eulalia sp and Ischaemum sp. These areas are considered to have a medium sensitivity to change.

 

LR7 Agricultural Fields

 

7.6.11           The Study Area contains extensive pockets of wet and dry agricultural fields particularly associated with adjacent village settlements. The remnant field areas are covered by a combination of grass and shrub areas with intermittent tree growth. The main concentration of wet agricultural land is at Lok Ma Chau Village with the main crop species being Ipomoea aquatica and Nasturtium officinale. The dry agricultural areas largely utilised for crop production, occur in small patches near the rural villages within the Study Area and are characterised by cultivated species such as Lactuca sativa, Brassica parachinensis, Brassica chinensis, Colocasia esculenta, Apium graveolens and Daucus carota. There are also a number of areas of abandoned agricultural fields particularly in the areas between Ma Tso Lung and Sha Tau Kok via Man Kam To, Ta Kwu Leng and Lin Ma Hang. The common plant species in these areas include Ipomoea cairica, Brachiaria mutica, Conyza bonariensis, Bidens alba, Amaranthus viridis, Ipomoea triloba, Emilia sonchifolia, Youngia japonica, Mikania micrantha, Mimosa pudica, Polygonum chinense, Scoparia dulcis, Solanum nigrum, Panicum maximum and Cynodon dactylon. These areas are important to the landscape setting of the existing village settlements and so the ability of this resource to accommodate change is considered to be medium.

 

LR8 Fishponds

 

7.6.12           The Study Area contains an extensive coverage of fishponds including areas at Mai Po, San Tin, Lok Ma Chau and Hoo Hok Wai.  The majority of fishponds extending from the Deep Bay coastal plain and extend into the rural landscape to the south and east. The fishponds are characterised by their rectilinear shapes and are considered to be a regionally significant landscape resource and a distinctive feature within the Study Area. The main species composition of these areas includes Brachiaria mutica, Phragmites australis, Panicum maximum and Cynodon dactylon. This resource is considered to be important both to the landscape setting of the NWNT and is important in views from areas to the north of the border, it is susceptible to small changes and hence is considered to have a high sensitivity to change.

 

LR9 Natural Watercourses

 

7.6.13           The most extensive section of natural watercourse river within the Study Area is the unchannelised section of the upper course of the Shenzhen River and the Lin Ma Hang Stream is an ecologically important tributary. Other natural watercourses include the drainage ditches within the fishpond areas at San Tin. These are important landscape resources in setting the character for the Study Area and the dominant plant species along the streams and ditches are common riparian vegetation types such as Brachiaria mutica, Commelina diffusa, Pennisetum purpureum, Alocasia odora and Rumex trisetifer. Given the channelised nature of many of the watercourses within the Study Area this resource is considered to be valuable to its landscape and visual amenity and hence have a high sensitivity to further change.   

 

LR10 Modified Watercourse

 

7.6.14           The majority of the significant watercourses within the Study Area have been modified by man and include channelised Shenzhen River, and the lower courses of the Ng Tung River and Ping Yuen River. These water course have been widened or modified in phases for drainage improvement of coastal plain and lowland areas in NWNT since 1990s to resolve the flooding problem in these areas. The resources are characterised by their engineered nature and straightening of their banks with concrete banks and their associated access and maintenance roads. The common riparian plants found on the concrete banks include Brachiaria mutica, Commelina diffusa, Phragmites australis and Sesbania javanica. Although these watercourses are largely disturbed by engineering works, they are still scenic elements in the local landscape context. They are reasonably tolerant to changes, hence are considered to have a medium sensitivity to change.      

 

LR11 Mangrove

 

7.6.15           There are two main concentrations of mangrove located in Gei-Wai, which is an inter-tidal pond traditionally for used shrimp production, at Mai Po Nature Reserve and another smaller area to the west of Sha Tau Kok. These resources are important in forming part of the transition from the maritime landscapes of Deep Bay and Starling Inlet and the agricultural landscapes of the hinterland. The dominant mangrove species include Kandelia obovata, Avicennia marina, Aegiceras corniculatum while Phragmites australis and Brachiaria mutica are common species along the banks of the Gei-Wai. These areas form important landscape resources and hence are considered to have a high sensitivity to change.      

 

LR12 Marshland

 

7.6.16            The main areas of marshland can be found on Hoo Hok Wai to the north of Ma Tso Lung. These marshes are largely areas of former fishponds or agricultural lands which have become disused with time and colonised by natural plant species. The dominant wetland plant species include Colocasia esculenta, Ludwigia octovalvis, Phragmites australis, Brachiaria mutica, Commelina diffusa and Cyclosorus interruptus. Although not very mature and found in piecemeal pattern, these resources are regionally important and distinctive a landscape resource in Hong Kong.  Therefore marshlands are considered to have a high sensitivity to change.

 

LR13 Developed Area

 

7.6.17            Open storage is one of major urban intrusions within the NWNT, regarding to the rapid development of transportation and trading between Hong Kong and China, there is an increasing demand on container storage areas since 1980s. New storage locations within the urban area are limited hence some abandoned agricultural fields adjacent to village settlements in NT were reclaimed with concrete platforms for open container storage due to their location and proximity to cross-boarder road corridors. This urban intrusion is visually not compatible with the rural landscapes and these open storage developments in NT have been controlled since the 1990s. This resource is able to accommodate extensive change, hence, is considered to have a low sensitivity to change. 

 

7.6.18            For the purposes of this assessment the landscape resources are represented by the existing land coverage. The condition of these landscape resources is also important in determining the landscape quality of the Study Area and its sensitivity to change as described above. Therefore the preservation and enhancement of the existing landscape resources is important to the successful integration of the proposals into the landscape context of the Study Area. The following describes the impact on landscape resources due to the proposed works. Table 7-4 provides an assessment of the sensitivity of the identified LRs and their sensitivity to change.


Table 74     Landscape Resources and their Sensitivity to Change

ID.

No.

Landscape Resource

/ Area (Ha)

Quality of Landscape Resource

(High / Medium / Low)

Importance

and Rarity

(High / Medium / Low)

Ability to accommodate Change

(High / Medium

/ Low)

Local Significance of Potential Change

(High / Medium

/ Low)

Regional Significance of Potential Change

(High / Medium

 / Low)

Maturity

(High / Medium

 / Low)

Sensitivity to Change

(High / Medium / Low)

LR 1

Cross border Infrastructure and Facilities

(85Ha)

Low

Low

High

Low

Low

Medium

Low

LR2

Village Settlements

(65Ha)

Medium

Low

High

Low

Low

Medium

Low

LR3

Mixed Woodland

(79Ha)

High

High

Low

High

High

High

High

LR4

Plantation Woodland

(92Ha)

Medium

Medium

Medium

Medium

Medium

Medium

Medium

LR5

Shrubland

(45Ha)

Medium

Medium

Medium

Medium

Medium

Medium

Medium

LR6

Grassland

(618Ha)

Medium

Medium

Medium

Medium

Medium

Medium

Medium

LR7

Agricultural Fields

(36Ha)

Medium

Medium

Medium

Medium

Medium

Medium

Medium

LR8

Fishponds

(389Ha)

High

High

Low

High

High

Medium

High

LR9

Natural Stream Courses

(38Ha)

High

High

Low

High

High

High

High

LR10

Modified Watercourse

(140Ha)

Medium to Low

Low

Medium

Low

Low

Low

Medium

LR11

Mangrove

(3.3Ha)

High

High

Low

High

High

High

High

LR12

Marsh

(104Ha)

High

High

Low

High

High

High

High

LR13

Developed Area

(800Ha)

Low

Low

High

Low

Low

Low

Low

 


Landscape Character Areas (LCAs)

 

7.6.19            The landscape of the Study Area is characterized by a combination of the lowland village landscape with surrounded by both active and inactive agricultural fields, extensive fishpond areas to the south west of the Study Area, bounded by extensive upland areas with wooded hill slopes giving way to shrub and coarse grassland. The course of the Shenzhen River forms the main spine which links sections 1 to 3 of the Study Area for the proposed scheme and the extensive high-rise development to the north of the border forms a significant determinant of character for areas in which it is visible. The main lowland landscape areas are situated in the western part of the Study Area. This lowland landscape gradually gives way to a more undulating and hill landscape to the south and east including the upland areas of the Lam Tsuen Country Park and Kwun Yam Shan to the west and Robin’s Nest to the east. The main village settlements are located within the lowland areas situated throughout the Study Area.  

 

7.6.20            The rural landscape of the Study Area is largely intact although some degradation has occurred due to the introduction of major infrastructure such as the existing border crossings and the channelization of the Shenzhen River. Fishponds, agricultural fields and scattered traditional village settlement patterns backed by the naturalistic upland areas are important in forming the character of the Study Area.  Figures 7-3A to D show the location of the LCAs which form the Study Area, and Figures 7-4A to F demonstrate how these various characters fit together and form the landscape context for the Study Area. The identified LCAs are briefly described below.

 

LCA1 Tam Kon Chau Lowland Rural Landscape

 

7.6.21            This LCA is located to the south west of the Study Area and is characterised by the remnant fishponds to the south of the Shenzhen River with their largely rectilinear form separated by earth bunds and access tracks. Some of the fishponds have been abandoned over the passing of time and have reverted to marshland areas whilst there are also some limited areas of mangrove with the typical mangrove vegetation of small shrub like trees and intertidal mud banks. This LCA is an important landscape within Hong Kong and in forming the landscape setting for the dense urban development to the north of the Shenzhen River. Given its importance to the landscape of the region it is considered to have a high sensitivity to change. 

 

LCA2 Mai Po Lowland Rural Landscape

 

7.6.22            This LCA is located to the south west of the Study Area, again it is characterised by the remnant fishponds to the south of the Shenzhen River and contains the important Mai Po Nature Reserve. This LCA is an important landscape within Hong Kong and as with LCA 1 is important in forming the landscape setting for the dense urban development to the north of the Shenzhen River. Given its importance to the landscape of the region it is considered to have a high sensitivity to change. 

 

LCA3 Lok Ma Chau Cross-border Infrastructure and Facilities Landscape

 

7.6.23            The Lok Ma Chau area is dominated by the structures associated with the border crossing including the vehicular crossing and the buildings and viaduct associated with the more recent East Rail Spur Line. The vehicular crossing is characterised by the extensive apron for waiting vehicles bounded by plantation woodland. The more modern railway crossing is characterised by the modernity of the building and the preserved and enhanced wetland areas (fishponds) to the south and west. This LCA is important as gateway to Hong Kong although the landscape quality of the vehicular crossing is degraded by its functional requirements. The railway crossing has given greater consideration to the landscape character of the area although the structures are still dominant within the LCA.   Given the level of existing development within this LCA it is considered to have a relatively low sensitivity to change. 

 

LCA4 Lok Ma Chau Lowland Rural Landscape

 

7.6.24            The landscape character of this area is shaped by a combination of the wooded hill slopes of the Lok Mau Chau ridgeline, the village settlement of Lok Ma Chau at the base of the ridgeline and its network of associated agricultural fields and fishpond areas; and the large expanse of the grassland formed within the abandoned meander of the Shenzhen River. In a sense this area forms a representation of the landscape of the rural NWNT in microcosm. Given the nature of the rural landscape in this area together with the relative degradation formed by the reclamation of the fishponds within the reclaimed area it is considered to have a medium sensitivity to further change.

 

LCA5 Sam Po Shue Lowland Rural Landscape

 

7.6.25            This LCA is characterised by a combination of the lower hill slopes Tai Shek Mo with the grassland of the higher elevations giving way to shrubland and wooded lower hill slopes;   the village settlement of Shun Yee San Tsuen located in a valley; and the extensive active and abandoned fishponds to the north and west. The fishponds in this LCA are more organically shaped than those of the previous areas described above. The main concentrations of abandoned fishponds are located through the central portion of the LCA and these have reverted to grassland with the active areas located around the periphery. There is also a relatively large area of plantation woodland to the east of the LCA to the north of the village settlement of Liu Pok.  Despite the abandonment of some of the fishpond areas this LCA is considered to have a high sensitivity to further change.

  

LCA6 Lo Wu Cross-border Infrastructure and Facilities Landscape

 

7.6.26            The landscape character of this area is formed by a combination of the wooded hill slopes of the Tai Shek Mo and the knoll of Seung Ma Lei Yue to the south and west; the flat agricultural land on the valley floor on the western bank of the Ng Tung River; and the channelized river course lined to the east by the infrastructure associated with the East Rail Line and the crossing facilities at Lo Wu. It is landscape characterised by the contrast between the naturalistic landscape to the west and the man-made landscapes to the east. Given the level of existing development on the valley floor this LCA is considered to have a low sensitivity to further change.  

 

LCA7 Sandy Range Hillside Landscape

 

7.6.27           This LCA is largely formed by the main northeast - southwest orientation of the Sandy Ridge upland area with its combination of plantation and secondary woodland to the east and west and the more upland nature of the central portion of the uplands. The uplands bound the southern bank of the channelized Shenzhen River with some reclaimed grassland areas forming the former footprint of the natural river course in the central and eastern portions of the river frontage. This LCA is considered to have a high sensitivity to change.

 

LCA8 Man Kam To Cross-border Infrastructure and Facilities Landscape

 

7.6.28         The landscape of this area, located between Man Kam To Road and the Ta Kwu Ling Village, is one characterised by the level of human disturbance with the lower, wooded hill slopes of Lo Shue Ling giving way to the extensive development associated with the border crossing bounded by plantation woodland; a central portion containing the village settlements of  Muk Wu and Muk Wu Nga Yiu; and the eastern portion with the security development flanked by extensive areas of plantation and secondary woodland. The area is bounded to the north by the channelized course of the Shenzhen River. The western portion of the LCA is dominated by the development including the buildings and large concrete apron of the Man Kam To border crossing with some agricultural fields to the east associated with the village of Muk Wu. To the east the existing development is located within the woodland and largely screened from the adjacent landscape although it is visible from the upland area to the south.  Given the level of development in this LCA it is considered to have a low sensitivity to change.

 

LCA9 North Ta Kwu Ling Lowland Rural Landscape

 

7.6.29         This LCA is characterised by a combination of the relatively open hill slopes of Lo Shue Ling to the east and the uplands Ta Kwo Ling to the west bisected by the valley of the now channelized Ping Yuen River and its tributaries. This landscape gives way to the north to a landscape characterised by the village settlements of Ta Kwu Ling Village, Kan Tau Wai and Kaw Liu Village on the lower hill lopes and narrow flat plain on the southern bank of the Shenzhen River.  The upper reaches of the river retain their natural form with series of meanders and organically shaped river banks. Small pockets of plantation and secondary woodland are located on the hill slopes in the western and eastern sections of the LCA.  This LCA is considered to have a medium sensitivity to change.

 

LCA10 Lin Ma Hang Hillside Landscape

 

7.6.30          The landscape of this area is characterised by a lowland landscape with the hills to the south of village of Tsung Yuen Ho in the western portion and the more extensive area of the lower hill slopes of the Lin Ma Hang mountain range in the eastern portion. In the central portion of the LCA is dominated by the grass and shrubland covered knoll of Pau Fu Shan. The area is crossed by the east – west orientated Lin Ma Hang Road. The main concentration of secondary mixed woodland is located to the west of Kaw Liu Village with an area of shrubland to the east of Pau Fu Shan.  The remainder of the area is covered with coarse grassland with areas of agricultural fields associated with the village settlements of Ha Heung Yuen, Heung Yuen Wai to the west and Lin Ma Hang to the east.   To ht eorth of the LCA a narrow river plain is bounded by the natural course of the Shenzhen River. Given the relatively undeveloped character of this area it is considered to have a medium sensitivity to change. 

 

 

LCA11 Shenzhen Liantang High-rise Residential Landscape

 

7.6.31           This LCA located to the north of the Shenzhen River has three main zones the eastern portion is characterised by a combination of the regimented rows of high and medium-rise, east – west orientated residential development flanked to the east by a scarred landscape of quarrying and major road development. The central portion of the LCA contains a light industrial area bounded to the north west by wooded hill slopes and the western portion is formed by a combination of a village settlement again bounded to the northwest by wooded hill sides and a large sewage treatment works which occupies the main flat are to the south of the village. This landscape is characterised by both modern and more traditional urban development and the extent of the infrastructure and utility works. Given the developed nature of this LCA it is considered to have a low sensitivity to change.   

 

LCA12 Shenzhen Wenjandu Port Infrastructure and Facilities Landscape

 

7.6.32          The landscape of this area is dominated by the infrastructural development of the Shenzhen Wenjandu Port, the counterpart to the crossing facilities at Man Kam To. This includes an extensive road network which passes through the LCA on a northeast – southwest orientation, the rectilinear form of an industrial area in the eastern portion, large areas of hard standing and storage facilities in the central portion and pockets of high-rise commercial development to the west. The main concentrations of existing vegetation include a landscape buffer of amenity tree and shrub planting on the southern side of the main east –west road and a semi-circular park to the south of the LCA. The area is bounded to the south by the meandering form of the Shenzhen River and to the north by the dense urban development of metropolitan Shenzhen. Given the level of development within this LCA it is considered to have a low sensitivity to change. 

 

LCA13 Shenzhen Lo Wu Cross-border Infrastructure  and Facilities

 

7.6.33          This LCA is characterised by a landscape of high-rise residential and commercial development in the eastern portion; the development associated with the Shenzhen Lo Wu border crossing in the central portion with its extensive infrastructure, apron for approaching vehicles and associated government buildings and an organically shaped residential settlement in the western portion.  The main concentrations of vegetation are located on the banks of the Shenzhen River in the central portion and the wooded hill slopes of knoll which separates the border crossing facilities from the adjacent residential area. The LCA is again bounded to the south by the Shenzhen River and to the north by a combination of high and medium rise residential development and areas of high-rise commercial development. Given the developed nature of this LCA it is considered to have a low sensitivity to change.  

 

LCA14 Shenzhen Huanggang Cross-border Infrastructure and Facilities Landscape

 

7.6.34          The landscape of this area has two distinct characters. The first to the northeast is dominated by high-rise residential development which extends in a grid-like form to the banks of the channelized banks of the Shenzhen River. The second character is that of the facilities associated with the Shenzhen Huanggang, the counterpart to the Lok Mau Chau crossing, with its road development and extensive apron areas for the processing of cross border traffic. To the west the crossing is flanked by a small parcel of high-rise residential development designed on spiral layout. The main concentrations of vegetation include amenity tree and shrub planting lining the riverfront adjacent to the residential area in the eastern portion of the LCA and a landscape buffer from tree and shrub planting adjacent to the hard standing and major infrastructure development associated with the border crossing. Given the level of development within this LCA it is considered to have a low sensitivity to change.   

 

LCA15 Shenzhen Futian Industrial Landscape

 

7.6.35          This LCA is dominated by the grid-like form of the Shenzhen Futian Industrial Area with its large rectilinear industrial buildings extending to the road on the river frontage. The shape of the industrial area mirrors that of the curing form of the channelised Shenzhen River to the south and extends north to the remainder of the industrial area and beyond to medium-rise residential development.  This is characterised by its lack of vegetation although there are some street trees at the central portion of the river frontage and lining the intersecting road to the north. Given the level of industrial development within this LCA and its lack of landscape resources it is considered to have a low sensitivity to change.   

 

LCA16 Sha Tau Kok Rural Landscape

 

7.6.36          The landscape of this area is one formed by three distinct areas. The first is the coastal landscape of Starlet Inlet although in this portion of the LCA it is dominated by the structures associated with the sewage treatment works. The second area located to the east is the medium-rise residential development of Sha Tau Kok Tsuen and Shun Lung Street. The third area, located to the west of Sha Tau Kok Road – Sha Mo Road are the lower, wooded slopes of the foothills of the natural uplands of the Robin’s Nest – Hung Fa Chai range of mountains.  The main concentrations of vegetation in LCA are the mixed woodland, shrub and grassland of the foothills to the west and the open spaces and waterfront promenade associated with the residential areas to the east.  Despite the location of the sewage treatment works this LCA is considered to a medium level of sensitivity to change. 

 

7.6.37          Table 7-5 provides an assessment of the sensitivity of the identified LCAs to change.

 


Table 75     Landscape Character Areas and their Sensitivity to Change

ID. No.

Landscape Character Area

(LCA)

Quality of Landscape Character

(High /  Medium / Low)

Importance and Rarity

(High / Medium / Low)

Ability to accommodate Change

(High / Medium / Low)

Local Significance of Potential Change

(High / Medium / Low)

Regional Significance of Potential Change

(High / Medium / Low)

Sensitivity to Change

(High / Medium / Low)

LCA1

Tam Kon Chau Lowland Rural Landscape

High

High

Low

High

High

High

LCA2

Mai Po Lowland Rural Landscape

High

High

Low

High

High

High

LCA3

Lok Ma Chau Cross-border Infrastructure and Facilities Landscape

Low

Low

High

Low

Low

Low

LCA4

Lok Ma Chau Lowland Rural Landscape

Medium

Medium

Medium

Medium

Medium

Medium

LCA5

Sam Po Shue Lowland Rural Landscape

High

Medium

High

High

Medium

High

LCA6

Lo Wu Cross-border Infrastructure and Facilities Landscape

Low

Low

High

Low

Low

Low

LCA7

Sandy Range Hillside Landscape

High

High

Low

High

Medium

High

LCA8

Man Kam To Cross-border Infrastructure and Facilities Landscape

Low

Low

High

Low

Low

Low

LCA9

North Ta Kwu Ling Lowland Rural Landscape

Medium

Medium

Medium

High

Medium

Medium

LCA10

Lin Ma Hang Hillside Landscape

High

High

Low

High

Medium

Medium

LCA11

Shenzhen Liantang High-rise Residential Landscape

Low

Low

High

Low

Low

Low

LCA12

Shenzhen Wenjandu Port Infrastructure and Facilities Landscape

Low

Low

High

Low

Low

Low

LCA13

Shenzhen Lo Wu Cross-border Infrastructure and Facilities Landscape

Low

Low

High

Low

Low

Low

LCA14

Shenzhen Huanggang Cross-border Infrastructure and Facilities Landscape

Low

Low

High

Low

Low

Low

LCA15

Shenzhen Futian Industrial Landscape

Low

Low

High

Low

Low

Low

LCA16

Sha Tau Kok Rural Landscape

 

Medium

Medium

Medium

Medium

Medium

Medium

 


7.7                   Existing Visual Context

 

Visual Envelope

 

7.7.1              The Visual Envelope (VE), the area from which the proposed works associated with the Secondary Boundary Fence would be visible is largely limited to a relatively narrow corridor following the alignment of the fence with the exception of the flat expanse of the fishponds located between the Ha Wan Tsuen in the west and Liu Pok in the east. The VE is described according to each f the four sections of the proposed scheme.

 

Section 1 – Mai Po to Lok Ma Chau Control Point

 

7.7.2              The VE for this section is largely limited to a relatively narrow corridor following the alignment of the fence through the fishponds adjacent to Mai Po and Sam Po Shue. Visibility is restricted due to the existing vegetation on the bunds between the fishponds and wetland areas and the flat nature of the topography.

 

Section 2 – Lok Ma Chau Control Point to Ng Tung River

 

7.7.3              The VE for this section extends to the uplands of the Fung Kong Shan - Tai Shek Mo range of mountains, Sandy Ridge and Lo Shue Ling with visibility extending inland through the valleys which bisect the upland areas including that at Lok Ma Chau, the Ng Tung River valley. There are panoramic views across the flat expanse of the fishponds which are he main landscape feature of this area although pockets of tree planting and tall grass / reed growth  on the bunds between the fishponds limit views in some locations. The VE extends to the high-rise development on the north western bank of the Shenzhen River. 

 

Section 3 – Ng Tung River to Lin Ma Hang Village

           

7.7.4              The VE for this section of the proposed SBF again forms a narrow corridor on either side of the alignment. It extends south east to the combined form of the uplands of the and the foothills of Wong Mau Hang Shan and includes the agricultural areas of Man Kam To and the Ping Yuen River valley are largely screened beyond the flat agricultural plain by the intervening vegetation and village development. Views are screened in some locations by existing tree growth particularly around the village settlements and the existing topography such as the knoll at Pok Fu Shan. Views from Shenzhen to the north are largely limited to the development immediately adjacent to the northern bank of the Shenzhen River.

 

 

Section 4 – Lin Ma Hang Village to Sha Tau Kok

 

7.7.5              The VE for the Section 4 of the proposals at Sha Tau Kok are largely limited by the village developments and the intervening vegetation associated with Hai Tam Shui Hang and Shan Tsui to the north and by the development lining Sha Tau Kok Road to the east.

 

7.7.6              The extent of the visual envelope and the locations of the identified VSRs is indicated on Figures 7-6A to B and Figures 7-6C to G provide an indication of the visual context.

 

 

Visual Sensitive Receivers

 

7.7.7          VSRs identified within the VE are grouped by according to village settlements, residential and industrial developments, vehicle travellers and staff of the border crossing facilities whom have a view of the proposed works associated with the Secondary Boundary Fence. Despite the relatively long length of the proposals the Study Area has a relatively low level of development due to security consideration and so the identified VSRs are limited to existing village settlements, the residents of high-rise developments lining the Shenzhen River and the main road and rail infrastructure at the border crossing points. Views from the north are limited due to a combination of the scale of the proposals and the viewing distances involved. The selected VSRs are representative of the views available to people at each location for the four sections of the proposals and include the following:

 

Section 1 – Mai Po to Lok Ma Chau Control Point

 

VSR1:              Residents of Tam Kon Chau Village Settlement 

VSR2:              Residents of Sam Po Shue Village Settlement / Planned Development on OU (Comprehensive Development and Wetland Enhancement Area) 

VSR3:              Travellers and Staff at Lo Ma Chau Cross-border Infrastructure Facilities

VSR4:              Residents of Ha Wan Tseun Village Settlement

 

Section 2 – Lok Ma Chau Control Point to Ng Tung River

 

VSR5:              Residents of Lok Ma Chau Village Settlement   

VSR6:              Residents of Shun Yee San Tsuen Village Settlement   

VSR7:              Residents of Tak Yuet Lau Tsuen Village Settlement    

VSR8:              Travellers and Staff at Lo Wo Cross-border Infrastructure Facilities

OVSR19:         Staff working in Shenzhen Futian Industrial Area

PVSR 20:         Staff working in the future Development at the Lok Ma Chau Loop

 

Section 3 – Ng Tung River to Lin Ma Hang Village

 

VSR9:              Residents of Lo Wo Village Settlement   

VSR10:            Travellers and Staff at Man Kam To Cross-border Infrastructure Facilities

VSR11:            Residents of Ta Kwu Ling Village Settlement   

VSR12:            Residents of Kaw Liu Village Settlement   

VSR13:            Residents of Village Settlement along Lin Ma Hang Road  

VSR14:            Residents of Lin Ma Hang Village Settlement

OVSR18:         Residents of Shenzhen Liantang High-rise Development      

PVSR 20:         Staff working in the future Development at the Lok Ma Chau Loop

VSR 21:           Residents of Chuk Yuen

VSR 22:           Residents of Tsung Yuen Ha

 

Section 4 – Lin Ma Hang Village to Sha Tau Kok 

 

VSR15:            Residents of Sha Tau Kok Tsuen Village Settlement   

VSR16:            Residents of Tam Shui Hang Village Settlement   

VSR17:            Residents of Shan Tsui Village Settlement   

VSR 23:           Residents of Kong Ha

 

 

7.7.8             Table 7-6 below determines the sensitivity of selected VSRs within the VE to accommodate change.


Table 76     Visually Sensitive Receivers (VSRs) and their Sensitivity to Change

 

ID. No.

Key Visually Sensitive Receivers (VSRs)

/ Viewing Distance

Type of

VSRs

Population of Viewers

(Large / Intermediate / Few / Very Few)

Quality of Existing View

(Good / Fair / Poor)

Amenity of Alternative Views

(Good / Fair / Poor)

Direction of Main  Views / Availability of Alternative Views

(Yes/ No)

Degree of Visibility

(Full / Partial / Glimpsed)

Frequency of View

(Very Frequent/ Frequent/ Occasional / Rare)

Sensitivity to Change

(Low / Medium /  High)

Section 1 – Mai Po to Lok Ma Chau Control Point

VSR 1

Residents of Tam Kon Chau Village Settlement  / 15m

Residential

Few

Good to fair

Good

Northeast / Yes

Partial

Frequent

High

VSR 2

Residents of Sam Po Shue Village Settlement  / Planned Development on OU (Comprehensive Development and Wetland Enhancement Area) / 50m  

Residential

Few

Good to fair

Good

Northwest / Yes

Partial

Frequent

High

VSR 3

Travellers and Staff at Lok Ma Chau Cross-border Infrastructure Facilities / 20m

Vehicle travellers and Staff

Large

Poor

Fair

North and south / Yes

Partial

Frequent

Low

VSR 4

Residents of Ha Wan Tseun Village Settlement / 20m

Residential

Few

Good to fair

Fair

East to Northeast / Yes

Partial

Frequent

High

Section 2 – Lok Ma Chau Control Point to Ng Tung River

VSR 5

Residents of Lok Ma Chau Village Settlement / 80m

Residential

Few

Good to fair

Good

North to Northeast / Yes

Partial

Frequent

High

VSR 6

Residents of Shun Yee San Tsuen Village Settlement / 30m

Residential

Few

Good to fair

Good

Northeast / Yes

Full

Frequent

High

VSR 7

Residents of Tak Yuet Lau Tsuen Village Settlement / 20m

Residential

Few

Good to fair

Good

North / Yes

Full

Frequent

High

VSR 8

Travellers and Staff at Lo Wo Cross-border Infrastructure Facilities / 20m

Vehicle travellers and Staff

Large

Poor

Fair to poor

North and south / Yes

Partial

Frequent

Low

OVSR 19

Staff working in Shenzhen Futian Industrial Area /

200m to new fence

Factory workers

Intermediate

Good to Fair

Fair

South / Yes

Partial

Frequent

Medium

PVSR20

Staff working in the future Development at the Lok Ma Chau Loop /

50m to new fence

Staff and Factory workers

Intermediate

Fair

Fair

North west / Yes

Partial

Frequent

Medium

Section 3 – Ng Tung River to Lin Ma Hang Village

VSR 9

Residents of Lo Wo Village Settlement  / 20m

Residential

Few

Good to fair

Good to fair

North / Yes

Partial

Frequent

High

VSR 10

Travellers and Staff at Man Kam To Cross-border Infrastructure Facilities / 130m

Vehicle travellers and Staff

Large

Poor

Poor

North and south / Yes

Partial

Frequent

Low

VSR 11

Residents of Ta Kwu Ling Village Settlement / 20m

Residential

Few

Good to fair

Good to fair

Northwest / Yes

Partial

Frequent

High

VSR 12

Residents of Kaw Liu Village Settlement / 20m  

Residential

Few

Good to fair

Good to fair

West / Yes

Partial

Frequent

High

VSR 13

Residents of Village Settlement along Lin Ma Hang Road  / 250m 

Residential

Few

Good to fair

Good to fair

Northeast / Yes

Partial

Frequent

High

VSR 14

Residents of Lin Ma Hang Village Settlement  /

20m to removal of existing fence / 150m to new fence 

Residential

Few

Good to fair

Good to fair

North / Yes

Partial

Frequent

High

OVSR 18

Residents of Shenzhen Liantang High-rise Development /

100m to new fence

 

Residential

Large

Good to fair

Good to fair

South / Yes

Partial

Frequent

High

VSR 21

Residents of Chuk Yuen /

150m to new fence

 

Residential

Few

Good to fair

Good

Northwest / Yes

Partial

Frequent

High

VSR 22

Residents of Tsung Yuen Ha / 200m to new fence

 

 

Residential

Few

Good to fair

Good

Northwest / Yes

Partial

Frequent

High

Section 4 – Lin Ma Hang Village to Sha Tau Kok

VSR 15

Residents of Sha Tau Kok Tsuen Village Settlement  / 90m to new fence

Residential

Few

Good to fair

Good to fair

West / Yes

Partial

Frequent

High

VSR 16

Residents of Tam Shui Hang Village Settlement /   

50m to new fence

Residential

Few

Good to fair

Good to fair

East / Yes

Partial

Frequent

High

VSR 17

Residents of Shan Tsui Village Settlement /

130m to new fence

Residential

Large

Good to fair

Good to fair

South / Yes

Partial

Frequent

High

VSR 23

Residents of Kong Ha  /

100m to new fence  

Residential

Few

Good to fair

Good to fair

West / Yes

Full

Frequent

High

 

 


7.8                   Landscape Impact Assessment

 

Sources of Landscape Impacts

 

7.8.1             The main landscape and visual impacts will be limited to the Boundary Fence corridor and will involve the loss of existing trees and some limited loss of landscape resources and a limited impact on the existing landscape character of the Study Area. Therefore it is considered that the proposed works with the successful implementation of the landscape mitigation measures will be relatively integrated with the local landscape character. Hence, there is no significant adverse impact to the existing landscape resources, character and amenity.

 

Construction Phase

 

7.8.2             During the construction phase, works will be limited to works boundary adjacent to the proposed alignment of the boundary fence. The proposed scheme will involve the erection of a new fence and construction of new boundary patrol road with the associated structures largely in the immediate vicinity of the existing fence alignment. The areas impacted by the proposals include:

 

Section 1 – Mai Po to Lok Ma Chau Control Point

 

(i)    The erection of the SBF along the existing BPR (approximately 4.1km); and

 

(ii)   The replacement of the existing checkpoint at Pak Hok Chau.       

 

Section 2 – Lok Ma Chau Control Point to Ng Tung River

 

(i)    The conversion of the existing Drainage Services Department maintenance services road along the Shenzhen River bank to the north of the Lok Ma Chau Loop and Hoo Hok Wai into a new section of the BPR (approximately 5.6km);

 

(ii)   The erection of the new PBF with the sensor alarm system and an SBF respectively along the northern and southern side of the converted road;

 

(iii)   The removal of the original PBF and the sensor alarm system thereon along the existing BPR south of the Lok Ma Chau Loop and Hoo Hok Wai; and

 

(iv)  The removal of the existing checkpoint at Lok Ma Chau Road.

 

Section 3 – Ng Tung River to Lin Ma Hang Village

 

(i)    The erection of an SBF along the existing BPR except the sections to the north of Pak Fu Shan and northwest of Lin Ma Hang Village (approximately 7.5km); 

 

(ii)   The construction of new sections of the BPR along the Shenzhen River side to the north of Pak Fu Shan and northwest of Lin Ma Hang Village without necessitating river training (approximately 4.0km);

 

(iii)   The erection of a new PBF with the sensor alarm system and an SBF along the northern and southern sides of the new sections of BPR respectively;

 

(iv)  The removal of the original PBF and the sensor alarm system thereon along the existing BPR near Pak Fu Shan and Lin Ma Hang Village; and

 

(v)   The removal of the existing checkpoints at Sha Ling and Ping Che.

 

Section 4 – Lin Ma Hang Village to Sha Tau Kok

 

(i)    The erection of an SBF from the entrance of the Sha Tau Kok town (i.e. the location of “Gate One”) to the Sha Tau Kok Control Point (approximately 0.5km);

 

(ii)   The provision of a new checkpoint at “Gate One”; and

 

(iii)   The removal of the existing checkpoint at Shek Chung Au.

 

7.8.3             Many of the potential impacts will arise from the visual intrusion caused by the actual work activities e.g. change of landscape amenity, exposure of earthworks for the new PBR and PBF, demolition works for some of the existing structures including the proposed checkpoint replacements, erection works for the new lengths of boundary fence superstructure and works traffic; and the construction activity associated with the replacement of existing checkpoints. Limited areas surrounding these proposed works will be also disturbed due to the temporary works areas and contractor’s compounds.

 

Operational Phase

 

7.8.4             The main impacts during the operational phase will be limited to the introduction of the new fence structures and the proposed lengths of PBR and BBR, and the replacement of check points. However given that the area already contains the boundary fence the potential impacts on the landscape resources and character of the Study Area are not considered to be significant. 

 

 


Table 77     Magnitude of Change for Landscape Resources

ID. No.

Landscape Resources

(Area affected)

Description of Impacts

Scale of the Development relative to Baseline Conditions

(Nil / Small / Medium / Large)

Compatibility of the Project with Landscape Resource

(Nil / Low / Medium / High)

Duration of Impacts

(Nil / Short / Medium / Long)

 

Reversibility of Change

(Yes / No /

Not Applicable)

Magnitude of Change

(Large / Intermediate / Small / Negligible)

Construction

Operational

LR 1

Cross border Infrastructure and Facilities

(14Ha)

Construction work will involve the new alignment for the PBR and PBF, and the replacement of some Check Points and associated facilities

Small

High

Construction

stage- short

Operation

stage- Nil

Not Applicable

Small

Small

LR2

Village Settlements

(0.16Ha

Area at the northern peripheries of  Lo Wu Village and Kwu Liu Village

Small

Medium

Construction

stage- nil

Operation

stage-nil

Not Applicable

Small

Small

LR3

Mixed Woodland

(0Ha)

No direct impact

Small

Low

Construction stage- nil

Operation stage-

nil

Not Applicable

Negligible

Negligible

LR4

Plantation Woodland

(3.2Ha)

Plantation woodland at embankment of existing border road at Tam Kon Chau and Sham Po Shue fishpond areas,  and area to west of Chuk Yuen.

Small

Low

Construction stage- nil

Operation stage-

Nil

Not Applicable

Small

Small

LR5

Shrubland

(0.02Ha)

Shrubland affected along existing boundary road and fence near Shun Yee San Tsuen .

Small

Low

Construction stage- nil

Operation stage-

Nil

Not Applicable

Small

Small

LR6

Grassland

(4.6Ha)

Grassland located near and around  Lo Wu,  Man Kam To, Ta Kwu Ling  village, Pau Fu Shan Lin Ma Heung village.

Small

Low

Construction stage- nil

Operation stage-

Nil

Not Applicable

Small

Small

LR7

Agricultural Fields

(0.015Ha)

Land affected at Shun Yee San Tsuen.

Small

Low

Construction stage- nil

Operation stage-

nil

Not Applicable

Small

Small

LR8

Fishponds

(0.1Ha )

Small area affected adjacent to existing border road Tam Kon Chau. No direct impact as the proposals will utilise existing DSD access roads and bunds and will not lead to the loss of fishponds.

Small

Low

Construction stage- nil

Operation stage-

nil

Not Applicable

Small

Small

LR9

Natural Stream Courses

(0Ha)

No direct impact

Small

Low

Construction stage- nil

Operation stage-

nil

Not Applicable

Negligible

Negligible

LR10

Modified Watercourse

(0.4Ha)

Small area of embankment affected of the Shenzhen River near Yuen Ling Chai. For other areas no direct impact although part of the SBF will be relocated to follow the course of the river in the central section.

Small

Low

Construction stage- nil

Operation stage-

nil

Not Applicable

Small

Small

LR11

Mangrove

(0Ha)

No direct impact

Small

Low

Construction stage- nil

Operation stage-

nil

Not Applicable

Negligible

Negligible

LR12

Marsh

(0Ha)

No direct impact

Small

Low

Construction stage- nil

Operation stage-

nil

Not Applicable

Negligible

Negligible

LR13

Developed Area

(0.6Ha)

Carpark adjacent to Shau Tau Kok Road

Small

Medium

Construction stage- nil

Operation stage-

nil

Not Applicable

Small

Small

 

 


Table 78     Magnitude of Change for Landscape Character Areas

ID. No.

Landscape Character Areas

Description of Impacts

Scale of the Development relative to Baseline Conditions

(Nil / Small / Medium / Large)

Compatibility of the Project with Landscape Character Area

(Nil / Low / Medium / High)

Duration of Impacts

(Nil / Short / Medium / Long)

 

Reversibility of Change

(Yes /  No /  Not Applicable)

Magnitude of Change

(Large / Intermediate / Small / Negligible)

Construction

Operational

LCA1

Tam Kon Chau Lowland Rural Landscape

Erection of new check point. Proposed SBF to follow the alignment of existing PBF.

Small

High

Construction stage- Short

Operation stage-

Nil

Yes

Small

Small

LCA2

Mai Po Lowland Rural Landscape

Proposed SBF to follow the alignment of existing PBF.

Medium

High

Construction stage- short

Operation stage- long

 

Yes

Small

Small

LCA3

Lok Ma Chau Cross-border Infrastructure and Facilities Landscape

 

 

Proposed SBF to follow the alignment of existing PBF.

Small

High

Construction stage- short

Operation stage- long

 

Yes

Small

Small

LCA4

Lok Ma Chau Lowland Rural Landscape

 

 

Proposed SBF to follow new alignment on the banks of the Shenzhen River and utilise existing DSD road for the BPR. Proposal balanced against enhancements arising from the removal of the existing fence alignment (Green Route)

Small

Medium

Construction stage- short

Operation stage- long

 

Yes

Small

Small

LCA5

Sam Po Shue Lowland Rural Landscape

 

 

 

Proposed SBF to follow new alignment on the banks of the Shenzhen River and utilise existing DSD road for the BPR. Proposal balanced against enhancements arising from the removal of the existing fence alignment (Green Route) . It is likely that the relocation of the fence will have a beneficial effect on the landscape character of this area.

Small

Medium

Construction stage- short

Operation stage- long

 

Yes

Small

Small

LCA6

Lo Wu Cross-border Infrastructure and Facilities Landscape

 

Proposed SBF to follow new alignment on the banks of the Shenzhen River and utilise existing DSD road for the BPR. Proposal balanced against enhancements arising from the removal of the existing fence alignment (Green Route)

Small

High

Construction stage- short

Operation stage- long

 

Yes

Small

Small

LCA7

Sandy Range Hillside Landscape

Construction of the SBR immediately adjacent to the PBF.

Small

Medium

Construction stage- short

Operation stage- long

 

Yes

Small

Small

LCA8

Man Kam To Cross-border Infrastructure and Facilities Landscape

 

Construction of the SBR immediately adjacent to the PBF.

Small

High

Construction stage- short

Operation stage- long

 

Yes

Small

Small

LCA9

North Ta Kwu Ling Lowland Rural Landscape

 

Construction of the SBR immediately adjacent to the PBF.

Small

Medium

Construction stage- short

Operation stage- long

 

Yes

Small

Small

LCA10

Lin Ma Hang Hillside Landscape

 

Proposed SBF to follow new alignment for two sections on the banks of the Shenzhen River and utilise existing DSD road for the BPR. Proposal balanced against enhancements arising from the removal of the existing fence alignment (Green Route). Remaining sections of the SBR fence follow the same alignment as PBF.

Small

Medium

Construction stage- short

Operation stage- long

 

Yes

Small

Small

LCA11

Shenzhen Liantang High-rise Residential Landscape

No direct impact

Small

High

Construction stage- Nil

Operation stage-

Nil

Yes

Small

Small

LCA12

Shenzhen Wenjandu Port Infrastructure and Facilities Landscape

No direct impact

Small

High

Construction stage- Nil

Operation stage-

Nil

Yes

Small

Small

LCA13

Shenzhen Lo Wu Cross-border Infrastructure and Facilities Landscape

No direct impact

Small

High

Construction stage- Nil

Operation stage-

Nil

Yes

Negligible

Negligible

LCA14

Shenzhen Huanggang Cross-border Infrastructure and Facilities Landscape

 

No direct impact

Small

High

Construction stage- Nil

Operation stage-

Nil

Yes

Negligible

Negligible

LCA15

Shenzhen Futian Industrial Landscape

No direct impact

Small

High

Construction stage- Nil

Operation stage-

Nil

Yes

Negligible

Negligible

LCA16

Sha Tau Kok Rural Landscape

 

Erection of SBF from the entrance of the Sha Tau Kok town (i.e. the location of “Gate One”) to the Sha Tau Kok Control Point (approximately 0.5km) following existing alignment. Replacement of Checkpoint at Shek Chung Au.  

 

Small

Medium

Construction stage- Short Operation stage-

Long

Yes

Small

Small

 


Table 79     Significance of Impacts on Landscape Resources in the Construction and Operational Phases

ID. No.

Landscape Resources

Sensitivity

(Nil / Small / Medium / Large)

Magnitude of Change

(Large/ Intermediate/ Small/ Negligible)

Significance Threshold

(Unmitigated)

(Negligible, Slight, Moderate and Significant)

Mitigation

Measures

(Refer to Tables

7-13 and 7-14)

Significance Threshold

(Mitigated)

(Negligible, Slight, Moderate and Significant)

Construc

-tion

Opera-

tional

Construction

Operational

Construction

Operational

LR 1

Cross border Infrastructure and Facilities

 

Low

Small

Small

Slight  adverse

Slight  adverse

CP1 to CP5 and OP1to OP4

Slight  adverse

Negligible

LR2

Village Settlements

 

Low

Small

Small

Slight  adverse

Slight  adverse

CP1 to CP5 and OP1to OP4

Slight  adverse

Negligible

LR3

Mixed Woodland

 

High

Negligible

Negligible

Negligible

Negligible

CP1 to CP5 and OP1to OP4

Negligible

Negligible

LR4

Plantation Woodland

 

Medium

Small

Small

Slight  adverse

Slight  adverse

CP1 to CP5 and OP1to OP4

Slight  adverse

Negligible

LR5

Shrubland

 

Medium

Small

Small

Slight  adverse

Slight  adverse

CP1 to CP5 and OP1to OP4

Slight  adverse

Negligible

LR6

Grassland

 

Medium

Small

Small

Slight  adverse

Slight  adverse

CP1 to CP5 and OP1to OP4

Slight  adverse

Negligible

LR7

Agricultural Fields

 

Medium

Small

Small

Slight  adverse

Slight  adverse

CP1 to CP5 and OP1to OP4

Slight  adverse

Negligible

LR8

Fishponds

 

High

Small

Small

Moderate  adverse

Moderate adverse

CP1 to CP5 and OP1to OP4

Moderate adverse

Slight adverse

LR9

Natural Stream Courses

 

High

Negligible

Negligible

Negligible

Negligible

CP1 to CP5 and OP1to OP4

Negligible

Negligible

LR10

Modified Watercourse

 

Medium

Small

Small

Slight  adverse

Slight  adverse

CP1 to CP5 and OP1to OP4

Slight  adverse

Negligible

LR11

Mangrove

 

High

Negligible

Negligible

Negligible

Negligible

CP1 to CP5 and OP1to OP4

Negligible

Negligible

LR12

Marsh

 

High

Negligible

Negligible

Negligible

Negligible

CP1 to CP5 and OP1to OP4

Negligible

Negligible

LR13

Developed Area

 

Low

Small

Small

Slight  adverse

Slight  adverse

CP1 to CP5 and OP1to OP4

Slight  adverse

Negligible

 

 


Table 710   Significance of Impacts on Landscape Character Areas in the Construction and Operational Phases

 

ID. No.

Landscape Character Areas

Sensitivity

(Nil / Small / Medium / High)

Magnitude of Change

(Large / Intermediate / Small / Negligible)

Significance Threshold

(Unmitigated)

(Negligible / Slight / Moderate / Significant)

Mitigation

Measures

(Refer to Tables

7-13 and 7-14)

Significance Threshold

(Mitigated)

(Negligible / Slight / Moderate / Significant)

Construction

Operational

Construction

Operational

Construction

Operational

LCA1

Tam Kon Chau Lowland Rural Landscape

High

Small

Small

Moderate

Moderate

CP1 to CP5

and OP1to OP4

Moderate

Slight

LCA2

Mai Po Lowland Rural Landscape

High

Small

Small

Moderate

Moderate

CP1 to CP5

and OP1to OP4

Moderate

Slight

LCA3

Lok Ma Chau Cross-border Infrastructure and Facilities Landscape

Low

Small

Small

Slight

Slight

CP1 to CP5

and OP1to OP4

Slight

Negligible

LCA4

Lok Ma Chau Lowland Rural Landscape

Medium

Small

Small

Slight

Slight

CP1 to CP5

and OP1to OP4

Slight

Negligible

LCA5

Sam Po Shue Lowland Rural Landscape

High

Small

Small

Moderate

Moderate

CP1 to CP5

and OP1to OP4

Moderate

Slight

LCA6

Lo Wu Cross-border Infrastructure and Facilities Landscape

Low

Small

Small

Slight

Slight

CP1 to CP5

and OP1to OP4

Slight

Negligible

LCA7

Sandy Range Hillside Landscape

High

Small

Small

Moderate

Moderate

CP1 to CP5

and OP1to OP4

Moderate

Slight

LCA8

Man Kam To Cross-border Infrastructure and Facilities Landscape

Low

Small

Small

Slight

Slight

CP1 to CP5

and OP1to OP4

Slight

Negligible

LCA9

North Ta Kwu Ling Lowland Rural Landscape

 

Medium

Small

Small

Slight

Slight

CP1 to CP5

and OP1to OP4

Slight

Negligible

LCA10

Lin Ma Hang Hillside Landscape

Medium

Small

Small

Slight

Slight

CP1 to CP5

and OP1to OP4

Slight

Negligible

LCA11

Shenzhen Liantang High-rise Residential Landscape

Low

Small

Small

Negligible

Negligible

OP1 and OP2

Negligible

Negligible

LCA12

Shenzhen Wenjandu Port Infrastructure and Facilities Landscape

Low

Small

Small

Negligible

Negligible

OP1 and OP2

Negligible

Negligible

LCA13

Shenzhen Lo Wu Cross-border Infrastructure and Facilities Landscape

Low

Negligible

Negligible

Negligible

Negligible

OP1 and OP2

Negligible

Negligible

LCA14

Shenzhen Huanggang Cross-border Infrastructure and Facilities Landscape

Low

Negligible

Negligible

Negligible

Negligible

OP1 and OP2

Negligible

Negligible

LCA15

Shenzhen Futian Industrial Landscape

Low

Negligible

Negligible

Negligible

Negligible

OP1 and OP2

Negligible

Negligible

LCA16

Sha Tau Kok Rural Landscape

 

Medium

Small

Small

Slight

Slight

CP1 to CP5

and OP1to OP4

Slight

Negligible

 

 

 

 


7.9                   Visual Impact Assessment

 

Source of Visual Impact

 

Construction Phase

 

7.9.1             Despite the relatively open nature of the landscape views towards the proposals are in many cases partially screened by the existing topography, vegetation and existing development, the presence of the existing fence and access road structures.  More open views are available from elevated locations and from areas to the north and west of the Shenzhen River although due to the viewing distances involved the proposed works will form a relatively minor component within the visual context of the identified VSRs. The potential impacts will be mitigated to an extent with the immediate reinstatement of works area and the new tree and shrub planting which will be located along the proposed alignment. Generally it is predicted that there will not be a significant adverse impact on the visual quality or amenity available to the identified VSRs.

 

7.9.2              There will be some low level views towards the works from the adjacent village settlements and residential developments although due to the flat nature of the landscape and the relative density of the development views will largely be limited to the properties on the edge of each settlement. The views from properties within each development will be limited to an extent by the form of the neighbouring houses on the periphery.

 

7.9.3              During the construction phase, works will be limited to a works boundary adjacent to the proposed alignment of the boundary fence. The proposed scheme will involve the erection of a new fence and construction of new boundary patrol road with the associated structures largely in the immediate vicinity of the existing fence alignment. The VSRs impacted by the proposals will include:

 

Section 1 – Mai Po to Lok Ma Chau Control Point

 

7.9.4              The main impacts will arise from the construction activity associated with the erection of the SBF along the existing BPR (approximately 4.1km). The replacement of the existing checkpoint at Pak Hok Chau will involve the replacement with a similarly sized structure. The main impacts will be apparent for residents of Tam Kon Chau (VSR 1), Residents of Sam Po Shue and the planned development on the adjacent area zoned OU (VSR 2), and residents of Ha Wan Tsuen (VSR 4) who will be subject to moderate adverse visual impacts during the construction phase due to the proximity of the works including the domilition of a section of the fence and its relocation to the north. Vehicle travellers and staff at the Lok Ma Chau border crossing (VSR 3) will be subject to slight adverse visual impacts due to the more restricted nature of the available views and the level of visual disturbance caused by the existing boundary and security facilities.

 

Section 2 – Lok Ma Chau Control Point to Ng Tung River

 

7.9.5              The main impacts will arise from the construction activity associated with the conversion of the existing Drainage Services Department maintenance services road along the Shenzhen River bank to the north of the Lok Ma Chau Loop and Hoo Hok Wai into a new section of the BPR (approximately 5.6km), and the erection of the new PBF and SBF respectively along the northern and southern side of the converted road. During the construction phase the residents of Lok Ma Chau (VSR 5), Shun Yee San Tsuen (VSR 6) and Tak Yuet Lau Tsuen (VSR 7) would be subject to moderate adverse impacts due to the relative proximity of the proposed construction works involved in the removal of the existing fence alignment. Vehicle travellers and staff at the Lo Wo border crossing (VSR 8) will be subject to slight adverse visual impacts due to the more restricted nature of the available views and the level of visual disturbance caused by the existing boundary and security facilities. Staff of the Shenzhen Futian Industrial Area (OVSR19) would experience a moderate adverse impact due to the construction of the proposed new closer fence alignment along the bank of the Shenzhen River which would disturb what is essentially a rural view. It is assumed that the development of the Lok Ma Chau Loop (PVSR 20) will take place following the construction of the works and so there will not be any construction phase impacts for this VSR.

 

Section 3 – Ng Tung River to Lin Ma Hang Village

 

7.9.6              The main impacts will arise from the construction activity associated with the erection of an SBF along the existing BPR except the sections to the north of Pak Fu Shan and northwest of Lin Ma Hang Village (approximately 7.5km) and the construction of new sections of the BPR along the Shenzhen River side to the north of Pak Fu Shan and northwest of Lin Ma Hang Village without necessitating river training (approximately 4.0km). Other lesser impacts will arise from the removal of the original PBF along the existing BPR near Pak Fu Shan and Lin Ma Hang Village and the removal of the existing checkpoints at Sha Ling and Ping Che. Due to the proximity of the proposed works to the existing village settlements on the valley floor the residents of Lo Wo Village (VSR9), Ta Kwu Ling Village (VSR11), Kaw Lui Village (VSR12), the settlement along Lin Ma Hang Road (VSR 13), the residents of Lin Ma Hang Village (VSR14), Chuk Yuen (VSR21) and Tsung Yuen Ha (VSR22) would be subject to a moderate adverse visual impact.  The residents of the high-rise development in Shenzhen Liantang (OVSR18) would also be subject to a moderate adverse due in part to the proximity of the proposed works and the elevated nature of the viewing position.  Vehicle travellers and staff at the Man Kam To border crossing (VSR 10) will be subject to slight adverse visual impacts due to the more restricted nature of the available views and the level of visual disturbance caused by the existing boundary and security facilities.     

 

Section 4 – Lin Ma Hang Village to Sha Tau Kok

 

7.9.7              The main impacts will arise from the construction activity associated with the erection of an SBF from the entrance of the Sha Tau Kok town (i.e. the location of “Gate One”) to the Sha Tau Kok Control Point (approximately 0.5km), the provision of a new checkpoint at “Gate One” and to a lesser extent the removal of the existing checkpoint at Shek Chung Au. However due to the proximity of the proposed works the construction impacts for the residents of Sha Tau Kok Tsuen (VSR15) and Tam Shui Hang Village Settlement (VSR16) are likely to be moderate adverse. Whereas due to the presence of the existing fence structure and the limited visibility of the proposed works due to the adjacent development and intervening vegetation the predicted impacts for the residents of Shan Tsui Village (VSR17) and Kong Ha (VSR23) will be slight adverse.

 

 

7.9.8              Many of the potential impacts will arise from the visual intrusion caused by the actual work activities e.g. change of landscape amenity, exposure of earthworks for the new PBR and PBF, demolition works for some of the existing structures including the proposed checkpoint replacements, erection works for the new lengths of boundary fence superstructure and works traffic; and the construction activity associated with the replacement of existing checkpoints. Limited areas surrounding these proposed works will be also disturbed due to the temporary works areas and contractor’s compounds.

 

7.9.9              The assessment contained in Table 7.12 concludes that for most VSRs the impacts will be limited to a moderate to slight adverse impact on visual amenity. The most significant impacts will be experienced by VSRs in close proximity to the proposed construction works including residents of the adjacent villages although for vehicle travellers and staff at the border crossings the views are restricted and characterised to an extent by the existing security structures. With the proposed mitigation measures including construction works control and the preservation of existing trees along the roadside it is anticipated that many of these impacts can be successfully mitigated during the construction period.

 

7.9.10           The recommended landscape mitigation measures and residual impact on these VSRs is further discussed in Table 7.12 and 7.13.

 

Operational Phase

 

7.9.11           Through a combination of the proposed realignment of sections of the PBR, PBF and SBF, and the planting of new trees and shrubs to break up the horizontal emphasis of the fence line the potential visual impact it is considered that the proposals will not have a significant impact on the existing visual amenity of the Study Area. The main impacts on the identified VSRs during the operational stage of the project are described below.

 

Section 1 – Mai Po to Lok Ma Chau Control Point

 

7.9.12           The main impacts will arise from the construction the presence of the SBF along the existing BPR (approximately 4.1km). The replacement of the existing checkpoint at Pak Hok Chau will involve the replacement with a similarly sized structure. The main impacts will be apparent for residents of Tam Kon Chau (VSR1) where the moderate adverse visual impact will persist into the operational phase of the project due to proximity of the proposals to the settlement and the lack of opportunities for mitigation measures. For residents of Sam Po Shue and the planned development on the adjacent area zoned OU (VSR2) the operational impacts will be slight adverse due to the effect of the proposed planting of trees and shrubs along the fence alignment. With the relocation of the fence alignment to the north the residents of Ha Wan Tsuen (VSR4) will be subject to more open views of the landscape to the north east and will therefore experience a moderate beneficial impact. Vehicle travellers and staff at the Lok Ma Chau border crossing (VSR3) will be subject to negligible level of impact due to the restricted nature of the existing views and the fact that the proposed scheme will be seen against backdrop of the existing fence alignment and security structures. 

 

 

 

 

 

Section 2 – Lok Ma Chau Control Point to Ng Tung River

 

7.9.13           The main impacts will arise from the relocation of the fence line to the river bank to the north of the Lok Ma Chau Loop and Hoo Hok Wai and the presence of the new PBF and SBF respectively along the northern and southern side of the converted road. The proposed realignment of the PBF and SBF would allow more open views of the surrounding landscape for the residents of Lok Ma Chau (VSR 5) and Shun Yee San Tsuen (VSR 6) who would be subject to a moderate beneficial impact during the operational stage of the project. These villages were located immediately adjacent to the existing alignment and so the proposals would realise a significant enhancement of existing views. The moderate adverse impact predicted during the construction phase for the staff of the Shenzhen Futian Industrial Area (OVSR19) would persist into the operational phase due to the visual intrusion caused by the new structure. The residents of Tak Yuet Lau Tsuen (VSR 7) would be subject to a slight adverse impact due to the proximity of the proposed fence alignment mitigated to ane extent by the proposed tree and shrub planting propodrf for the area to the south of the fence alignment. The potential impacts experienced by VSR 7 should be balanced to an extent by the enhancements realised through removal of the existing fence alignment in views to the south. Vehicle travellers and staff at the Lo Wo border crossing (VSR 8) will be subject to negligible residual impacts due to the more restricted nature of the available views and the level of visual disturbance caused by the existing boundary and security facilities. For the future workers and staff within the development of the Lok Ma Chau Loop (PVSR 21) the potential impacts arising from the proposed PBF and SBF alignment could be mitigated to an extent through the use of tree and shrub planting along the northern periphery of the development zone resulting in a light adverse level of impact. 

 

Section 3 – Ng Tung River to Lin Ma Hang Village

 

7.9.14           The main impacts will arise from the presence of the SBF along the existing BPR except the sections to the north of Pak Fu Shan and northwest of Lin Ma Hang Village (approximately 7.5km) and the new sections of the BPR along the Shenzhen River side to the north of Pak Fu Shan and northwest of Lin Ma Hang Village (approximately 4.0km). Other lesser impacts will arise from the removal of the original PBF along the existing BPR near Pak Fu Shan and Lin Ma Hang Village and the removal of the existing checkpoints at Sha Ling and Ping Che. Due to the proximity of the proposed works to the existing village settlements on the valley floor the residents of Lo Wo Village (VSR9), Ta Kwu Ling Village (VSR11), Kaw Lui Village (VSR12), Lin Ma Hang Village (VSR14), Chuk Yuen (VSR21) and Tsung Yuen Ha (VSR22) would be subject to a slight adverse residual impact mitigated to an extent through the planting of trees and shrubs along the proposed alignment.  Vehicle travellers and staff at the Man Kam To border crossing (VSR 10) will be subject to a negligible impact due to the more restricted nature of the available views and the level of visual disturbance caused by the existing boundary and security facilities. The moderate adverse impact predicted for the residents of the high-rise development in Shenzhen Liantang (OVSR18) would persist into the operational phase of the project due in part to the proximity of the proposed works and the elevated nature of the viewing position. With the proposed realignment of the PBF and SBF to the north and west, and the opening up of new views the residents of the settlement along Lin Ma Hang Road (VSR 13) would be subject to a moderate beneficial impact and Tsung Yuen Ha (VSR22) a slight beneficial impact.

 

Section 4 – Lin Ma Hang Village to Sha Tau Kok

 

7.9.15           The main impacts will arise from the presence of the SBF from the entrance of the Sha Tau Kok town (i.e. the location of “Gate One”) to the Sha Tau Kok Control Point (approximately 0.5km), and the provision of a new checkpoint at “Gate One”.  With the completion of the construction works and the growth proposed tree and shrub planting the predicted residual impacts for Sha Tau Kok Tsuen (VSR15), Tam Shui Hang Village Settlement (VSR16) and Shan Tsui Village (VSR17) would be slight adverse while for the residents of and Kong Ha (VSR23) the predicted impacts would be negligible.

 

 


Table 711   Magnitude of Change for Visually Sensitive Receivers

ID. No.

Visually Sensitive Receivers (VSRs)

/ Viewing

Distance

Description

of Impacts

Scale of the Development

relative to Baseline Conditions

(Nil / Small / Medium / Large)

Blockage of View

(Nil / Small, Medium / Large)

Compatibility of the Project with Existing Visual Amenity

(Nil / Low / Medium / High)

Duration of Impacts

(Nil / Short / Medium / Long)

 

Reversibility of Change

(Yes / No / Not Applicable)

Magnitude of Change

(Large / Intermediate / Small / Negligible)

Construction

Operational

Section 1 – Mai Po to Lok Ma Chau Control Point

VSR 1

Residents of Tam Kon Chau Village Settlement  / 15m

Erection of new check point. Proposed SBF to follow the alignment of existing PBF.

Medium

Small

High

Construction stage- Short

Operation stage-

Long

Yes

Intermediate

Small

VSR 2

Residents of Sam Po Shue Village Settlement  / Planned Development on OU (Comprehensive Development and Wetland Enhancement Area) / 50m  

Proposed SBF to follow the alignment of existing PBF.

Medium

Small

High

Construction stage- Short

Operation stage-

Long

Yes

Small

Small

VSR 3

Travellers and Staff at Lok Ma Chau Cross-border Infrastructure Facilities / 20m

Proposed SBF to follow the alignment of existing PBF.

Medium

Small

High

Construction stage- Short

Operation stage-

Long

Yes

Small

Small

VSR 4

Residents of Ha Wan Tseun Village Settlement / 20m

Proposed SBF to follow new alignment on the banks of the Shenzhen River and utilise existing DSD road for the BPR. Proposal balanced against enhancements arising from the removal of the existing fence alignment (Green Route)

Medium

Nil

High

Construction stage- Short

Operation stage-

Long

Yes

Intermediate

Intermediate

Section 2 – Lok Ma Chau Control Point to Ng Tung River

VSR 5

Residents of Lok Ma Chau Village Settlement / 80m

Proposed SBF to follow new alignment on the banks of the Shenzhen River and utilise existing DSD road for the BPR. Proposal balanced against enhancements arising from the removal of the existing fence alignment (Green Route)

 

Medium

Nil

Medium

Construction stage- Short

Operation stage-

Long

Yes

 

 

 

 

Intermediate

Intermediate

VSR 6

Residents of Shun Yee San Tsuen Village Settlement / 30m

Proposed SBF to follow new alignment on the banks of the Shenzhen River and utilise existing DSD road for the BPR. Proposal balanced against enhancements arising from the removal of the existing fence alignment (Green Route)

Medium

Nil

Medium

Construction stage- Short

Operation stage-

Long

Yes

Intermediate

Intermediate

VSR 7

Residents of Tak Yuet Lau Tsuen Village Settlement / 20m

Proposed SBF to follow new alignment on the banks of the Shenzhen River and utilise existing DSD road for the BPR. Proposal balanced against enhancements arising from the removal of the existing fence alignment (Green Route)

Medium

Medium

Low

Construction stage- Short

Operation stage-

Long

Yes

Intermediate

Small

VSR 8

Travellers and Staff at Lo Wo Cross-border Infrastructure Facilities / 20m

Construction of the SBF immediately adjacent to the PBF.

Medium

Small

High

Construction stage- Short

Operation stage-

Long

Yes

Small

Small

OVSR 19

Staff working in Shenzhen Futian Industrial Area /

200m to new fence

Proposed SBF to follow new alignment on the banks of the Shenzhen River and utilise existing DSD road for the BPR.

Medium

Small

Low

Construction stage- Short

Operation stage-

Long

Yes

Intermediate

Intermediate

PVSR20

Staff working in the future Development at the Lok Ma Chau Loop /

50m to new fence

Proposed SBF to follow new alignment on the banks of the Shenzhen River and utilise existing DSD road for the BPR.

Medium

Medium

High

Construction stage- N/A

Operation stage-

Long

Yes

N/A

Proposals constructed before the Lok Ma  Chau Development becomes operational

Intermediate

Section 3 – Ng Tung River to Lin Ma Hang Village

VSR 9

Residents of Lo Wo Village Settlement  / 20m

Construction of the SBF immediately adjacent to the PBF.

Medium

Medium

High

Construction stage- Short

Operation stage-

Long

Yes

Small

Small

VSR 10

Travellers and Staff at Man Kam To Cross-border Infrastructure Facilities / 130m

Construction of the SBF immediately adjacent to the PBF.

 

Medium

Small

High

Construction stage- Short

Operation stage-

Long

Yes

Small

Small

VSR 11

Residents of Ta Kwu Ling Village Settlement / 20m

Construction of the SBF immediately adjacent to the PBF.

Medium

Small

High

Construction stage- Short

Operation stage-

Long

Yes

Small

Small

VSR 12

Residents of Kaw Liu Village Settlement / 20m  

Construction of the SBF immediately adjacent to the PBF.

Medium

Small

High

Construction stage- Short

Operation stage-

Long

Yes

Small

Small

VSR 13

Residents of Village Settlement along Lin Ma Hang Road  / 250m 

Proposed SBF to follow new alignment on the banks of the Shenzhen River and utilise existing DSD road for the BPR. Proposal balanced against enhancements arising from the removal of the existing fence alignment (Green Route)

Medium

Nil

High

Construction stage- Short

Operation stage-

Long

Yes

Intermediate

Intermediate

VSR 14

Residents of Lin Ma Hang Village Settlement  /

20m to removal of existing fence / 150m to new fence

Construction of the SBF immediately adjacent to the PBF.

Medium

Small

High

Construction stage- Short

Operation stage-

Long

Yes

Small

Small

OVSR 18

Residents of Shenzhen Liantang High-rise Development /

100m to new fence

 

Construction of the SBF immediately adjacent to the PBF.

Medium

Small

High

Construction stage- Short

Operation stage-

Short

Yes

Small

Small

VSR 21

Residents of Chuk Yuen /

150m to new fence

 

Proposed SBF to follow new alignment on the banks of the Shenzhen River and utilise existing DSD road for the BPR.

Medium

Nil

High

Construction stage- Short

Operation stage-

Long

Yes

Small

Small

VSR 22

Residents of Tsung Yuen Ha / 200m to new fence

 

Proposed SBF to follow new alignment on the banks of the Shenzhen River and utilise existing DSD road for the BPR. Proposal balanced against enhancements arising from the removal of the existing fence alignment (Green Route)

 

Medium

Small

High

Construction stage- Short

Operation stage-

Long

Yes

Small

Small

Section 4 – Lin Ma Hang Village to Sha Tau Kok

VSR 15

Residents of Sha Tau Kok Tsuen Village Settlement  / 90m to new fence

Construction of the SBF immediately adjacent to the PBF.

Medium

Medium

Medium

Construction stage- Short

Operation stage-

Long

Yes

Intermediate

Intermediate

VSR 16

Residents of Tam Shui Hang Village Settlement /   

50m to new fence

Construction of the SBF immediately adjacent to the PBF.

Medium

Medium

Medium

Construction stage- Short

Operation stage-

Long

Yes

Intermediate

Intermediate

VSR 17

Residents of Shan Tsui Village Settlement /

130m to new fence

Construction of the SBF immediately adjacent to the PBF. 

Medium

Small

Medium

Construction stage- Short

Operation stage-

Long

Yes

Small

Small

VSR 23

Residents of Kong Ha  /

100m to new fence  

Construction of the SBF immediately adjacent to the PBF.

Small

Small

Medium

Construction stage- Short

Operation stage-

Long

Yes

Small

Small

 


Table 712   Significance of Impacts on Visually Sensitive Receivers in the Construction and Operational Phases

ID. No.

Visually Sensitive Receivers

Sensitivity

(Nil / Small / Medium / Large)

Magnitude of Change

(Large / Intermediate / Small / Negligible)

Significance Threshold

(Unmitigated)

(Negligible / Slight / Moderate /  Significant)

Mitigation

Measures

(Refer to Tables

7-13 and 7-14)

Significance Threshold

(Mitigated)

(Negligible / Slight / Moderate / Significant)

Construction

Operational

Construction

Operational

Construction

Operational

Section 1 – Mai Po to Lok Ma Chau Control Point

 

VSR 1

Residents of Tam Kon Chau Village Settlement 

High

Intermediate

Small

Moderate adverse

Moderate adverse

CP1 to CP5 and OP1to OP4

Moderate adverse

Moderate adverse

VSR 2

Residents of Sam Po Shue Village Settlement / Planned Development on OU (Comprehensive Development and Wetland Enhancement Area)  

High

Small

Small

Moderate adverse

Moderate adverse

CP1 to CP5 and OP1to OP4

Moderate adverse

Slight adverse

VSR 3

Travellers and Staff at Lok Ma Chau Cross-border Infrastructure Facilities

Low

Small

Small

Slight adverse

Slight adverse

CP1 to CP5 and OP1to OP4

Slight adverse

Negligible

VSR 4

Residents of Ha Wan Tseun Village Settlement   

High

Intermediate

Intermediate

Moderate adverse

Moderate beneficial

CP1 to CP5 and OP1to OP4

Moderate adverse

Moderate beneficial

Section 2 – Lok Ma Chau Control Point to Ng Tung River

VSR 5

Residents of Lok Ma Chau Village Settlement

High

Intermediate

Intermediate

Moderate adverse

Moderate beneficial

CP1 to CP5 and OP1to OP4

Moderate adverse

Moderate beneficial

VSR 6

Residents of Shun Yee San Tsuen Village Settlement

High

Intermediate

Intermediate

Moderate adverse

Moderate beneficial

CP1 to CP5 and OP1to OP4

Moderate adverse

Moderate beneficial

VSR 7

Residents of Tak Yuet Lau Tsuen Village Settlement   

High

Intermediate

Small

Moderate adverse

Moderate adverse

CP1 to CP5 and OP1to OP4

Moderate adverse

Slight

adverse

VSR 8

Travellers and Staff at Lo Wo Cross-border Infrastructure Facilities

Low

Small

Small

Slight adverse

Negligible

CP1 to CP5 and OP1to OP4

Slight adverse

Negligible

OVSR 19

Staff working in Shenzhen Futian Industrial Area

Medium

Intermediate

Intermediate

Moderate adverse

Moderate adverse

CP1 to CP5 and OP1to OP4

Moderate adverse

Moderate adverse

PVSR20

Staff working in the future Development at the Lok Ma Chau Loop

Medium

N/A

Intermediate

N/A

Moderate adverse

CP1 to CP5 and OP1to OP4

N/A

Slight adverse

Section 3 – Ng Tung River to Lin Ma Hang Village

VSR 9

Residents of Lo Wo Village Settlement   

High

Small

Small

Moderate adverse

Moderate adverse

CP1 to CP5 and OP1to OP4

Moderate adverse

Slight adverse

VSR 10

Travellers and Staff at Man Kam To Cross-border Infrastructure Facilities.

Low

Small

Small

Slight adverse

Slight adverse

CP1 to CP5 and OP1to OP4

Slight adverse

Negligible

VSR 11

Residents of Ta Kwu Ling Village Settlement   

High

Small

Small

Moderate adverse

Moderate adverse

CP1 to CP5 and OP1to OP4

Moderate adverse

Slight adverse

VSR 12

Residents of Kaw Liu Village Settlement   

High

Small

Small

Moderate adverse

Moderate adverse

CP1 to CP5 and OP1to OP4

Moderate adverse

Slight adverse

VSR 13

Residents of Village Settlement along Lin Ma Hang Road  

High

Intermediate

Intermediate

Moderate adverse

Moderate beneficial

CP1 to CP5 and OP1to OP4

Moderate adverse

Moderate beneficial

VSR 14

Residents of Lin Ma Hang Village Settlement   

High

Small

Small

Moderate adverse

Moderate adverse

CP1 to CP5 and OP1to OP4

Moderate adverse

Slight adverse

OVSR 18

Residents of Shenzhen Liantang High-rise Development   

High

Small

Small

Moderate adverse

Moderate adverse

CP1 to CP5 and OP1to OP4

Moderate adverse

Moderate adverse

 

 

 

 

 

 

 

 

 

 

VSR 21

Residents of Chuk Yuen

High

Small

Small

Moderate adverse

Moderate adverse

CP1 to CP5 and OP1to OP4

Moderate adverse

Slight adverse

VSR 22

Residents of Tsung Yuen Ha

High

Small

Small

Moderate adverse

Slight beneficial

CP1 to CP5 and OP1to OP4

Moderate adverse

Slight beneficial

Section 4 – Lin Ma Hang Village to Sha Tau Kok

VSR 15

Residents of Sha Tau Kok Tsuen Village Settlement   

High

Intermediate

Intermediate

Moderate adverse

Moderate adverse

CP1 to CP5 and OP1to OP4

Moderate adverse

Slight adverse

VSR 16

Residents of Tam Shui Hang Village Settlement   

High

Intermediate

Intermediate

Moderate adverse

Moderate adverse

CP1 to CP5 and OP1to OP4

Moderate adverse

Slight adverse

VSR 17

Residents of Shan Tsui Village Settlement   

High

Small

Small

Slight adverse

Slight adverse

CP1 to CP5 and OP1to OP4

Slight adverse

Slight adverse

VSR 23

Residents of Kong Ha

High

Small

Small

Slight adverse

Negligible

CP1 to CP5 and OP1to OP4

Slight adverse

Negligible

 


7.10               Cumulative Impacts

 

7.10.1           A number of projects are currently in progress or planned within the Study Area, which will result in landscape and visual impact during the degradation of landscape character and visual amenity, and loss of landscape resources. These planned projects include:

 

Ÿ                     Proposed New Wave Wall / Modification to Existing Wave Wall in Section 2 - The works in Section 2 will have interface with DSD’s proposed modification of the existing wave and construction of a new wave wall alongside the Shenzhen River.  Liaison with DSD is on-going to resolve the interface problem and entrustment approach may be adopted.  Current construction programme for the construction of boundary fences in Section 2 has already taken the potentially entrustment works from DSD into account. With good coordination between the two projects potential cumulative landscape and visual impacts can be minimised.

 

Ÿ                     Liantang / Heung Yuen Wai Boundary Control Point in Section 3 - A new Boundary Control Point (BCP) is proposed at Heung Yuen Wai.  Civil Engineering and Development Department confirmed Section 3 will be completed at end 2012 before the commencement of the proposed BCP.  Therefore it is not anticipated that there will be any significant cumulative landscape and visual impacts. 

 

Ÿ                     Advanced Works for River Training in Section 3 - In association with the proposed BCP at Heung Yuen Wai, Drainage Service Department (DSD) will carry out advanced works for the river training works from Ping Yuen River to Pak Fu Shan.  DSD have confirmed that these works would commence in mid 2012 and the actual extent of the works confirmed after a study at the end 2009.  Since the advanced works would involve realignment of the existing boundary patrol road there may be some conflict with the Secondary Boundary Fence (SBF) alignment.  It is proposed to provide the SBF under DSD’s advance works.  In turn, the proposed works from Ping Yuen River to Pak Fu Shan Project would be excised from this Project. The coordination of the two projects would minimise the potential landscape and visual impacts. 

 

7.10.2           Mitigation measures to address landscape and visual impact have been incorporated into the design of each of the approved projects. It is envisaged that that although some aspects of the works will be concurrent with careful coordination any potential cumulative landscape and visual impacts can be minimised.

 

7.10.3           There are no other planned projects within the Study Area and so there will be no cumulative impact to the Landscape Resources and Landscape Character, and the visual amenity enjoyed by adjacent VSRs.

 

7.11               Recommended Mitigation Measures

 

7.11.1           The landscape mitigation measures described in this report are at a level which both demonstrates their ability to alleviate the potential landscape and visual impacts identified in the assessment and also to allow the proposals to be carried forward during the detailed design stage. The measures are designed to address both the construction and operational phases of the project. A more detailed landscape and compensatory planting proposals will be developed at a later stage during detailed design and construction phase of this project following the completion of the detailed Tree Survey Report. The tree survey report and the proposed strategy for the treatment of the existing trees will be submitted to the relevant departments for approval at that stage.

 

7.11.2           The landscape and visual mitigation measures are described both in a generic sense for measures, which apply to all of works area and in terms of the proposed landscape strategy for the roadside planting and amenity areas alongside of the boundary fence.  The aim of the mitigation measures is to:

 

·         Alleviate where possible those landscape and visual impacts which are unavoidable through the review of fence and patrol road alignment.

·         Establish a coherent and integrated landscape framework for the proposed works drawing together the visually disparate components if any of the proposed works. However given the limited land acquisition designed to minimise the impact on the existing fishponds and wetlands which have a high ecological value and requirements for clearance requirement alongside of boundary fence for security reasons there will be limited opportunities for new tree and shrub planting. Although there may be opportunities for off-site planting of woodland clumps and small tree groups to break up the horizontality of the fence alignment.  

·         Enhance the existing landscape and visual context of the surrounding areas providing integration between the proposed works and its context. 

·         Provide a co-ordinated approach between the ecological and landscape mitigation proposals where there is an interface.

 

7.11.3           Figures 7-8A to 7-8D have mapped the main landscape and visual mitigation strategies and the application of design mitigation measures including integrated design approach, compensatory and new planting proposals. Application of the recommended mitigation measures including treatment of boundary fence are presented in Figures 7-9A to 7-9M Photomontages. 

 

7.11.4           It is recommended that the Environmental, Monitoring and Audit Requirements (EM&A) for landscape and visual resources described in Section 10 of this report is undertaken during both the construction and operational phases of the Project.  

 

General Mitigation Measures

 

7.11.5           In accordance with the EIAO-TM, the hierarchy for landscape and visual impact mitigation is first avoidance of impact, then minimisation of impact and finally compensation of impact.  As has been described in the Project description in this report, the current proposals have been undertaken to fulfil the following objectives:

 

·         Minimisation of potential impacts on landscape resources such as watercourses and existing trees by review the alignment and location of check point facilities through preserving wooded knolls including those adjacent at Ma Tso Lung, Sandy Ridge and Lin Ma Hang, avoid impact to the Mai Po SSSI and the fishponds with high ecological value at Sham Po Shue.

·         Restoration and enhancement of existing rural landscapes through the planting of trees, where the space and security concerns allow, following the completion of the construction phase of the project. This will help to reduce the horizontal emphasis of the fence alignment and integrate it within its landscape context.

·         Review the site area for the proposed fence and patrol road to ensure that sufficient space is reserved for compensatory planting and other landscape works.

·         Carefully locate the proposed check point and associated structures to minimise the potential ecological, visual and landscape impacts.

 

7.11.6           In accordance with the EIAO-TM, mitigation measures for the construction and operational phases of the project have been designed to minimise predicted landscape and visual impacts, and to compensate for lost landscape resources as far as is possible given the Project constraints. 

 

Specific Mitigation Measures

 

7.11.7           A series of mitigation measures have been designed to alleviate the potential landscape and visual impacts and where possible compensate for the loss of landscape resources, change of landscape character and visual amenity for VSRs resulting from the construction and operational phases of the project. The implementation, funding, and management and maintenance for the amenity landscape areas associated with the proposed works will be undertaken by relevant departments.

 

7.11.8           The mitigation measures are summarised in Table 7-13 and Table 7-14.

 

Table 713               Proposed Construction Phase Mitigation Measures

Mitigation Code

Mitigation Measure

Funding Agency

Implementation Agency

CP1

 

Preservation of Existing Vegetation - The proposed works should avoid disturbance to the existing trees as far as practicable within the works areas. It is recommended that a full tree survey and felling application will be undertaken and submitted for approval by the relevant government departments in accordance with ETWB TCW No. 3/2006, ‘Tree Preservation’ during the detailed design phase of the project. Where possible all trees which are not in conflict with the proposals would be retained and shall be protected by means of fencing where appropriate to prevent potential damage to tree canopies and root zones from vehicles and storage of materials. Specifications for the protection of existing trees will be circulated for approval by the relevant government authorities during the preparation of the detailed tree survey at detailed design and construction stage.  

SB

ArchSD

CP2

 

Preservation of Existing Topsoil - Topsoil disturbed during the construction phase will be tested using a standard soil testing methodology and where it is found to be worthy of retention stored for re-use. The soil will be stockpiled to a maximum height of 2 m and will be either temporarily vegetated with hydroseeded grass during construction or covered with a waterproof covering to prevent erosion. The stockpile should be turned over on a regular basis to avoid acidification and the degradation of the organic material, and reused after completion. Alternatively, if this is not practicable, it should be considered for use elsewhere, including other projects.

SB

ArchSD

CP3

 

Works Area and Temporary Works Areas - The landscape of the works areas shall be restored to their original state (or where appropriate adopt a new enhanced amenity) following the completion of the construction phase. Construction site controls shall be enforced, where possible, to ensure that the landscape and visual impacts arising from the construction phase activities are minimised including the storage of materials, the location and appearance of site accommodation and the careful design of site lighting to prevent light spillage. Screen hoarding may not be practicable for this project due to the  viewing distances involved and the spatial constraints of the works area

SB

ArchSD

CP4

 

Mitigation Planting - Replanting of disturbed vegetation should be undertaken at the earliest possible stage of the construction phase of the project and this should use predominantly native and/or ornamental plant species.

 

Replanting of disturbed vegetation should be undertaken at the earliest possible stage during the construction phase of the project to maximise its effect during the operational phase

SB

ArchSD

CP5

 

Transplantation of Existing Trees - Existing trees which are recommended to be transplanted due to a conflict with the works will as far as possible be relocated to final recipient sites adjacent to their current locations. This will maintain their contribution to the local landscape context. The potential recipient sites will be determined during the detailed design stage of the project.  The implementation programme of the proposed works should reserve enough time for advance tree transplanting preparation works to enhance the survival of these transplant trees.  The transplanting proposals will subject to the findings of the detailed tree survey and felling application which will b prepared during the detailed design stage of the project and submitted for approval by the relevant departments.

SB

ArchSD

           

Note:   The responsibilities for the funding, implementation, management and maintenance of the mitigation proposals will be resolved according to the principles contained in ETWB TCW No. No. 2/2004 on Maintenance of Vegetation and Hard Landscape Features.

 

Table 714   Proposed Operational Phase Mitigation Measures

Mit. Code

Mitigation Measure

Funding Agency

Implementation Agency

Maintenance/ Management Agency

OP1

 

Design of Boundary Fence, Boundary Patrol Road and Police Check Point – These structural elements will be designed in accordance with security requirement from Police Force and  incorporate design features as part of design mitigation measures including:

Integrated design approach – the boundary fence should integrated, as far as technically feasible, with existing built structures such as existing road, footpath and track and embankment of  fishponds, river and drainage channel as part of design mitigation measures to reduce the potential cumulative impact of the proposed works. The location and orientation of the police check points should be away from landscape and visually sensitive areas such wetland, fishpond and agricultural field.

Building massing - the proposed use of simple responsive design for the built structures with a low building height profile to reduce the potential visual mass of the structure within a rural context.

Treatment of built structures - the architectural design should seek to reduce the apparent visual mass of the facilities further through the use of natural materials such as wooden frame, vertical greening or other sustainable materials such as recycled plastic.

 

Responsive building and fence finishes - In terms of the proposed finishes natural tones should be considered for the colour palette with non-reflective finishes are recommended to reduce glare effect. The use of colour blocking on the proposed fence could be used to break up the visual mass of the structure.

Responsive lighting design – Aesthetic design of architectural and track lighting with following glare design measures:

Directional and full cut off lighting is recommended particularly for areas adjacent to existing village to minimise light spillage.

Minimise geographical spread of lighting, only applied for safety and security reasons;

Limited lighting intensity to meet the minimum safety and operation requirement; and

High-pressure sodium road lighting is recommended for more stringent light control reducing spillage and thus visual impacts.

SB

ArchSD

LCSD / ArchSD

OP2

 

Tree and Shrub Planting – Given the rural nature of the proposed alignment it is recommended that the where possible tree and shrub species which are native to Hong Kong be used. In addition where possible the planting of new trees and shrubs will aim to link together existing woodland areas and small tree groups to improve the connectivity between habitats and create more coherent landscape framework. The planting of small groups of trees along the alignment of the proposed fence will serve to de-emphasise the horizontality of the fence structure and provide for better sense of visual integration with the landscape context. Where practicable vertical greening measures should also be considered on engineering structures.

SB

ArchSD

LCSD

OP3

Compensatory Planting Proposals – Given the works extent is largely limited along existing roadside embankment to minimise impact to existing village settlements and valuable landscape resources such as wetland, fishpond, stream course and existing trees, and considered the importance of tree retention within the works area, new tree planting will concentrate in selected new amenity areas along the alignment, infilling between retained and transplanted trees. The preliminary planting proposals for the proposed works include the planting of some 357 new trees utilising a combination of mature to light standard sized stock (i.e. approximately 15% of mature trees, 75% of standard trees, and 10% light standard trees). These trees will be planted in woodland clumps and small tree groups at strategic locations to de-emphasise the horizontality of the fence alignment. Based on preliminary findings the proposed planting will result in a compensatory planting ratio of 1:1 (new planting: trees recommended for felling). This compares favourably with the report's assertion that some 357 trees would be felled due to the proposed works. With the proposed preservation of existing trees, transplantation of trees in conflict with the proposals and the planting of new trees the project area will contain approximately 2000 trees. Trees forming part of the new planting will provide screening to neighbourhood villagers and will utilise species native to Hong Kong. These proposals will be subject to review at detailed design stage of the project.

SB

ArchSD

LCSD

Note:   The responsibilities for the funding, implementation, management and maintenance of the mitigation proposals will be resolved according to the principles contained in ETWB TCW No. No. 2/2004 on Maintenance of Vegetation and Hard Landscape Features.

 

 

7.12               Programme for Landscape Works

 

7.12.1            The landscape works will closely follow the completion of the construction of the proposed fence construction works which are to be implemented by contractors to be appointed by ArchSD and the first contract is to be awarded in late 2009. The construction works are expected to commence in late 2009 and be completed in late 2012. The design year is for the purposes of this study taken as approximately 10 – 15 years after the scheme opening when the proposed soft landscape mitigation is mature.  The landscape works will be implemented at the earliest possible time in the planting season immediately following the sectional completion of the construction works. The implementation schedule of landscape works is presented in Chapter 11 of this report and in the EM&A Manual.

 

Operational (Residual) Landscape and Visual Impacts

 

7.12.2           Overall, in terms of residual landscape and visual impacts the main effects will primarily result from the interruption of the existing landscape and visual amenity where the fence adopts a new alignment. However in general the proposals will be located adjacent to an existing fence alignment and many of the new structures will be direct replacement for existing structures. Therefore given a combination of the condition of the landscape which is bisected by the existing fence and the utilisation of the existing DSD maintenance access track for the BPR the proposals will not cause a permanent impact to landscape resources and a relatively low level of disturbance to visual context and visual amenity available to VSRs.

 

7.12.3           A series of computer generated images or photomontages have been prepared for the proposed schemes are presented as Figures 7-9A to M. The location of the vantage points used for these images has been identified on Figures 7-7A to B. The photomontages of the proposed scheme show the existing conditions, after the completion of the construction phase when the primary mitigation measures have not been implemented, and Day 1 with the introduction of mitigation measures and Year 10 of the Operational Phase when the proposed soft landscape mitigation measures (tree and shrub planting) is fully established. The final image Operational Phase is designed to demonstrate the predicted residual impacts, which would exist in the design year during the operational phase usually taken as between 10 and 15 years after the completion of the construction phase.

 

7.13               Conclusion

 

7.13.1           This section summarises the landscape and visual impact assessment result for the Project and highlights the potential residual impacts after full establishment of recommended landscape and visual mitigation measures. Given the that the proposed SBF will closely follow the alignment for the existing boundary fence for much of its length the impacts on the landscape resources and character and visual amenity available to VSRs are not likely to be significant. 

 

7.13.2           The landscape mitigation measures recommended and discussed in section 7.11 of this report and are designed to alleviate the potential and visual impacts to ensure the implementation of the fence proposals will fit into the existing landscape and visual context. These measures include the design of the fence proposals, the appearance of the proposed structures and where possible from a land take and security perspective the planting of trees and shrubs. Another important aspect of the landscape mitigation approach is the planting of new trees and shrubs utilizing native species where possible to restore and enhance the landscape setting and visual amenity of the road and its ecological value.

 

7.13.3           The proposed works will not impact upon the land use zonings discussed in section 7.5. Therefore the Project will fit within the future landscape planning framework as represented by the OZPs and so no amendment to the published land use plans is required.

 

Landscape Impacts

 

Preservation of Landscape Resources

 

7.13.4            Given the proposed works are largely located immediately adjacent to the existing fence alignment and that many of the associated structures are replacements for existing ones the impacts on the landscape resources are not thought to be significant. Therefore the residual impacts on the existing landscape resources are likely to be negligible with the full implementation of the proposed landscape mitigation measures. One exception to this is the predicted impacts on the fishponds within the Study Area which would be slight adverse for their comparatively higher sensitivity to change. In fact the proposals will utilise the existing DSD access roads and pond bunds and will not lead to the loss of fishponds.

 

Maintenance of Landscape Character

 

7.13.5            Generally the impacts on the landscape character of the Study Area will be negligible due to the proposed alignment of the fence adjacent to the existing alignment. However there will be a slight adverse residual impact for lowland rural landscapes of Tam Kon Chau (LCA1), Mai Po (LCA2) and Sam Po Shue (LCA5) as these areas are directly affected or in close proximity to the proposals. There would also be a slight adverse indirect impact on the landscape character of Sandy Ridge Hillside (LCA7) due to the loss of landscape setting arising from the construction and operation of the proposed scheme. The landscape character of part of the central portion of the Study Area would be improved to an extent through the movement of the fence alignment to the banks on the channelised Shenzhen River. This would reduce the fragmentation of the landscape and create more naturalistic transition between the lowland plane and the upland backdrop formed by the hill slopes which line the route alignment.

 

Visual Impacts

 

7.13.6            Given the scale and nature of the Project, the nature of the existing landscape and the visual amenity enjoyed by the identified VSRs the impacts for many of the VSRs would be negligible. Even those located in close proximity to the proposed SBF already have the existing fence structures within their views.

 

7.13.7           Through a combination of the proposed realignment of sections of the PBR, PBF and SBF, and the planting of new trees and shrubs to break up the horizontal emphasis of the fence line the residual visual impacts are not predicted to be significant. The main residual impacts on the identified VSRs during the operational stage of the project are described below.

 

Section 1 – Mai Po to Lok Ma Chau Control Point

 

7.13.8           The main impacts will be apparent for residents of Tam Kon Chau (VSR1) where the moderate adverse visual impact will persist into the operational phase of the project due to proximity of the proposals to the settlement. For residents of Sam Po Shue and the planned development on the adjacent area zoned OU (VSR2) the operational impacts will be slight adverse due to the effect of the proposed planting of trees and shrubs along the fence alignment. With the relocation of the fence alignment to the north the residents of Ha Wan Tsuen (VSR4) will be subject to more open views of the open landscape to the north east and will therefore experience a moderate beneficial impact. Vehicle travellers and staff at the Lok Ma Chau border crossing (VSR3) will be subject to negligible level of impact due to the restricted nature of the existing views and the fact that the proposed scheme will be seen against backdrop of the existing fence alignment and security structures. 

 

Section 2 – Lok Ma Chau Control Point to Ng Tung River

 

7.13.9           The proposed realignment of the PBF and SBF would allow more open views of the surrounding landscape for the residents of Lok Ma Chau (VSR 5) and Shun Yee San Tsuen (VSR 6) who would be subject to a moderate beneficial impact during the operational stage of the project. These villages were located immediately adjacent to the existing alignment and so the proposals would realise a significant enhancement of existing views. The residents of Tak Yuet Lau Tsuen (VSR 7) would be subject to a slight adverse impact due to the proximity of the proposed fence alignment although the potential impacts would be mitigated to an extent by the tree and shrub panting proposed for the area to the south of the fence. These impacts are balanced to an extent by the enhancements in views to the south realised through the removal of the existing fence alignment. The staff of the Shenzhen Futian Industrial Area (OVSR19) would be subject to moderate adverse impacts due to the visual intrusion caused by the new structure. Vehicle travellers and staff at the Lo Wo border crossing (VSR 8) will be subject to negligible residual impacts due to the more restricted nature of the available views and the level of visual disturbance caused by the existing boundary and security facilities. For the future workers and staff within the development of the Lok Ma Chau Loop (PVSR 21) the potential impacts arising from the proposed PBF and SBF alignment could be mitigated to an extent through the use of tree and shrub planting along the northern periphery of the development zone resulting in a light adverse level of impact. . 

 

Section 3 – Ng Tung River to Lin Ma Hang Village

 

7.13.10       Due to the proximity of the proposed works to the existing village settlements on the valley floor the residents of Lo Wo Village (VSR9), Ta Kwu Ling Village (VSR11), Kaw Lui Village (VSR12), Lin Ma Hang Village (VSR14), Chuk Yuen (VSR21) and Tsung Yuen Ha (VSR22) would be subject to a slight adverse residual impact mitigated to an extent through the planting of trees and shrubs along the proposed alignment.  Vehicle travellers and staff at the Man Kam To border crossing (VSR 10) will be subject to a negligible impact due to the more restricted nature of the available views and the level of visual disturbance caused by the existing boundary and security facilities. The residents of the high-rise development in Shenzhen Liantang (OVSR18) would be subject to moderate adverse level of impact due in part to the proximity of the proposed works and the elevated nature of the viewing position. With the proposed realignment of the PBF and SBF to the north and west, and the opening up of new views the residents of the settlement along Lin Ma Hang Road (VSR 13) would be subject to a moderate beneficial impact and Tsung Yuen Ha (VSR22) a slight beneficial impact.

 

Section 4 – Lin Ma Hang Village to Sha Tau Kok

 

7.13.11       With the completion of the construction works and the growth proposed tree and shrub planting the predicted residual impacts for Sha Tau Kok Tsuen (VSR15), Tam Shui Hang Village Settlement (VSR16) and Shan Tsui Village (VSR17) would be slight adverse while for the residents of and Kong Ha (VSR23) the predicted impacts would be negligible.

 

Conclusion on Significance of Residual Impact

 

7.13.12        Although the proposed construction of the Second Boundary Fence is a significant project in terms of the length of the alignment the impacts are largely limited due to an alignment which mirrors that of the existing fence. Further in some instances the impacts would be beneficial due to the movement of the fence alignment away from villages or to the periphery of landscape character areas opening up new views in the first instance and minimising the fragmentation of the landscape in the second.  Therefore in accordance with Annex 10, Paragraph 1.1(c) of the EIAO TM, the landscape and visual impacts of the proposed works would be ‘acceptable with mitigation’ that is to say ‘there would be some adverse effects, but these can be eliminated, reduced or offset to a large extent by specific measures’.

 

 


8                        CULTURAL HERITAGE

 

8.1                   Introduction

 

8.1.1              This section will present the baseline profile of the archaeological and built heritage resources present in the Study Area and results of the impact assessment

 

8.2                   Environmental Legislation and Standards

 

8.2.1              Legislation, Standards and Guidelines relevant to the consideration of Cultural Heritage impacts under this study include the following:

 

·         Antiquities and Monuments Ordinance

·         Environmental Impact Assessment Ordinance

·         Hong Kong Planning Standards and Guidelines

·         Technical Memorandum on Environmental Impact Assessment Process

·         Guidelines for Cultural Heritage Impact Assessment

·         DEVB TC (W) No. 11/2007

Antiquities and Monuments Ordinance

 

8.2.2              The Antiquities and Monuments Ordinance (the Ordinance) provides the statutory framework to provide for the preservation of objects of historical, archaeological and palaeontological interest.  The Ordinance contains the statutory procedures for the Declaration of Monuments. The proposed monument can be any place, building, site or structure, which is considered to be of public interest by reason of its historical, archaeological or palaeontological significance.

 

8.2.3              Under Section 6 and subject to sub-section (4) of the Ordinance, the following acts are prohibited in relation to certain monuments, except under permit;

 

·         To excavate, carry on building works, plant or fell trees or deposit earth or refuse on or in a proposed monument or monument;

·         To demolish, remove, obstruct, deface or interfere with a proposed monument or monument.

 

8.2.4              The discovery of an Antiquity, as defined in the Ordinance must be reported to the Antiquities Authority (the Authority), or a designated person. The Ordinance also provides that, the ownership of every relic discovered in Hong Kong after the commencement of this Ordinance shall vest in the Government from the moment of discovery.  The Authority on behalf of the Government may disclaim ownership of the relic.

 

8.2.5              No archaeological excavation may be carried out by any person, other than the Authority and the designated person, without a licence issued by the Authority. A licence will only be issued if the Authority is satisfied that the applicant has sufficient scientific training or experience to enable him to carry out the excavation and search satisfactorily, is able to conduct, or arrange for, a proper scientific study of any antiquities discovered as a result of the excavation and search and has sufficient staff and financial support.

 

8.2.6              It should also be noted that the discovery of an antiquity under any circumstances must be reported to the authority, i.e. the Secretary for Development or designated person. The authority may require that the antiquity or suspected antiquity is identified to the authority and that any person who has discovered an antiquity or suspected antiquity should take all reasonable measures to protect it.

 

Environmental Impact Assessment Ordinance

 

8.2.7              The Environmental Impact Assessment Ordinance (EIAO) was implemented on 1 April 1998. Its purpose is to avoid, minimise and control the adverse impact on the environment of designated projects, through the application of the EIA process and the Environmental Permit (EP) system.

 

Hong Kong Planning Standards and Guidelines

 

8.2.8              Chapter 10 of the HKPSG details the principles of conservation of natural landscape and habitats, historical buildings and archaeological sites. The document states that the retention of significant heritage features should be adopted through the creation of conservation zones within which uses should be restricted to ensure the sustainability of the heritage features. The guidelines state that the concept of conservation of heritage features, should not be restricted to individual structures, but should endeavour to embrace the setting of the feature or features in both urban and rural settings.

 

8.2.9              The guidelines also address the issue of the preparation of plans for the conservation of historical buildings, archaeological sites and other antiquities. It is noted that the existing Declared Monuments and proposed Monuments be listed in the explanatory notes of Statutory Town Plans and that it be stated that prior consultation with AMO is necessary for any redevelopment or rezoning proposals affecting the Monuments and their surrounding environments.

 

8.2.10           It is also noted that planning intention for non-statutory town plans at the sub-regional level should be include the protection of monuments, historical buildings, archaeological sites and other antiquities through the identification of such features on sub-regional layout plans. It also addresses the issue of enforcement. The appendices list the legislation and administrative controls for conservation, other conservation related measures in Hong Kong, and Government departments involved in conservation.

 

Technical Memorandum on Environmental Impact Assessment Process

 

8.2.11           The general criteria and guidelines for evaluating and assessing impacts to Cultural Heritage are listed in Annexes 10 and 19 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM). It is stated in Annex 10 that all adverse impacts to Sites of Cultural Heritage should be kept to an absolute minimum and that the general presumption of impact assessment should be in favour of the protection and conservation of all Sites of Cultural Heritage. Annex 19 provides the details of scope and methodology for undertaking Cultural Heritage Impact Assessment, including baseline study, impact assessment and mitigation measures.

 

Guidelines for Cultural Heritage Impact Assessment

 

8.2.12           This document, as issued by the Antiquities and Monuments Office, outlines the specific technical requirement for conducting terrestrial archaeological and built heritage impact assessments and is based upon the requirements of the Technical Memorandum for Environmental Impact Assessment. It includes the parameters and scope for the Baseline Study, specifically desk-based research and field evaluation. There are also included guidelines encompassing reporting requirements and archive preparation and submission in the form of Guidelines for Archaeological Reports and Guidelines for the Handling of Archaeological Finds and Archives.

 

8.2.13           The prerequisite conditions for conducting impact assessment and mitigation measures are presented in detail, including the prediction and evaluation of impacts based upon five levels of significance (Beneficial, Acceptable, Acceptable with Mitigation Measures, Unacceptable and Undetermined). The guidelines also state that preservation in totality must be taken as the first priority and if this is not feasible due to site constraints or other factors, full justification must be provided.

 

8.2.14           Mitigation measures will be proposed in cases with identified impacts and shall have the aim of minimising the degree of adverse impact and also where applicable providing enhancement to a heritage site through means such as  enhancement of the existing environment or improvement to accessibility of heritage sites. The responsibility for the implementation of any proposed mitigation measures must be clearly stated with details of when and where the measures will be implemented and by whom.

 

Development Bureau Technical Circular (Works) No. 11/2007: Heritage Impact Assessment Mechanism for Capital Works Projects

 

8.2.15           The technical circular contains the procedures and requirements for assessing heritage impact arising from the implementation of new capital works projects as defined in section 5 of the TC. It is stated in the document that the works agent will provide a checklist to the AMO of any heritage sites (as defined in the TC) situated within or within the vicinity of the project boundary (usually to be defined as not more than 50 metres measured from the nearest point of the project boundary, including works areas).

 

8.2.16           The identification of the heritage sites should be undertaken at the earliest possible stage, preferably as part of the Technical Feasibility Statement. If the works boundary cannot be defined at this stage, the checklist should be provided as soon as the project boundary has been defined. Upon receipt of the above information from the works agent, the AMO will determine if the proposed project will affect the heritage value of any heritage site and decide the necessity of conducting an HIA based upon the submitted information.

 

8.2.17           If an HIA is required, the works agent shall submit a proposal for the scope of the HIA for AMO approval. Once the scope has been approved it will be the responsibility of the works agent to conduct the HIA.

 


8.3                   Methodology

 

Archaeological Resources

 

Baseline Study

 

8.3.1              As stated in the Criteria for Cultural Heritage Impact Assessment, the baseline study is used to compile a comprehensive inventory of all sites of archaeological interest within and in the environs of the project Study Area. The results are then presented in a report that provides both clear evidence that the required processes have been satisfactorily completed as well as a detailed inventory of all identified sites of archaeological interest, which includes a full description of their cultural significance.

 

8.3.2              The following tasks are undertaken in order to gather the necessary information for the compilation of the baseline study:

 

Desk-based research

 

8.3.3              Firstly, desk-based research is carried out in order to identify any known or potential sites of archaeological interest within the project study area and to evaluate the cultural significance of these sites once identified. The following is a non-exhaustive list of resources that are consulted as part of the research programme: the Antiquities and Monuments Office published and unpublished papers and studies; publications on relevant historical, anthropological and other cultural studies; unpublished archival papers and records; collections and libraries of tertiary institutions; historical documents held in the Public Records Office, Lands Registry, District Lands Office, District Office and Museum of History; cartographic and pictorial documentation; and geotechnical information.

 

Site visit

 

8.3.4              To supplement the information gathered in the desk-based study, a site visit is undertaken to assess the current status of the Study Area and also to make note of existing impacts.

 

Archaeological Field Investigation (if required)

 

8.3.5              If the results of the desk-based study and site visit indicate that there is insufficient data for purposes of identification of sites of archaeological interest, determination of cultural significance and assessment of impacts, an archaeological field investigation programme will be designed and submitted to the AMO for approval. Once approved, a qualified archaeologist must apply for a licence to undertake the archaeological excavation, which must be approved by the Antiquities Authority before issuance. The archaeological field investigation typically consists of some or all of the following steps:

 

Field Scan

 

8.3.6              Field walking is conducted to identify archaeological deposits on the surface. The scanning of the surface for archaeological material is conducted, under ideal circumstances, in a systematic manner and covers the entire study area. Particular attention is given to areas of land undisturbed in the recent past and to exposed areas such as riverbed cuts, erosion areas, terraces, etc. During the filed scanning, concentrations of finds are recorded, bagged and mapped on 1:1000 scale mapping and are retained as part of the archive. Topography, surface conditions and existing impacts are noted during the field walking.

 

Auger Testing Programme

 

8.3.7              Auger survey of the identified areas that will be impacted by proposed works will be carried out in order to establish soil sequence, the presence/absence of cultural soils or deposits and their horizontal extent. The auger tool consists of a bucket, pole and handle and is vertically drilled by hand into the surface.  When the bucket is filled with soil the auger is extracted and the soil emptied from the bucket.  Soils are described and depth changes are measured inside the hole.  The depth and type of any finds recovered are also recorded.  The auger hole is abandoned when water table, the end of the auger or rock is reached or the auger bucket fails to hold the soil. The location of each auger hole test is marked on a 1:1000 scale map. The results of the auger tests provide one of the criteria used to position the test pit excavations.

 

Test Pit Excavation

 

8.3.8              Test pit excavations are carried out to verify the archaeological potential within a study area. The choice of location for test pit excavations will depend on various factors such as desk-based information, landforms, field scan and auger test results as well as issues relating to access.

 

8.3.9              Hand digging of test pits measuring between 1 by 1 and 2 by 2 metres is carried out in order to determine the presence/absence of archaeological deposits and their stratigraphy.  The size may depend on close proximity to large trees, narrow terraces or other external factors. Hand excavation will continue until decomposing rock or sterile soils are reached and no potential for further cultural layers exists. A test pit will also be abandoned when the effects of ground water prevent futher excavation or when the depth poses safety problems. During excavation contexts, finds and features are recorded, soils are described and relevant depths measured. Artefacts are recorded, bagged and labelled by context. Sections are photographed and drawn and, if required, ground plans are also photographed and/or drawn. The position of each test pit, its top and bottom levels and associated TBM are recorded by a qualified land surveyor and plotted on 1:1000 scale mapping. On completion of all recording the test pits are backfilled.

 

Reporting and Submission of Archive

 

8.3.10           A report of the findings of the archaeological survey will be compiled following the requirements as outlined in the AMO’s Guidelines for the Preparation of Archaeological Reports (see Section 14.1). The processing of recovered archaeological material and preparation of the project archive will follow the AMO’s Guidelines for Handling of Archaeological Finds and Archives (see Section 14.2).

 

Impact Assessment

 

8.3.11           The prediction and evaluation of both direct and indirect impacts must be undertaken to identify any potential adverse affects to all identified sites of archaeological interest within a project Study Area. A detailed description of the works and all available plans (with their relationship to the identified resources clearly shown) should be included, to illustrate the nature and degree of potential impacts. The impact assessment must adhere to the detailed requirements of Annexes 10 and 19 of the Technical Memorandum on Environmental Impact Assessment Process.

 

Mitigation Measures

 

8.3.12           As stated in the Guidelines for Cultural Heritage Impact Assessment “Preservation in totality must be taken as the first priority”. If such preservation is not feasible, as in the case where the need for a particular development can be shown to have benefits that outweigh the significance of the site of archaeological interest, a programme of mitigation measures must be designed and submitted to the AMO for approval. The mitigation measures must be clearly listed and the party responsible for implementation and timing of the measures must also be included. Examples of mitigation measures include; rescue excavation and archaeological watching brief.

 

Built Heritage Resources

 

Baseline Study

 

8.3.13           A baseline study was undertaken to ensure that all built heritage resources in the project area would be identified in order to identify any indirect or direct impacts to these resources, including direct loss, destruction or disturbance and any deterioration of the existing environmental setting. The baseline study consisted of a desk top research and a built heritage field survey.

 

Desk-Based Research

 

8.3.14           The purpose of undertaking the desk top study is to collect and collate all extant information on built heritage resources in the project study area and to determine if the existing information is sufficient for purposes of impact assessment or if field evaluation will also be required. In the case of the current project, it was determined that the existing information was not sufficient and a built heritage field survey was also undertaken.

 

Built Heritage Field Survey

 

8.3.15           A proposal for built heritage field survey was prepared and submitted to AMO for review and approval. The built heritage survey was conducted for any areas and resources that have not been covered by previous surveys within the project Study Area. A boundary of 50 metres from all alignments and works areas is proposed for the survey.

 

Resource Scope

 

8.3.16           Definition of Features that Fall within the Scope of Built Heritage Survey:

 

·         All pre-1950 buildings and structures;

·         Selected post-1950 buildings and structures of high architectural and historical significance or interest;

·         Cultural landscape features, such as sites of historical events, or providing a significant historical record or a setting for buildings or monuments of architectural importance, historical field patterns, tracks and fish pond and cultural elements, such as fung shui woods and historical clan graves.

 

Recording Requirements

 

8.3.17           Detailed Recording of all Identified Built Heritage Features divided into the following categories: Buildings and Structures, Graves and Cultural Landscape Features. It should be noted that any sections of identified historical village wall or paving stones will be covered under the built heritage survey. The recording of the structures must adhere to the requirements of conducting built heritage survey as presented in the Guidelines for Cultural Heritage Impact Assessment.

 

8.3.18           Interviews with local informants, including residents and village elders should also be undertaken. The interviews should be used to gather information, such as, cultural and historical background of the structures and the villages, historical events associated with the structures and villages for the compilation of a background description.

 

Documentation

 

8.3.19           Systematic documentation of all recorded features within each of the categories listed below must be undertaken. The following must be included:

 

For Built Structures

 

8.3.20           A set of photographs of each building or structure including the exterior, the interior (if permission of owner is given to enter the premises) and special architectural details where possible, as well as the surroundings of the feature should be included. The boundary and location of each recorded structure will be provided on a 1:1000 scale map and the relationship to the proposed site boundary, including all works areas will also be provided. Locations of Graded Historical Buildings and Declared Monuments will be provided on separate maps.

 

8.3.21           Written descriptions of each recorded feature, including; age of structure, details of architectural features, condition of the structure, past and present uses, architectural appraisal, notes on any modifications, direction faced and associations with historical/ cultural events or individuals is required, as is a description of the surrounding environment and orientation of each recorded resource.

 

8.3.22           A background summary of each village, including a physical description of the environmental setting (surrounding environment) as well as information gathered from oral interviews with local informants, should also be included in the report. For isolated structures descriptions must be done on an individual basis. The description for structures within a village can be covered by a village background summary, this must include physical and cultural attributes, such as orientation of villages to any identified fung shui features, general condition of structures, settlement history, historical economic activities and associated clans.

 

For Historical Clan Graves

 

8.3.23           The location of the each recorded grave including its relationship to the proposed site boundary, including all works areas on a 1:1000 scale map, as well as a written description of each recorded grave (including; the construction year of the grave if available, the associated clan, a copy of the inscription, the dimensions, the orientation, any renovation dates, a physical description of the architectural elements of the grave, including whether the grave consists of modern or historical building materials. The renovation dates must also be listed and the incorporation of any historical elements (such as an inscription plaque) have been incorporated into a modern renovated grave. Finally, a set of photographs of each grave must also be provided.

 

For Cultural Landscape Features

 

8.3.24           The location of each recorded feature including its relationship to the proposed site boundary, including all works areas must be provided on a 1:1000 scale map. A written description of each recorded feature, including information gathered from interviews with local informants and a set of photographs of each recorded feature must also be provided.

 

Reporting

 

8.3.25           The report will include a detailed inventory of all identified built heritage resources. The heritage significance of the resources will be included in the report under the following categories:

 

·         HIGH: Declared or Proposed Monuments

 

·         MEDIUM: Graded Historic Buildings and Government Historic Sites

 

·         LOW: Buildings, structures, sites and landscape features that are included in the definition of heritage sites as stated in the Guidelines for Cultural Heritage Impact Assessment, but have not been included in the above government issued lists. It should be noted that as stated in section 4.3 of the Hong Kong Planning Standards and Guidelines, the AMO is responsible for identifying, recording and researching buildings and sites of historical interest and that it is the role of the Antiquities Advisory Board to recommend as to whether or not the identified structures merit conservation. Also, as stated in the standards and guidelines that as the recording of heritage resources is an ongoing process, any new items discovered should be referred to AMO for follow-up action.

 

8.4                   Results of the Desk-Based Assessment

 

Archaeological Resources

 

8.4.1              This section presents the results of the desk-based assessment, which sought to provide background information on the project study area in terms of its geology, topography, historical development and known archaeological resource.

 

Geology and Topography

 

8.4.2              The topography of the Study Area ranges in character from coastal low-lying marshy land and estuarine/ intertidal deposits in the west, to flat alluvium and terrace alluvium in the north.

 

8.4.3              The geology of the north-eastern part of the Study Area at Pak Fu Shan and Lin Ma Hang consists mainly of Pleistocene debris flow deposits and strips of Holocene alluvium along the coast (Figure 8.1).  There is also an extensive outcrop of volcanic rocks of coarse ash crystal tuff of Tai Mo Shan Formation.

 

8.4.4              In the middle part of the Study Area at Man Kam To, the geology is dominated by estuarine and intertidal deposits along the coast (Figure 8.2).  Strips of Holocene alluvium and Pleistocene debris flow deposits are also identified. Outcropping volcanic rocks in the form of metasediments of the Lok Ma Chau Formation occur near Nam Hang.

 

8.4.5              Holocene estuarine and intertidal deposits are the major geological feature occupying the northern part of the Study Area at Hoo Hok Wai (Figure 8.3).

 

8.4.6              The geology of the western part of the Study Area at Mai Po, San Tin and south-west of Hoo Hok Wai is dominated by dark grey marine mud and low-lying marshy land (Figure 8.3).  The Sha Tau Kok study area is mainly situated on Pleistocene terraced alluvium (Figure 8.4).

 

8.4.7              In general, the onshore superficial deposits of the Study Area comprise mainly of marine mud, alluvial, debris flow, estuarine, and intertidal deposits of Pleistocene and Holocene age.  Alluvium is widespread along the Shenzhen River and River Indus valleys, forming extensive floodplains (GEO 1996).  A series of existing ponds and wetland on marine mud occupy the western part of the Study Area along Mai Po, San Tin and Hoo Hok Wai.

 

Archaeological Background

 

8.4.8              There are several archaeological sites located within or close to the Study Area (Figure 8.5):

 

Section 1 – Mai Po to Lok Ma Chau Control Point

 

8.4.9              No known archaeological sites are located in this section.

 

Section 2 – Lok Ma Chau Control Point to Ng Tung River

 

8.4.10           No known archaeological sites are located in this section.

 

Section 3 – Ng Tung River to Lin Ma Hang Village

 

Muk Wu Nga Yiu Kilns

 

8.4.11           Four kilns in the Muk Wu Nga Yiu area were first recorded in 2000 during the Shenzhen River Regulation Project (HKIA 2001).  Three of the kilns were located in Nga Yiu Tsuen and one in Muk Wu Nga Yiu Tsuen.  These kilns date back to approximately 100 years ago and were used for brick and tile production (HKIA 2001).

 

Section 4 – Lin Ma Hang Village to Sha Tau Kok

 

Sha Tau Kok San Tsuen Archaeological Site

 

8.4.12           The site was first identified during the 1998 Territory-wide Survey, with the discovery of some Qing dynasty materials (AMO 1999). Field investigations in 2000 revealed that the site contained rich prehistoric cultural deposits including Warring States hard pottery sherds and Late Neolithic stone implements (Au 2000).  An excavation was conducted at the centre of the archaeological site in San Tsuen in 2001 prior to a small village house construction.  Four cultural layers (Early Neolithic, Mid Neolithic, Late Neolithic and Bronze Age), as well as a large number of stone artefacts, and features including 3 postholes, 2 pits and traces of stone working areas were identified (Mok 2001).  

 

Areas of Archaeological Interests located near the Study Area (Figure 8.5):

 

Tsung Yuen Ha

 

8.4.13           The monitoring of sewerage groundworks in 2004 resulted in the identification of a Ming Dynasty occupation site at Tsung Yuen Ha and another settlement of indeterminate age, which appeared to extend under standing historical buildings.   The structural remains had a different orientation to the current historical village, but the associated finds did not, however, allow the structures to be dated.  The exact extent of the site could not be established due to the geographical limitations of the monitoring works and the concrete covering of the current village. Further investigation is needed to understand the extent both geographically and chronologically of the site (AAL 2005).

 

Tong Fong

 

8.4.14           The village has a settlement history of approximately 200 years. At the rear of the village at a depth of 1 m below the surface a single ceramic jar was found.  The find, although not closely datable, suggested that the village may contain remains from earlier historical periods, which can only be confirmed through further investigation (AAL 2005).      

 

Yuen Leng Tsai

 

8.4.15           The site was first identified in 2001 during the archaeological investigation for the Shenzhen River Regulation Project (with the discoveries of Bronze Age, Song/Yuan and Ming/Qing finds from surface scan, auger hole tests and test pit excavation) (HKIA 2001).  Since the identified areas at Yuen Leng Chai would be directly impacted by the proposed works, a subsequent rescue excavation was carried out in 2001 as mitigation measure.  Two burials dated to the Song/Yuan period, as well as some Bronze Age geometric sherds, were recorded in the excavation (HKIA 2003).   

 

Previous archaeological investigations within or close to the Study Area:

 

Territory-wide Survey

 

8.4.16           Field investigations were carried out near Sha Tau Kok Hoi and on the south bank of Shenzhen River as part of the 1997-98 Territory-wide Survey.  Some of the investigated areas were located within or near the current Study Area boundary:

 

·         Shan Tsui (NW) – 1 auger hole test; high water table, confirmed as having no archaeological potential

·         Sha Tau Kok – 4 auger hole tests, highly modified landform/landscape, impossible to locate the original alluvial deposits

·         Lin Ma Hang – Surface scan and 8 auger hole tests; no archaeological materials were identified

·         Pak Fu Shan – Surface scan and 7 auger hole tests; Qing dynasty-recent period porcelain sherds were collected on surface

·         Tsung Yuen Ha – Surface scan and 3 auger hole tests; Qing dynasty-recent period porcelain sherds were collected on surface

·         Chuk Yuen – Surface scan and 3 auger hole tests; modern porcelain sherds were collected on the surface

·         Lo Shu Ling – Surface scan and 3 auger hole tests; modified landform/landscape, no archaeological materials were identified

·         Muk Wu Nga Yiu – 1 auger hole test; no archaeological materials were identified

·         Muk Wu – 1 auger hole; no archaeological materials were identified

·         Yuen Leng Chai – Surface scan and 1 auger hole; no archaeological materials were identified.

 

The 2000 Archaeological Survey & Assessment for Shenzhen River Regulation Project Stage III

 

8.4.17           An archaeological field investigation as part of the above EIA was undertaken in 2000.  The entire Study Area was located within the closed area, along Shenzhen River.  A Song/Yuan period site was identified at Yuen Leng Chai.  Several Warring States-Hang Dynasty geometric pottery surface finds were also collected at the site.  In addition, four early 20th-century kilns in the Muk Wu Ngau Yiu area were recorded (HKIA 2001).

 

Rescue Excavation at Yuen Leng Chai

 

8.4.18           This Song/Yuan site was identified during the archaeological investigation carried out for the Shenzhen River Regulation Project Stage III in 2000.  Since the site would be directly impacted by the proposed work, a rescue excavation was conducted in 2002-2003 prior to the construction phase.  Two well preserved burials dated to Song/Yuan period were recorded, along with associated finds such as celadon bowls, cloth-pattern tiles, and nine iron nails – probably part of the decayed coffins (HKIA 2003).     

 

Agreement No. CE64/96, Planning & Development Study on NENT, CHIA

 

8.4.19           A field investigation was carried out for the above project at Kwu Tung, Ma Tso Lung, Fung Kong, Ho Sheung Heung, Yin Kong and Lo Wu Correctional Institute and its adjacent hills.  Only the investigated area at Ma Tso Lung and Lo Wu Correctional Institute were located within the current Study Area boundary.  A surface survey, 19 auger hole test and 8 test pit excavations (1m x 1.5m) were conducted in Ma Tso Lung.  Two Song celadon sherds were collected on the surface and some Qing Dynasty bowl base sherds were found in one of the test pits.  All finds were identified as secondary deposits.  For the investigated area at Lo Wu Correctional Institute, no archaeological materials were identified in the surface scan and test pit excavation.  According to the report, the valley was filled by soil excavated from the hill slope during levelling and filling for the construction of the Lo Wu Camp (now known as the Correctional Institute).  Any in situ ancient cultural remains had been destroyed and the entire area was confirmed by the field testing as having no archaeological potential (ERM 2001).  

 

The 2001 Archaeological Survey & Assessment for the Proposed NENT Landfill Extension

 

8.4.20           An early 17th- to early 20th-century settlement site was identified in the Tong To Shan/ Lin Ma Hang area.  Findings included 6 stone trackways surfaced with flat stone slabs, 74 ‘slope-protection walls’, the remains of nine houses, and one cistern.  Forty graves were also identified in the Ngong Tong area.  Some Wun Yiu style blue-and-white porcelain sherds were collected at/near the house ruins (HKIA 2002).

 

Agreement No. CE20/2004 (EP), NENT Landfill Extension – Feasibility Study, CHIA

 

8.4.21           A total of ten auger hole tests and two test pit excavations were conducted at Tong To Shan.  The results indicated that the hill slope and terraces consisted of moderate to deeply weathered colluvium.  No archaeological material was recovered during the auger testing and test pit excavations (AAL 2005).

 

Northeast New Territories Village Sewerage: Archaeological Monitoring and Condition Survey

 

8.4.22           Archaeological watching brief was conducted within the closed border area at Ta Kwu Ling during the construction phase of the NENT Village Sewerage project.  Significant findings included the identification of a Ming Dynasty occupation site at Tsung Yuen Ha and a settlement of indeterminate age, which appeared to continue under the existing historical buildings.  Other materials were also collected from nearby historical villages, such as Tong Fong and Ping Che (AAL 2005).  

 

Archaeological Survey at Wang Lek near Lin Ma Hang Road

 

8.4.23           A field investigation was carried out at Wang Lek near Lin Ma Hang Road for the Secondary Boundary Fence project in 2006.  The works area measured approximately 2m wide by 800m long. The alignment of the proposed work was situated on either debris flow or alluvial deposits.  A field scan, 25 auger hole tests and eight test pit excavations were conducted.  No archaeological or historical remains were identified in the survey (HKIA 2006).

 


Built Heritage Resources

 

Declared or Proposed Monuments

 

8.4.24           There are no Proposed or Declared Monuments in the project Study Area.

 

Government Historic Sites

 

8.4.25           There are no such sites in the project Study Area.

 

Historical Villages

 

8.4.26           The proposed works will not take place within the boundaries of any occupied historical villages. The alignment will include the periphery of the ruins of the abandoned village of Chuk Yuen.

 

Graded Historic Buildings

 

8.4.27           There are no Graded Historic Buildings in the project Study Area.

 

8.5                   Findings of Assessment

 

Assessment of Archaeological Potential

 

8.5.1              Although the archaeological potential of the closed area is generally high due to a lack of disturbance to potential deposits in the past and only limited archaeological investigation (which have provided very little information regarding the nature and extent of archaeological deposits), most of the current proposed works are located on Existing Boundary Patrol Roads. Such alignments were previously disturbed by the original construction work. Therefore, the potential for in situ archaeological deposits under the existing road corridors is limited. As well, some of the proposed alignments are located on former wet areas, or close to existing rivers, or in areas where the natural riverbank was modified during canalisation works, which would have had impacted archaeological potential.  

 

Section 1

 

Proposed Secondary Boundary Fence along Existing Boundary Patrol Road (Mai Po to Lok Ma Chau Control Point)

 

8.5.2              No archaeological potential – The entire proposed alignment is located on former wetland/marine mud and is now surrounded by ponds.  As well, the proposed alignment is located on the existing Boundary Patrol Road along Shenzhen River.

 

Existing Pak Hok Chau Checkpoint to be replaced

 

8.5.3              No archaeological potential – The study area is located on former wetland/marine mud and is now surrounded by ponds. In addition, the proposed checkpoint will be constructed on the footprint of the existing one.

 

Section 2

 

Proposed Secondary Boundary Fence along Existing Boundary Patrol Road at Lok Ma Chau

 

8.5.4              No archaeological potential – The study area is located on former wetland/marine mud and is now surrounded by ponds.

 

Existing Boundary Fence to be removed (from Lok Ma Chau to Ng Tung River)

 

8.5.5              No archaeological potential – No impacts on underground deposits are anticipated from the proposed work along the existing Boundary Fence from Lok Ma Chau to Ng Tung River.

 

Proposed new Boundary Patrol Road with Primary and Secondary Boundary Fences (North of the Lok Ma Chau Loop and Hoo Hok Wai)

 

8.5.6              No archaeological potential – The alignment is situated on an existing man-made river embankment/ road, which follows the canalised Shenzhen River.  The embankment/ road was filled and constructed by DSD in the late 1990s.  As well, the study area is located on former wetland and marine mud, and is now surrounded by ponds.

 

Existing Lok Ma Chau Checkpoint to be removed

 

8.5.7              No archaeological potential – No impacts on underground deposits are anticipated from the proposed work.

 

Section 3

 

Proposed Secondary Boundary Fence along Existing Boundary Patrol Road (Lo Wu to Lin Ma Hang)

 

8.5.8              No archaeological potential – Most parts of this section of the study area were investigated in the 2001 Shenzhen River Regulation Project (HKIA 2001).  Historical kilns were identified in Muk Wu Ngau Yiu, and a Song/Yuan site was identified at Yuen Leng Chai.  A rescue excavation was later conducted prior to the commencement of construction works, which led to the discovery of two Song/Yuan burials and Bronze Age geometric pottery sherds (HKIA 2003). 

 

8.5.9              Although archaeological remains were discovered near the current project area, all of the proposed SBF are located on the existing BPR, which already has disturbance from the previous road construction work.  As well, some areas were disturbed by the above mentioned Shenzhen River Regulation Project. Therefore, the potential of finding in situ archaeological deposits here is limited. More importantly, no impacts are anticipated from the proposed works, which involve the addition of a boundary fence along (and within the footprint of) the existing boundary patrol road.  No field testing is therefore needed in this instance.

 

Existing Boundary Fence to be removed (at Pak Fu Shan area)

 

8.5.10           No archaeological potential – No impacts on underground deposits are anticipated from the proposed work.

 

****Proposed new Boundary Patrol Road with Primary and Secondary Boundary Fences

(Pak Fu Shan)

 

8.5.11           Some archaeological potential – the proposed new road with secondary boundary fences is situated on alluvium, which fills the valley bottom between the river channel and foothill areas of Pak Fu Shan. The area presently consists of abandoned and overgrown agricultural land.  No previous field testing has been carried out in this area, and there are only limited existing impacts.

 

8.5.12           The 2006 Wang Lek survey (HKIA 2006) was conducted along the southern edge of the Shenzhen River Valley at the base-of-hillslope area on debris flow deposits, solid geology and a small area with alluvium. The topographic, geological and landuse contrast between the Wang Lek survey area and the proposed Boundary Patrol Road alignments at Pak Fu Shan and Lin Ma Hang is archaeologically significant. Therefore, the negative result from Wang Lek survey does not usefully inform our assessment of archaeological potential of the proposed Pak Fu Shan alignment, which lies on land that would have been far more attractive to past human populations in the area.

 

****Proposed new Boundary Patrol Road with Primary and Secondary Boundary Fences (Lin Ma Hang)

 

8.5.13           Some archaeological potential – Proposed alignments are situated on strips of alluvium.  The area presently consists of abandoned and overgrown agricultural land.  No former field testing has been carried out in this area, and there are only limited existing impacts.

 

8.5.14           The 2006 Wang Lek survey was conducted along the southern edge of the Shenzhen River Valley at the base-of-hillslope area on debris flow deposits, solid geology and a small area with alluvium (HKIA 2006). The topographic, geological and landuse contrast between the Wang Lek survey area and the proposed Boundary Patrol Road alignments at Pak Fu Shan and Lin Ma Hang is archaeologically significant. Therefore, the negative result from Wang Lek survey does not usefully inform our assessment of archaeological potential of the proposed Lin Ma Hang alignment, which lies on land that would have been far more attractive to past human populations in the area.

 

Existing Sha Ling Checkpoint to be removed

 

8.5.15           No archaeological potential – No impacts on underground deposits are anticipated from the proposed work.

 

Existing Ping Che Checkpoint to be removed

 

8.5.16           No archaeological potential – No impacts on underground deposits are anticipated from the proposed work.

 

8.5.17           **** Since Pak Fu Shan and Lin Ma Hang Study Areas are evaluated as having some archaeological potential, field testing is proposed in both areas.  A methodology has been submitted and agreed by the AMO.  However, part of those areas cannot be accessed currently. Therefore, the field testing can only be undertaken after land resumption (prior to construction work).   

 

Section 4

 

Proposed Secondary Boundary Fence along Existing Boundary Patrol Road (Sha Tau Kok)

 

8.5.18           Although this study area is located in close proximity to Sha Tau Kok San Tsuen Archaeological Site, the proposed SBF is located on an Existing Boundary Patrol Road (Shan Tsui Village Road and Sha Ho Road).  Any archaeological deposits under the road corridor would have been adversely impacted upon by the construction and ongoing maintenance of the road.  The likelihood of finding in situ archaeological deposits is therefore limited.

 

Proposed ‘Gate One’ Checkpoint at Sha Tau Kok

 

8.5.19           No archaeological potential - Although this study area is located in close proximity to Sha Tau Kok San Tsuen Archaeological Site and near the former coast, the proposed site is situated on an existing path next to Sha Tau Kok Road Shek Chung Au Section.  The area located to its immediate south consists of land that was artificially filled for development purposes.  The potential of finding in situ archaeological deposits is limited. 

 

Existing Shek Chung Au Checkpoint to be removed

 

8.5.20           No archaeological potential – No impacts on underground deposits are anticipated from the proposed work.

 

Results of the Field Survey for Built Heritage Resources

 

Section 1

 

8.5.21           This section of the alignment runs from Mai Po to the existing Lok Ma Chau Control Point. The works will consist of construction of a SBF of approximately 4.1 km and replacement of the existing checkpoint at Pak Hok Chau. No built heritage resources were identified in the project Study Area.

 

Section 2

 

8.5.22           This section of the alignment (which is approximately 5.6 km in length) runs along the southern edge of the Shenzen River, beginning at Lok Ma Chau through Hoo Hok Wai and to Lo Wu. The majority of the alignment runs through abandoned ponds and fields. Two built heritage resources were identified in the project Study Area a shrine associated with the village of Liu Pok (BF-HB1) and a renovated grave with an original burial dating to the Ming Dynasty (BF-G1). The locations of the shrine and grave can be seen on Figure 8.6 and the descriptions and photographs can be found in Appendix H.

 

Section 3

 

8.5.23           This section of the alignment runs from the Ng Tung River to Lin Ma Hang Village. The construction works will consist of provision of a new SBF along the existing BPR north of Pak Fu Shan and Northwest of Lin Ma Hang Village (approximately 7.5 km) and to construct new sections of BPR along the Shenzen River (approximately 4 km). One renovated grave (BF-G2) was identified at this section of the alignment, see Figure 8.7 for location and Appendix H for detailed description. As well, two ruined structures at the abandoned village of Chuk Yuen (BF-HB2 and BF-HB3) were found to be on the border of the Study Area and the locations of these are shown in Figure 8.8 and description can be found in Appendix H. This village was one of the listed indigenous villages in the New Territories and according to local informants, the original Chuk Yuen Wai was a Hakka village established 200-300 years ago in the low-lying area by the river.  ‘Yiu’ was the major clan occupying the village, with their own ancestral hall. There were also two families with the surname ‘Yau’. About 40 years ago, many of the villagers immigrated to Europe and the village was eventually completely abandoned due to flooding.

 

Section 4

 

8.5.24           This section of the alignment is located in Sha Tau Kok Town and consists of the construction of approximately 0.5 km of secondary boundary fence and a new checkpoint at Gate 1. One built heritage resource was identified during the survey of the Study Area for section 4. It is an historical residential structure (BF-HB4). A map showing the location of the building is shown in Figure 8.9 and a description and photograph of the building is provided in Appendix H.

 

8.6                   Impact Assessment

 

Archaeological Resources

 

Construction Phase

 

Section 1

 

Proposed Secondary Boundary Fence along Existing Boundary Patrol Road (Mai Po to Lok Ma Chau Control Point)

 

8.6.1              The Study Area will have direct impacts from the proposed works.  However, the proposed alignment has already been disturbed during the construction of the existing Boundary Patrol Road.  In addition, the Study Area is located on former wetland/marine mud and is now surrounded by ponds.

 

Existing Pak Hok Chau Checkpoint to be replaced

 

8.6.2              The Study Area will have direct impacts from the proposed works.  However, the proposed checkpoint will be constructed on the footprint of the existing one.  In addition, the Study Area is located on former wetland/marine mud and is now surrounded by ponds.

 

Section 2

 

Proposed Secondary Boundary Fence along Existing Boundary Patrol Road at Lok Ma Chau

 

8.6.3              The Study Area will have direct impacts from the proposed works.  However, the proposed alignment has already been disturbed during the construction of the existing Boundary Patrol Road.  In addition, the Study Area is located on former wetland/marine mud and is now surrounded by ponds.

 

Existing Boundary Fence to be removed (from Lok Ma Chau to Ng Tung River)

 

8.6.4              No impacts on underground deposits are anticipated from the proposed work.

 

Proposed new Boundary Patrol Road with Primary and Secondary Boundary Fences (North of the Lok Ma Chau Loop and Hoo Hok Wai)

 

8.6.5              The Study Area will have direct impacts from the proposed works.  However, the proposed alignment is situated on an existing man-made river embankment/ road, which follows the canalised Shenzhen River.  The embankment/ road was filled and constructed by DSD in the late 1990s.  As well, the study area is located on former wetland and marine mud, and is now surrounded by ponds.

 

Existing Lok Ma Chau Checkpoint to be removed

 

8.6.6              No impacts on underground deposits are anticipated from the proposed work.

 

Section 3

 

Proposed Secondary Boundary Fence along Existing Boundary Patrol Road (Lo Wu to Lin Ma Hang)

 

8.6.7              The Study Area will have direct impacts from the proposed works.  However, the proposed alignment has already been disturbed during the construction of the existing Boundary Patrol Road.  In addition, the Study Area is located on former wetland/marine mud and is now surrounded by ponds.

 

Existing Boundary Fence to be removed (at Pak Fu Shan area)

 

8.6.8              No impacts on underground deposits are anticipated from the proposed work.

 

Proposed new Boundary Patrol Road with Primary and Secondary Boundary Fences (Pak Fu Shan)

 

8.6.9              An archaeological survey to confirm the archaeological impact will be conducted after land resumption and before commencement of construction works.

 

Proposed new Boundary Patrol Road with Primary and Secondary Boundary Fences  (Lin Ma Hang)

 

8.6.10           An archaeological survey to confirm the archaeological impact will be conducted after land resumption and before commencement of construction works.

 

Existing Sha Ling Checkpoint to be removed

 

8.6.11           No impacts on underground deposits are anticipated from the proposed work.

 

 

Existing Ping Che Checkpoint to be removed

 

8.6.12           No impacts on underground deposits are anticipated from the proposed work.

 

Section 4

 

Proposed Secondary Boundary Fence along Existing Boundary Patrol Road (Sha Tau Kok)

 

8.6.13           The Study Area will have direct impacts from the proposed works.  However, the proposed alignment has already been disturbed during the construction of the existing Boundary Patrol Road. 

 

Proposed ‘Gate One’ Checkpoint at Sha Tau Kok

 

8.6.14           The Study Area will have direct impacts from the proposed works.  However, the proposed alignment has already been disturbed during the construction of the existing Boundary Patrol Road and the potential of finding in situ archaeological deposits is limited.

 

Existing Shek Chung Au Checkpoint to be removed

 

8.6.15           No impacts on underground deposits are anticipated from the proposed work.

 

Operational Phase

 

8.6.16           There will be no impacts to archaeological resources during the operational phase for all Study Areas.

 

Built Heritage

 

Construction Phase

 

8.6.17           The proposed works in the vicinity of the identified resources will only involve the removal and/ or construction of new boundary control fences along existing roads. As such, the impacts be limited to works areas where machinery and construction activities could cause damage to structures through direct contact. Details of the proposed works are provided below.

 

Section 1

 

8.6.18           The works associated with this section will not have adverse impact on any built heritage resources.

 

Section 2

 

8.6.19           The works that are located in the vicinity of built heritage resources (BF-HB1 and BF-G1) will involve the removal of the existing boundary fence along the existing Boundary Patrol Road.

 

·         BF-HB1: The shrine is located approximately 34 metres from the existing fence. If any works are in close proximity to the shrine it could be damaged. Also, safe public access to the shrine could be restricted by the construction works.

 

·         BF-G1: The grave is situated in close proximity to the alignment and may be damaged by any construction works in close proximity. Also, safe public access to the grave may be restricted by the construction works.

 

Section 3

 

8.6.20           The works in the vicinity of built heritage resources will involve the construction of a secondary boundary fence along the existing Boundary Patrol Road (BF-HB2 and HB3) and removal of the existing boundary fence (BF-G2).

 

·         BF-HB2 and HB3: The ruins are located at approximately 50 metres from the proposed works and will not be adversely impacted by the construction works.

 

·         BF-G2: The grave is situated in close proximity to the alignment and may be damaged by any construction works in close proximity. Also, safe public access to the grave may be restricted by the construction works.

 

Section 4

 

8.6.21           The works in the vicinity of the built heritage resource (BF-HB4) will involve the construction of a secondary boundary fence along the existing Boundary Patrol Road.

 

·         BF-HB4: The structure is located approximately 50 metres from the proposed construction works and this distance will provide an adequate buffer zone to ensure that the building will not be adversely impacted during the construction phase.

 

Operational Phase

 

8.6.22           There will be no impacts from sections of fence to be removed. The construction of a boundary fence may cause visual impacts to sensitive heritage structures.

 

Removal of Existing Fence

 

8.6.23           The removal of an existing fence and this will provide beneficial impacts to the currently existing environment, as the removal of the fence will return the area to a more natural setting. Resources to be beneficially impacted are BF-HB1, BF-G1 and BF-G2.

 

Construction of Fence

 

8.6.24           The fence construction will be approximately 50 metres from the nearest identified resource.

 

·         BF-HB2 and HB3: The fence construction will have no impact on the resources, as the buildings are located in a village area that was abandoned over 40 years ago and consist of unused (it was confirmed on the site visit that the former occupants do not maintain family shrines or utilise the buildings in any way) and un-maintained ruinous shells of buildings with no heritage value apart from marking the location of the original Chuk Yuen Village. Hence, the setting of the ruins will not be adversely impacted by the construction of the fence.

 

·         BF-HB4: The building is situated at the base of the existing boundary patrol road (with boundary fence). The presence of the proposed fencing will not adversely impact on the existing environment of the structure.

 

8.7                   Mitigation Recommendations

 

Archaeological Resources

 

8.7.1              Since Pak Fu Shan and Lin Ma Hang Study Areas are evaluated as having some archaeological potential, archaeological survey with an aim to confirm the archaeological impact is required. Since part of those areas cannot be accessed currently, the proposed survey will be carried out after land resumption and before commencement of construction works.

 

8.7.2              If the archaeological survey has identified that there are archaeological interests in the works area, appropriate mitigation measures should be designed and implemented, such as:.

 

·         Preservation in situ

 

·         Full-scale excavation prior to construction works

 

·         Archaeological monitoring, whereby a professional archaeologist monitors the excavation works in area of archaeological interests in the course of excavation.

 

8.7.3              The project proponent should design and implement the mitigation measures in consultation with the Antiquities and Monuments Office.

 

Construction Phase

 

8.7.4              Based on the findings of the baseline study, no mitigation measures are required within the Study Areas, except the proposed new boundary road alignments at Pak Fu Shan and Lin Ma Hang of Section 3. An archaeological survey should be conducted at both areas after land resumption and before commencement of construction works.

 

Operational Phase

 

8.7.5              No mitigation measure is required for all Study Areas.

 

Built Heritage Resources

 

Construction Phase

 

8.7.6              The following resources have been found to have the potential to be adversely impacted by the proposed construction works if mitigation measures are not implemented:

 

·         BF-HB1: A buffer zone of a minimum distance of 1 metres should be established between the shrine and any construction works in close proximity. The buffer zone should be marked out by temporary fencing. Safe public access should be provided to the shrine during any construction works in close proximity.

 

·         BF-G1 and BF-G2: A buffer zone of a minimum distance of 1 metres should be established between the graves and any construction works in close proximity. The buffer zone should be marked out by temporary fencing. Safe public access should be provided to the graves during any construction works in close proximity.

 

Operational Phase

 

8.7.7              No adverse impacts will occur during the operational phase of the project and no mitigation will be required.

 

8.8                   Conclusion

 

Archaeological Resources

 

8.8.1              Based on the findings of the baseline study, no mitigation measures are required within the Study Area, except the proposed new boundary road alignment at Pak Fu Shan and Lin Ma Hang of Section 3 which are evaluated as having some archaeological potential. As part of those areas cannot be accessed currently, an archaeological survey should be undertaken after land resumption and before commencement of construction works. It is anticipated that no adverse impacts to archaeological resources will be caused during the operational phase for all Study Areas.

 

Built Heritage Resources

 

8.8.2              No major adverse impacts have been identified as arising from the proposed project. Minor impacts may occur during the construction phase to resources in close proximity to the proposed construction works. No adverse impacts are expected to arise during the operational phase of the project. Mitigation in the form of buffer zones and safe public access have been proposed for one shrine (BF-HB1) and two graves (BF-G1 and G2). The project will not cause any insurmountable impacts to built heritage resources if the mitigation measures as recommended are properly implemented.

 

8.9                   References

 

AMO Files: AM001607

 

Agreement No. PLNG 13/2007  Survey on Features with Cultural Heritage Value in Sha Tau Kok, Ta Kwu Ling and Ma Tso Lung Areas (Draft Final Report) ERM 2007.

 

Archaeological Assessments Ltd. 2005.  Agreement No. CE20/2004 (EP), NENT Landfill Extension – Feasibility Study, CHIA (unpublished report)

 

Archaeological Assessments Ltd. 2005.  Northeast New Territories Village Sewerage:  Archaeological Monitoring and Condition Survey.  (unpublished report)

 

ERM 2001.  Agreement No. CE64/96, Planning and Development Study on NENT, CHIA. (unpublished report)

 

Geotechnical Engineering Office 1988.  Geotechnical Area Studies Programme: North New Territories.  Hong Kong: Government of Hong Kong.

 

Geotechnical Engineering Office 1996.  Hong Kong Geological Survey Memoir No.5: Geology of the Northeastern New Territories.  Hong Kong: Government of Hong Kong.

 

HKIA 2001.  The 2000 Archaeological Survey & Assessment for Shenzhen River Regulation Project Stage III.  (unpublished report)

 

HKIA 2006.  Archaeological Survey at Wang Lek near Lin Ma Hang Road. (unpublished report)

 

HKIA 2002.  The 2001 Archaeological Survey & Assessment for the Proposed NENT Landfill Extension (Final Report).  (unpublished report)

 

HKIA 2003.  Rescue Excavation at Yuen Leng Tsai.  (unpublished report)

 

Hong Kong Geological Survey 1988.  San Tin Sheet 2: Solid and Superficial Geology Map.  Hong Kong: Geotechnical Control Office, Civil Engineering Services Department.

 

Hong Kong Geological Survey 1988.  Sheung Shui Sheet 3: Solid and Superficial Geology Map.  Hong Kong: Geotechnical Control Office, Civil Engineering Services Department.

 

List of Declared Monuments in Hong Kong as at 11 July 2008 (Antiquities and Monuments Office Leisure and Cultural Services Department Website)

 

List of Graded Historic Buildings in Hong Kong (as at May 2008)

 

List of Government Historic Sites in Hong Kong (as at 7 December 2007)

 

Peacock, B.A.V. and Nixon, T.J.P 1986. Report of the Hong Kong Archaeological Survey (unpublished report, AMO, Ref. No. ID5)

 

 

 

 

 


9                        SUMMARY OF ENVIRONMENTAL OUTCOMES

 

9.1                   Overall

 

9.1.1              This section summarises the environmental outcomes associated with the construction and operation of the Project.  The EIA process has facilitated integration of environmental considerations into the design process for the Project. One of the key environmental outcomes has been the ability to plan, design and ultimately construct the Project so that direct impacts to sensitive receivers are avoided, as far as practically possible. The mitigation measures are detailed in the Implementation Schedule of Environmental Mitigation Measures in Section 11.

 

9.2                   Air Quality

 

9.2.1              Air quality impacts resulting from the construction works of the Project are not anticipated be significant to air sensitive receivers.

 

9.2.2              Gaseous emissions from the operation of the secondary boundary fence and the new boundary patrol roads are considered to be insignificant, no air quality impact will be anticipated during the operational phase.

 

9.3                   Noise

 

9.3.1              The potential noise impact that could arise from daytime construction/ demolition activities of the Project has been evaluated.  With the use of quiet plant, the movable noise barriers and alternative demolition method, all the construction noise impact can be mitigated to acceptable levels.  The Contractor shall, from time to time, be aware of the noise impacts on the surrounding NSRs through adequate noise monitoring during the works so that adjustments could be made to control the construction noise levels.  These requirements should be triggered by an Event and Action Plan as part of the EM&A which should be incorporated in the works contract in order to make it enforceable.

 

9.3.2              During the operational phase, the road traffic noise generated from the newly constructed Border Road is predicted remaining unchanged to the existing scenario as there are mainly police patrol cars and maintenance cars (e.g. WSD, DSD etc.) travelling along the boundary patrol road.  A worst-case assumption of road traffic flow and the percentage of heavy vehicle has been adopted in the prediction, it is concluded that potential road traffic noise impact would comply with the noise criteria stipulated in the EIAO-TM.

 

9.4                   Water Quality

 

9.4.1              Water quality impacts are not anticipated in both construction and operational phases.

 

9.5                   Waste Management

 

9.5.1              Impacts associated with waste are not anticipated in both construction and operational phases.

 

9.6                   Ecology

 

9.6.1              Potential ecological impacts during construction and operational stages are considered acceptable given that recommended mitigation measures are fully implemented.

 

9.7                   Landscape and Visual

 

9.7.1              The potential landscape and visual impacts during the construction and operational stages are considered to be acceptable given the full implementation of the proposed mitigation measures. This is largely due to the proposed alignment of the SBF will closely follow the alignment for the existing boundary fence for much of its length and so the impacts on the landscape resources and character and visual amenity available to VSRs are not likely to be significant. In addition the movement of the fence to follow the new red alignment in some locations will benefit the landscape character of these areas and improve the visual amenity available to the adjacent villagers.    

 

9.8                   Cultural Heritage

 

9.8.1              No adverse impacts towards built heritage resources are anticipated in both construction and operational phase.

 

9.8.2              No adverse impacts towards archaeology in the opertiaonl phase are anticipated.

 

9.8.3              For the proposed new boundary road alignment at Pak Fu Shan and Lin Ma Hang of Section 3, an archaeological survey will be conducted after land resumption and before commencement of construction works to confirm the archaeological impact.

 

 

 


10                    ENVIRONMENTAL MONITORING AND AUDIT (EM&A) REQUIREMENTS

 

10.1.1           The Project mainly comprises the construction of an SBF along the southern edge of the existing BPR (approximately 21.7km) from west (Pak Hok Chau) to east (Sha Tau Kok).  For sections where the existing PBF runs along the southern edge of the BPR, a new fence with sensor alarm system will be constructed on the northern edge of the BPR as part of the PBF whereas the existing PBF will become the SBF.  The project also includes the conversion of the existing maintenance services road along the Shenzhen River bank to the north of the Lok Ma Chau Loop and Hoo Hok Wai into a new section of the BPR with a PBF and an SBF; and construction of two new sections of the BPR with a PBF and an SBF along the Shenzhen River side to the north of Pak Fu Shan and northwest of Lin Ma Hang Village.  In addition, the Project includes the construction of a checkpoint at the entrance to the Sha Tau Kok town (i.e. location of “Gate One”) and replacement of the existing checkpoint at Pak Hok Chau, removal of the existing checkpoints at Lok Ma Chau, Sha Ling, Ping Che and Shek Chung Au, and removal of the existing PBF along those sections of the existing BPR which will be replaced by new sections of the BPR.

 

10.1.2           A detailed EM&A Manual has been prepared for this project under a separate cover as part of the EIA study.  The following sections provide a summary of the need for monitoring and auditing of the individual environmental aspects.

 

10.1.3           In accordance with the requirements in Section 3.4.9.3 of the EIA Study Brief, an Implementation Schedule of the environmental mitigation measures recommended in the EIA study has been prepared in form of a checklist.  The Implementation Schedule is presented in Section 11 and also given in the EM&A Manual under a separate cover.

 

10.2               Air Quality

 

10.2.1           Full compliance with the air quality criteria will be achieved at all ASRs with the implementation of dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation. Dust monitoring is considered not necessary during the construction phase but weekly site audits are required to ensure that the dust control measures are properly implemented. No operational monitoring is considered to be necessary for this project.

 

10.3               Noise Impact

 

10.3.1           Environmental monitoring and audit is recommended to ensure that the noise levels do not exceed the criteria during the construction/ demolition activities as discussed in the EM&A Manual especially in recognition of the close proximity of the village type house along the boundary fence.  No operational monitoring is recommended.

 

10.4               Water Quality

 

10.4.1           Water quality impacts during the construction phase will be controlled through the implementation of good site practice. With appropriate mitigation and precautions measures in place during construction, there should be relatively minor impacts associated with this project. In the operation phase, the impact from sanitary facilities is anticipated to be negligible. No construction and operational monitoring is recommended.

 

10.5               Waste Management

 

10.5.1           Auditing of each waste stream is recommended to be carried out periodically during the construction phase to determine if wastes are being managed in accordance with approved procedures.  A site waste management plan will be prepared by the Contractor to define the waste management procedures and protocols.  The audits will examine all aspects of waste management including waste generation, storage, recycling, treatment, transport and disposal and would be conducted on a monthly basis or more frequently if required.

 

10.6               Ecology

 

10.6.1           Good site practices for checking air, noise and water quality are considered necessary to control potential impacts on adjacent habitats. Regular checking on the proposed protection measures for plant species of conservation concern shall be conducted as part of the routine site inspection during construction period. Avoidance of particular construction activities during the bird migratory season and ardeid breeding season should be strictly followed to avoid potential disturbance to the wetland dependent birds of conservation concern and egretry respectively.

 

10.7               Landscape and Visual

 

10.7.1           Good site practices shall be employed including the protection of the existing trees and the monitoring of the works in terms of minimising potential; landscape and visual impacts. The progress of the engineering works should be regularly reviewed on site to identify the earliest practical opportunities for the landscape works to be undertaken.

 

10.7.2           A specialist Landscape Sub-Contractor should be employed by the Contractor for the implementation of landscape construction works and subsequent maintenance operations during the 12 month establishment period.  It is proposed that the planting works be phased to coincide with the completion of each of the sections of the SBF and SBP so as to ensure that the affects of the mitigation measures are apparent at the earliest possible time. A minimum 12 month establishment period will be allowed for the planting works.

 

10.8               Cultural Heritage

 

10.8.1           Based on the findings of the baseline study, no mitigation measures are required within the Study Area, except the proposed new boundary road alignment at Pak Fu Shan and Lin Ma Hang of Section 3 which are evaluated as having some archaeological potential. As part of those areas currently cannot be accessed, an archaeological survey should be undertaken after land resumption and before commencement of construction works.

 

 

 


11                    PROJECT IMPLEMENTATION SCHEDULE

 

EIA Ref.

 

EM&A Log Ref.

Recommended Mitigation Measures

 

Objectives of the Recommended Measures & Main Concerns to address

 

Who to implement the measure?

Location of the measure

When to implement the measure?

What requirements or standards for the measure to achieve?

Air Quality

 

During Construction

2.5.2

3.2.2

The following good site practice should be implemented:

·       any excavated dusty materials or stockpile of dusty materials should be covered entirely by impervious sheeting or sprayed with water so as to maintain the entire surface wet, and recovered or backfilled or reinstated within 24 hours of the excavation or unloading;

To minimize construction dust impact

Contractor

Construction Work Sites

During Construction

EIAO-TM, Air Pollution Control

(Construction Dust)

Regulation

 

 

·       the working area of excavation should be sprayed with water immediately before, during and immediately after the operations so as to maintain the entire surface wet;

 

 

 

 

 

 

 

·       dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting;

 

 

 

 

 

 

 

·       the area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should paved with concrete, bituminous materials or hardcores;

 

 

 

 

 

 

 

·       the portion of road leading only to a construction site that is within 30m of designated vehicle entrance or exit should be kept clear of dusty materials;

 

 

 

 

 

 

 

·       all dusty materials should be sprayed with water prior to any loading, unloading or transfer;

 

 

 

 

 

 

 

·       vehicle speed should be limited to 10kph except on completed access roads;

 

 

 

 

 

 

 

·       every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites.

 

 

 

 

 

Noise

During Construction

3.8.14

4.8.1

The following good site practical should be implemented:

 

·       The Contractor shall adopt the Code of Practice on Good Management Practice to Prevent Violation of the Noise Control Ordinance (Chapter 400) (for Construction Industry) published by EPD;

To mitigate construction noise impact

Contractor

 

Construction Work Sites

During Construction

EIAO-TM, NCO

 

 

 

 

 

 

 

 

 

 

·       The Contractor shall observe and comply with the statutory and non-statutory requirements and guidelines;

 

 

 

 

 

 

 

·       Before commencing any work, the Contractor shall submit to the Engineer Representative for approval the method of working, equipment and noise mitigation measures intended to be used at the site;

 

 

 

 

 

 

 

·       The Contractor shall devise and execute working methods to minimise the noise impact on the surrounding sensitive uses, and provide experienced personnel with suitable training to ensure that those methods are implemented;

 

 

 

 

 

 

 

·       Noisy equipment and noisy activities should be located as far away from the NSRs as is practical;

 

 

 

 

 

 

 

·       Unused equipment should be turned off.  PME should be kept to a minimum and the parallel use of noisy equipment / machinery should be avoided;

 

 

 

 

 

 

 

·       Regular maintenance of all plant and equipment;

 

 

 

 

 

 

 

·       Material stockpiles and other structures should be effectively utilised as noise barriers, where practicable.

 

 

 

 

 

 

3.8.1 -3.8.3

4.8.2 -4.8.3

Other than good site practice, the Contractor is required to adopt Levels 1 and 2 site-specific direct mitigation measures as specified below during the construction phase.

 

With construction / demolition work undertaken at a distance of 60m or less to the NSRs, below mitigation measures should be included:

 

Level 1 – Use of Quiet Plant and Movable Noise Barrier

·       The Contractor shall obtain particular models of plant that are quieter than standards given in GW-TM. 

·       Purpose-built movable noise barriers should be used to mitigate construction noise directly at sources that are not usually mobile provide that the direct line of sight to the source is blocked.   

To mitigate construction noise impact

Contractor

 

Construction work sites, Figure 3.9 shows the typical section

of movable

noise barrier

During construction

EIAO-TM, NCO

 

3.8.9

4.8.4

In addition to the use of quiet plant and movable noise barrier, alternative demolition method of existing boundary fence at Section 2-3 shall be used where demolition works would be undertaken at a distance of 12m or less to the NSRs. These particular mitigation measures should be included:

 

Level 2 – Alternative Demolition Method of Existing Boundary Fence

·       The use of welder is recommended to replace the use of hand-held driller;

·       The use of hand-held breaker with movable noise barrier is recommended to replace the use of mini-robot mounted breaker; and the duration for the use of hand-held breaker is minimal as only the surface level of the footing to be broken; and

·       The removal of the footing of the existing boundary fence should be carried by concrete crusher mini-robot mounted after the surface level broken by hand-held breaker.

 

To mitigate construction noise impact for demolition of existing boundary fence

 

Contractor

 

Construction work sites (Section 2 - 3)

Before the commencement of demolition works

EIAO-TM, NCO

 

Water Quality

During Construction 

4.7.1

5.3.1

Good site practices in addition to the implementation of mitigation measures would minimize the impact to the surrounding environment.

To avoid site runoff and chemical leakage

Contractor

 

Construction work sites

During construction

Practice Note for Professional Persons with regard to site drainage (ProPECC PN 1/94) and TM standard

under the WPCO

 

 

General Prevention and Precaution Measures

 

 

 

 

 

 

·        The site should be confined to avoid silt runoff to the site.

 

 

 

 

 

 

·        No discharge of silty water into the storm drain and drainage channel within and the vicinity of the site.

 

 

 

 

 

 

·        Any soil contaminated with chemicals/oils shall be removed from site and the void created shall be filled with suitable materials.

 

 

 

 

 

 

·        Stockpiles to be covered by tarpaulin to avoid spreading of materials during rainstorms;

 

 

 

 

 

 

 

·        Suitable containers shall be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport;

 

 

 

 

 

 

 

·        Chemical waste containers shall be labelled with appropriate warning signs in English and Chinese to avoid accidents.  there shall also be clear instructions showing what action to take in the event of an accidental;

 

 

 

 

 

 

 

·        Storage areas shall be selected at safe locations on site and adequate space shall be allocated to the storage area;

 

 

 

 

 

 

·        Any construction plant which causes pollution to the water system due to leakage of oil or fuel shall be removed off-site immediately;

 

 

 

 

 

 

 

·        Spillage or leakage of chemical waste to be controlled by using suitable absorbent materials;

 

 

 

 

 

 

 

·        Chemicals will always be stored on drip trays or in bunded areas where the volume is 110% of the stored volume;

 

 

 

 

 

 

 

·        Regular clearance of domestic waste generated in the temporary sanitary facilities to avoid waste water spillage.  

 

 

 

 

 

 

 

·        Temporary sanitary facilities to be provided for on-site workers during construction.  

 

 

 

 

 

4.7.2 – 4.7.3

5.3.2-5.3.3

Concreting Work

A temporary drainage channel and associated facilities should be provided to collect the runoff generated and prevent concrete-contaminated water from entering watercourses. Adjustment of pH can be achieved by adding a suitable neutralising reagent to wastewater prior to discharge.

 

 

The concreting works should be temporarily isolated with proper methods, such as by placing of sandbags or silt curtains with lead edge at bottom and properly supported props.

To collect runoff generated and prevent concrete-contaminated water from entering watercourses

 


To prevent adverse impacts on the water quality of Lin Ma Hang Stream SSSI

Contractor

 

Construction work sites

 

 

 

 

 

Work sites of Section 3 in the proximity of Lin Ma Hang Stream SSSI

During construction

Practice Note for Professional Persons with regard to site drainage (ProPECC PN 1/94) and TM standard under the WPCO

 

CEDD General Specification- Protection of natural streams/rivers- Clause 25.09

4.7.4

5.3.4

Soil Excavation and Stockpiling

Excavated soil which needs to be temporarily stockpiled should be stored in a specially designated area and provided with a tarpaulin cover to avoid runoff into the drainage channels.

To avoid site runoff

Contractor

 

Construction work Sites

During construction

Practice Note for Professional Persons with regard to site drainage (ProPECC PN 1/94) and TM standard under the WPCO

4.7.5 - 4.7.6

5.3.5-5.3.6

Site Depot

All compounds in works areas should be located on areas of hard standing with provision of drainage channels and settlement ponds where necessary to allow interception and controlled release of settled/treated water. Hard standing compounds should drain via an oil interceptor. The oil interceptor should be regularly inspected and cleaned to avoid wash-out of oil during storm conditions. A bypass should be provided to avoid overload of the interceptor's capacity. Any contractor generating waste oil or other chemicals as a result of his activities should register as a chemical waste producer. Disposal of the waste oil should be done by a licensed collector.

 

Good housekeeping practices should be implemented to minimise careless spillage and to keep the storage and the work space in a tidy and clean condition. Appropriate training including safety codes and relevant manuals should be given to the personnel who regularly handle the chemicals on site.

 

 

To avoid wash-out of oil during storm conditions

Contractor

 

Construction work Sites

During construction

Practice Note for Professional Persons with regard to site drainage (ProPECC PN 1/94) and TM standard under the WPCO

4.7.7

5.3.7

Construction of Checkpoint

Sewage system should be constructed to divert domestic sewage, which will be generated from the sanitary facilities provided in the new checkpoint at Shek Chung Au, to public sewer connected to government sewage treatment facilities.

To avoid disposal of domestic sewage into watercourses.

Contractor

Construction work Site at Checkpoint

During construction

N/A

Waste Management

During Construction

5.6.7

6.3.6

Site Clearance

The topsoil and vegetation removed and excavated material may have to be temporarily stockpiled on-site. Control measures should be taken at the stockpiling area to prevent the generation of dust and pollution of stormwater channels, fish ponds or river channels. However, to eliminate the risk of blocking drains in the wet season, it is recommended that stockpiling of excavated materials during the wet season should be avoided as far as practicable.

Prevent the generation of dust and pollution of storm water channels

Contractor

Construction work sites

During construction

Waste Disposal Ordinance (Cap.354); ETWBTC No. 15/2003, Waste Management on Construction Site

 

5.6.10 – 5.6.12

6.3.8

Construction and Demolition Materials

Careful design, planning and good site management can minimize over-ordering and generation of waste materials such as concrete mortars and cement grouts. The design of formwork should maximize the use of standard wooden panels so to achieve high reuse levels. Alternatives such as steel formwork or plastic facing should be considered to increase the potential for reuse.

 

Minimize over-ordering and generation of waste materials

Contractor

Construction work sites

During construction

Waste Disposal Ordinance (Cap.354);  ETWBTC No. 15/2003, Waste Management on Construction Site

 

The Contractor should recycle as much of the C&D materials as possible on-site. Proper segregation of waste on-site will increase the feasibility of certain components of the waste stream by the recycling contractors. Different areas of the worksite shall be designated for such segregation and storage wherever site conditions permit.

 

Trip-ticket system should be employed to monitor the disposal of C&D material and solid at public filling facilities and landfills, and to control fly-tipping. Government has established a differentiated charging scheme for the disposal of waste to landfill, construction waste sorting facilities and public fill facilities. This will provide additional incentives to reduce the volume of waste generated and to ensure proper segregation of wastes.

 

5.6.13-5.6.14

6.3.9 – 6.3.13

Chemical Waste

For those processes which generate chemical waste, it may be possible to find alternatives which generate reduced quantities or even no chemical waste, or less dangerous types of chemical waste.

To avoid chemical leakage

Contractor

Construction work sites

During construction planning

Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes, Waste Disposal (Chemical Waste) (General) Regulation

 

 

 

Chemical waste that is produced, as defined by Schedule 1 of the Waste Disposal (Chemical Waste) (General) Regulation, should be handed in accordance with the Code of Practice on the Packaging, Handling and Storage of Chemical Waste as follows:

 

 

 

 

 

 

Containers used for the storage of chemical wastes should:

 

 

 

 

 

 

 

·       be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed:

 

 

 

 

 

 

 

·       have a capacity of less than 450 litres unless the specification have been approved by the EPD; and

 

 

 

 

 

 

 

·       display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations,

 

 

 

The storage area for chemical wastes should:

 

 

 

·       be clearly labelled and used solely for the storage of chemical waste;

 

 

 

·       be enclosed on at least 3 sides;

 

 

 

 

 

 

·       have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area whichever is the greatest;

 

 

 

 

 

 

·       have adequate ventilation;

 

 

 

 

 

 

 

·       be covered to prevent rainfall entering (water collected within the bund must be tested and disposed as chemical waste if necessary); and

 

 

 

 

 

 

 

·       be arranged so that incompatible materials are adequately separated.

 

 

 

 

 

 

 

Disposal of chemical waste should:

 

 

 

 

 

 

 

·       be via a licensed waste collector; and

 

 

 

 

 

 

 

·       be to a facility licensed to receive chemical waste, such as the Chemical Waste Treatment Facility which also offers a chemical waste collection service and can supply the necessary storage containers, or

 

 

 

 

 

 

 

·       to be re-user of the waste, under approval from the EPD.

 

 

 

 

 

5.6.16

6.3.15

General Refuse

Should be stored in enclosed bins or compaction units separate from C&D and chemical wastes.  The Contractor should employ a reputable waste collector to remove general refuse from the site, separate from C&D and chemical wastes, on a regular basis to minimise odour, pest and litter impacts.  Burning of refuse on construction sites is prohibited by law.

Minimise odour, pest and litter impacts

Contractor

Construction work sites

During construction

Public Health and Municipal Services Ordinance (Cap. 132)

5.6.18

6.3.16

Construction Waste Management Plan

A construction waste management plan (CWMP) should be prepared and developed by the contractor to ensure proper collection, treatment and disposal of waste on site. This CWMP will also take into account the requirement to handle chemical wastes on site which will need to be managed by a licensed waste collection contractor.

Waste management during construction

Contractor

Construction work sites

During construction

ETWB TCW No. 19/2005, Waste Management on Construction Sites

 Ecology

 

Table 6.38

7.2

Ecological Impacts on Floral Species of Conservation Concern

Erection of protective fencing to protect the plant during construction period

Protect the plant during construction period

Contractor

Construction work sites

During construction

EIAO

Table 6.40

7.2

Potential Ecological Impacts on Offsite Habitats

Good site practices for controlling the dust and water quality (avoid stockpiles adjacent to wetlands, covering the stockpiles with impervious sheeting, control of vehicle speed, no discharge of silty water to the rivers, streams and drainage channels);

Clear definition of works limit to avoid impact on adjacent habitats

 

To avoid site runoff and dust impact

Contractor

Construction work sites

During construction

EIAO / Air Pollution Control

(Construction Dust)

Regulation / WPCO

Table 6.39-Table 6.45

7.2

Disturbance to Wetland-Dependent Birds, Raptors, Terrestrial Birds and Egretry

Good working practices include switching off unused equipment, keep minimum number of powered mechanical equipment in operation at the same period, the use of stockpiles and other structures to form noise barriers where practicable, avoidance of feeding the wildlife to cause disturbance, site confinement and proper cover of stockpiles with impervious sheeting to minimize construction noise, uncontrolled surface runoff and discharge of silts;

Avoidance of construction works using Power Mechanical Equipments within the Wetland Conservation Area during bird migratory season (15th November – 15th March); and

Restriction of excavation works within a 150m buffer zone from the egretry to ardeid non-breeding season (from August to February).

To minimize disturbance to wildlife

Contractor

Construction work sites

During construction

EIAO / Air Pollution Control

(Construction Dust)

Regulation / WPCO

Landscape and Visual

 

 

Preservation of Existing Vegetation

Table 7-13

 

CP1

Table 9-1

·        To retain trees that have high amenity or ecology value and contribute most to the landscape and visual amenity of the site and its immediate environs.

 

Preservation of Existing Vegetation

 

Project Landscape Architect / Contractor

Site

Throughout construction phase

 

 

TM-EIA Annex 18, ETWB TCW No. 2/2004 & ETWB TCW No. 3/2006

Table 7-13

 

CP1

Table 9-1

·        Creation of precautionary area around trees to be retained equal to half of the trees canopy diameter. Precautionary area to be fenced.

 

To ensure the success of the tree preservation proposals.

Project Landscape Architect / Contractor

Site

Before

construction phase

commences

TM-EIA

Table 7-13

 

CP1

Table 9-1

·        Prohibition of the storage of materials including fuel, the movement of construction vehicles, and the refuelling and washing of equipment including concrete mixers within the precautionary area.

 

To ensure the success of the tree preservation proposals.

Project Landscape Architect / Contractor

Site

Throughout construction phase

TM-EIA Annex 18, ETWB TCW No. 2/2004 & ETWB TCW No. 3/2006

Table 7-13

 

CP1

Table 9-1

·        Phased segmental root pruning for trees to be retained and transplanted over a suitable period (determined by species and size) prior to lifting or site formation works which affect the existing rootball of trees identified for retention. The extent of the pruning will be based on the size and the species of the tree in each case.

 

To ensure the success of the tree preservation proposals.

Project Landscape Architect / Contractor

Site

Throughout construction phase

TM-EIA Annex 18, ETWB TCW No. 2/2004 & ETWB TCW No. 3/2006

Table 7-13

 

CP1

Table 9-1

·        Pruning of the branches of existing trees identified for transplantation and retention to be based on the principle of crown thinning maintaining their form and amenity value.

 

To ensure the success of the tree preservation proposals.

Project Landscape Architect / Contractor

Site

Throughout construction phase

TM-EIA Annex 18, ETWB TCW No. 2/2004 & ETWB TCW No. 3/2006

Table 7-13

 

CP1

Table 9-1

·        The watering of existing vegetation particularly during periods of excavation when the water table beneath the existing vegetation is lowered.

 

To ensure the success of the tree preservation proposals.

Project Landscape Architect / Contractor

Site

Throughout construction phase

TM-EIA Annex 18, ETWB TCW No. 2/2004 & ETWB TCW No. 3/2006

Table 7-13

 

CP1

Table 9-1

·     The rectification and repair of damaged vegetation following the construction phase to it’s original condition prior to the commencement of the works or replacement using specimens of the same species, size and form where appropriate to the design intention of the area affected

To ensure the success of the tree preservation proposals.

Project Landscape Architect / Contractor

Site

Throughout construction phase

Annex 18, ETWB TCW No. 2/2004 & ETWB TCW No. 3/2006

Table 7-13

 

CP1

Table 9-1

·     All works affecting the trees identified for retention and transplantation will be carefully monitored.  This includes the key stages in the preparation of the trees, the implementation of protection measures and health monitoring through out the construction period

To ensure the success of the tree preservation proposals.

Project Landscape Architect / Contractor

Site

Throughout construction phase

TM-EIA Annex 18, ETWB TCW No. 2/2004 & ETWB TCW No. 3/2006

Table 7-13

 

CP1

Table 9-1

·     Detailed landscape and tree preservation proposals will be submitted to the relevant government departments for approval under the lease conditions and in accordance with ETWB TCW No. 2/2004 and WBTC No. 3/2006.

To ensure the tree preservation and planting proposals are integrated with the existing landscape context and that the landscape resources are preserved where appropriate.

 

Project Landscape Architect / Contractor

Site

Throughout construction phase

TM-EIA Annex 18, ETWB TCW No. 2/2004 & ETWB TCW No. 3/2006

Table 7-13

 

CP1

Table 9-1

·     The tree preservation works should be implemented by approved Landscape Contractors and inspected and approved on site by a qualified Landscape Architect. A tree protection specification would be included within the contract documents.

To ensure the tree preservation and planting proposals are integrated with the existing landscape context and that the landscape resources are preserved where appropriate.

 

Contractor

Site

Throughout construction phase

TM-EIA Annex 18, ETWB TCW No. 2/2004 & ETWB TCW No. 3/2006

 

 

Preservation of Existing Topsoil

Table 7-13

 

CP2

Table 9-1

·     Topsoil disturbed during the construction phase should be tested using a standard soil testing methodology and where it is found to be worthy of retention stored for re-use.

To provide a viable growing medium suited to the existing conditions and reduce the need for the importation of top soil.

Contractor

Site

Throughout construction phase

TM-EIA

Annex 18

Table 7-13

 

CP2

Table 9-1

·     The soil will be stockpiled to a maximum height of 2m and will be either temporarily vegetated with hydroseeded grass during construction or covered with a waterproof covering to prevent erosion.

To provide a viable growing medium suited to the existing conditions and reduce the need for the importation of top soil.

Contractor

Site

Throughout construction phase

TM-EIA

Annex 18

Table 7-13

 

CP2

Table 9-1

·        The stockpile should be turned over on a regular basis to avoid acidification and the degradation of the organic material, and reused after completion. Alternatively, if this is not practicable, it should be considered for use elsewhere, including other projects.

To provide a viable growing medium suited to the existing conditions and reduce the need for the importation of top soil.

Contractor

Site

Throughout construction phase

TM-EIA

Annex 18

 

 

Permanent and Temporary Works Areas

 

 

 

 

 

Table 7-13

 

CP3

Table 9-1

·        Where appropriate to the final design the landscape of these works areas should be restored following the completion of the construction phase.

To minimise the disturbance to existing landscape resources and change of visual amenity.

Contractor

Site

Through out construction phase

TM-EIA

Annex 18

Table 7-13

 

CP3

Table 9-1

·        Construction site controls should be enforced including the storage of materials, the location and appearance of site accommodation and the careful design of site lighting to prevent light spillage.

To minimise the disturbance to existing landscape resources and change of visual amenity.

Contractor

Site

Through out construction phase

TM-EIA

Annex 18

 

 

Mitigation Planting

Table 7-13

 

CP4

Table 9-1

·        Replanting of disturbed vegetation should be undertaken at the earliest possible stage of the construction phase

To minimise the disturbance to existing landscape resources and change of visual amenity.

Contractor

Site

Through out construction phase

TM-EIA

Annex 18

Table 7-13

 

CP4

Table 9-1

·        Use of native plant species predominantly in the planting design for the buffer areas.

To minimise the disturbance to existing landscape resources and change of visual amenity.

Contractor

Site

Through out construction phase

TM-EIA

Annex 18

Table 7-13

 

CP4

Table 9-1

·        The tree planting works should be implemented by approved Landscape Contractors and inspected and approved on site by a qualified Landscape Architect. A tree planting specification would be included within the contract documents.

To minimise the disturbance to existing landscape resources and change of visual amenity.

Contractor

Site

Through out construction phase

TM-EIA

Annex 18

 

 

Transplantation of Existing Trees

Table 7-13

 

CP5

Table 9-1

·        The tree transplanting works should be implemented by approved Landscape Contractors and inspected and approved on site by a qualified Landscape Architect. A tree protection / transplanting specification would be included within the contract documents.

To minimise the disturbance to existing landscape resources and minimize the impacts on the visual amenity of the area.

Contractor

Site

Prior to the commencement of the proposed works

TM-EIA

Annex 18, ETWB TCW No. 2/2004 & ETWB TCW No. 3/2006

 

 

Operational Phase

 

 

Design of the Fence and associated Structures

Table 7-14

 

OP1

Table 9-2

·        Design of Boundary Fence, Boundary Patrol Road and Police Check Point – These structural elements will be designed in accordance with security requirement from Police Force and  incorporate design features as part of design mitigation measures including:

Responsive design to integrate the proposals into their landscape and visual context.

ArchSD

Site

Throughout design phase

TM-EIA

Annex 18 and BD

 

 

  1. Integrated design approach – the boundary fence should integrated, as far as technically feasible, with existing built structures such as existing road, footpath and track and embankment of  fishponds, river and drainage channel as part of design mitigation measures to reduce the potential cumulative impact of the proposed works. The location and orientation of the police check points should be away from landscape and visually sensitive areas such wetland, fishpond and agricultural field.

 

 

 

 

 

 

 

2.        Building massing - the proposed use of simple responsive design for the built structures with a low building height profile to reduce the potential visual mass of the structure within a rural context.

 

 

 

 

 

 

 

3.        Treatment of built structures - the architectural design should seek to reduce the apparent visual mass of the facilities further through the use of natural materials such as wooden frame, vertical greening or other sustainable materials such as recycled plastic.

 

 

 

 

 

 

 

4.        Responsive building and fence finishes - In terms of the proposed finishes natural tones should be considered for the colour palette with non-reflective finishes are recommended to reduce glare effect. The use of colour blocking on the proposed fence could be used to break up the visual mass of the structure.

 

 

 

 

 

 

 

5.        Responsive lighting design – Aesthetic design of architectural and track lighting with following glare design measures:

§  Directional and full cut off lighting is recommended particularly for areas adjacent to existing village to minimise light spillage.

§  Minimise geographical spread of lighting, only applied for safety and security reasons;

§  Limited lighting intensity to meet the minimum safety and operation requirement; and

§  High-pressure sodium road lighting is recommended for more stringent light control reducing spillage and thus visual impacts.

 

 

 

 

 

 

 

Compensatory Planting Proposals

Table 7-14

 

OP2

Table 9-2

·        Utilise native to Hong Kong will be utilized within the buffer planting areas.

Planting will serve to visually integrate the proposals within the existing landscape framework.

Contractor

Site

Throughout design phase

TM-EIA

Annex 18, HKPSG and BD

Table 7-14

 

OP 2 / 3

Table 9-2

·        A qualified or registered landscape architect will be involved in the design, construction supervision and monitoring, and maintenance period to oversee the implementation of the recommended landscape and visual mitigation measures including the tree preservation and landscape works on site.

Provide a linkage with the existing wooded areas creating a more coherent landscape framework whilst also improving the ecological connectivity between existing and proposed woodland habitats.

Contractor

Site

Throughout design phase

TM-EIA

Annex 18, HKPSG and BD

Table 7-14

 

OP 2

Table 9-2

Tree and Shrub Planting – Given the rural nature of the proposed alignment it is recommended that the where possible tree and shrub species which are native to Hong Kong be used. In addition where possible the planting of new trees and shrubs will aim to link together existing woodland areas and small tree groups to improve the connectivity between habitats and create more coherent landscape framework. The planting of small groups of trees along the alignment of the proposed fence will serve to de-emphasise the horizontality of the fence structure and provide for better sense of visual integration with the landscape context. Where practicable vertical greening measures should also be considered on engineering structures.

The planting proposal seeks to compensate for the predicted tree loss.

Contractor

Site

Throughout design phase

TM-EIA

Annex 18, HKPSG and BD

Table 7-14

 

OP 3

Table 9-2

Compensatory Planting Proposals – Given the works extent is largely limited along existing roadside embankment to minimise impact to existing village settlements and valuable landscape resources such as wetland, fishpond, stream course and existing trees, and considered the importance of tree retention within the works area, new tree planting will concentrate in selected new amenity areas along the alignment, infilling between retained and transplanted trees. The preliminary planting proposals for the proposed works include the planting of some 357 new trees utilising a combination of mature to light standard sized stock (i.e. approximately 15% of mature trees, 75% of standard trees, and 10% light standard trees). These trees will be planted in woodland clumps and small tree groups at strategic locations to de-emphasise the horizontality of the fence alignment. Based on preliminary findings the proposed planting will result in a compensatory planting ratio of 1:1 (new planting: trees recommended for felling). This compares favourably with the report's assertion that some 357 trees would be felled due to the proposed works. With the proposed preservation of existing trees, transplantation of trees in conflict with the proposals and the planting of new trees the project area will contain approximately 2000 trees. Trees forming part of the new planting will provide screening to neighbourhood villagers and will utilise species native to Hong Kong. These proposals will be subject to review at detailed design stage of the project.

The planting proposal seeks to compensate for the predicted tree loss.

Contractor

Site

Throughout design phase

TM-EIA

Annex 18, HKPSG and BD

Cultural Heritage

During Construction

 

 

 

 

 

 

 

 

8.7.1 – 8.7.4

8.1.1 – 8.1.4

An archaeological survey should be undertaken at the study areas of Pak Fu Shan and Lin Ma Hang of Section 3 after land resumption and before commencement of construction works

Assess the archaeological impact on the two identified sites of archaeological potential.

Contractor

(through professional archaeologist)

the study areas of Pak Fu Shan and Lin Ma Hang of Section 3

after land resumption and before commencement of construction works

Antiquities and Monuments Ordinance /

EIAO

8.7.6

8.2.1

Built Heritage Resources

Mitigation in the form of buffer zones and safe public access have been proposed for one shrine (BF-HB1) and two graves (BF-G1 and G2)

 

BF-HB1

A buffer zone of a minimum distance of 1 metre should be established between the shrine and any construction works in close proximity. The buffer zone should be marked out by temporary fencing. Safe public access should be provided to the shrine during any construction works in close proximity.

 

BF-G1 and BF-G2

A buffer zone of a minimum distance of 1 metre should be established between the graves and any construction works in close proximity. The buffer zone should be marked out by temporary fencing. Safe public access should be provided to the graves during any construction works in close proximity.

 

Avoid impacts to built heritage resources

Contractor

The works that are located in the vicinity of built heritage resources (BF-HB1 and BF-G1 and G2)

During Construction

EIAO

 

 

 


12                SUMMARY AND CONCLUSIONS

 

12.1               Summary

 

12.1.1           The impacts associated with the construction and operation of the Project are assessed according to the criteria listed in Annexes of the Technical Memorandum on Environmental Impact Assessment Process (TMEIA). The major potential impacts during construction and operation associated with the boundary fences are assessed.

 

12.2               Conclusions

 

12.2.1           The conclusions of the technical assessments are described below.

 

Air Quality

 

12.2.2           The dust control requirements of the Air Pollution Control (Construction Dust) Regulation will be followed to control the dust emission arising from the construction activities. It is expected no adverse impact to the surroundings or nearby sensitive receivers. During operational phase, no adverse impact is anticipated

 

Noise Impact

 

12.2.3           During the construction phase, the assessments have demonstrated that there no exceedances of noise criteria provided that the mitigation measures implemented properly. 

 

12.2.4           For the proposed new boundary patrol road near Hoo Hok Wai and Pak Fu Shan, it is anticipated that the road traffic generated would be minimal as there are mainly police patrol cars and maintenance cars (e.g. WSD, DSD etc.) travelling along the boundary patrol road.  A worst-case assumption of road traffic flow and the percentage of heavy vehicle has been adopted in the prediction, it is concluded that potential road traffic noise impact would comply with the noise criteria stipulated in the EIAO-TM.

 

Water Quality Impact

 

12.2.5           Water quality impacts for adjacent natural rivers, streams and fish ponds during the construction phase will be controlled through the implementation of good site practice. During operation, sewers and associated facilities should be provided to collect the domestic waste generated in the sanitary facilities inside the Checkpoints. No adverse water quality impacts are anticipated.

 

Waste Management

 

12.2.6           The construction activities generate waste types include site clearance, C&D material, chemical waste from the maintenance of construction plant and equipment and general refuse from the workforce. Provided that these wastes are handled, transported and disposed of using approved methods and that the recommended good site practices are followed, adverse environmental impacts are not expected during the construction phase.

 

12.2.7           The potential land contamination for this Project is expected to be low. No adverse environmental impacts are expected during operational phase. No site investigations or laboratory testing are proposed.

 

12.2.8           The waste type generated during the operational phase is a small amount of general refuse, which will have no adverse environmental impact.

 

Ecological Impact Assessment

 

12.2.9           An Ecological Impact Assessment had been conducted for the proposed project. Ecological surveys were carried out in November 2007 to October 2008 which covered both wet and dry seasons.

 

12.2.10       A total of 15 habitat types were identified within the Assessment Area, including woodland, shrubland, plantation, gei wai, mangrove, pond, marsh, wet agricultural land, dry agricultural land, abandoned agricultural land / low-lying grassland, hillside grassland, stream / river, drainage channel, open field and developed area.

 

12.2.11       Two individuals of flora species of conservation interest, Berchemia lineata and Aquilaria sinensis were recorded within the Project Area at Section 2 and Section 3 respectively. In-situ preservation and providing protective fencing during construction period are recommended to avoid potential impact on these plants.

 

12.2.12       The construction works at WCA without mitigation measures would have adverse impact on the ecology of the area notably the wetland-depended birds roosting in the Mai Po Nature Reserve and the surrounding fishponds. To avoid the potential disturbance to these ecological sensitive receivers, avoidance of construction works using PMEs in WCA during the wintering period (15th November to 15th March) is recommended.

 

12.2.13       Excavation works at Mai Po during the ardeid breeding season (from 1st March to 31th July) should not be carried out to prevent potential disturbance to the Tam Kon Chau egretry.

 

Landscape and Visual Impact Assessment

 

12.2.14       The potential landscape and visual impacts during the construction and operational stages are considered to be acceptable given the full implementation of the proposed mitigation measures. This is largely due to the proposed alignment of the SBF will closely follow the alignment for the existing boundary fence for much of its length and so the impacts on the landscape resources and character and visual amenity available to VSRs are not likely to be significant. In addition the movement of the fence to follow the new red alignment in some locations will benefit the landscape character of these areas and improve the visual amenity available to the adjacent villagers.

 

Cultural Heritage Impact Assessment

 

12.2.15       Based on the findings of the baseline study, only the proposed new boundary road alignments at Pak Fu Shan and Lin Ma Hang of Section 3 have some archaeological potential. As part of those areas currently cannot be accessed, an archaeological survey should be undertaken after land resumption and before commencement of construction works.

 

12.2.16       No major adverse impacts towards built heritage have been identified. Minor impacts may occur during the construction phase to resources in close proximity to the proposed construction works. No adverse impacts are expected to arise during the operational phase of the project. The project will not cause any insurmountable impacts to built heritage resources if the mitigation measures as recommended are properly implemented.